Missouri Gas Energy v. Public Service Com'n, State of Mo.

Decision Date18 August 1998
Docket NumberNo. WD,WD
Citation978 S.W.2d 434
PartiesUtil. L. Rep. P 26,666 MISSOURI GAS ENERGY, a Division of Southern Union Company, Appellant, v. PUBLIC SERVICE COMMISSION STATE OF MO et al, Respondent. 54710.
CourtMissouri Court of Appeals

W. Stanley Walsh, St. Louis, Gary W. Duffy, Jefferson City, for Appellant.

Roger W. Steiner, Thomas R. Schwarz, Jr., Douglas E. Micheel, Jefferson City, Stuart W. Conrad, Kansas City, for Respondent.

Before ELLIS, LOWENSTEIN and RIEDERER, JJ.

LOWENSTEIN, Judge.

This is an appeal from a final order of the Public Service Commission ("PSC" or "Commission"). The appellant is Missouri Gas Energy ("MGE"). MGE is a subsidiary of Southern Union Company. MGE operates to supply, at the retail level, natural gas in western Missouri. The appellant's business, formerly known as the Gas Service Company, was acquired by KP Western in the early 1990's, and operated as KP Western until 1994 when Southern Union bought the business and established what is now known as MGE. This case emanates from a series of Gas Line Safety Rules ("Rules") promulgated by the PSC in 1989 in response to federal legislation. As the name implies, the Rules required gas utilities to substantially replace all of their older service lines and mains. The effect of this requirement was to cause MGE's predecessor and MGE to incur a new and substantial expense not envisioned by them or accounted for in the then current rates as previously approved by the Commission. During the time that a service or main line construction project is in progress, the utility is allowed to "book a deferred amount," known as the Allowance for Funds Used During Construction ("AFUDC"), which allows the utility to compensate for the financing costs of the project.

When the project is finished, this new figure is an asset of the utility and is eligible to be placed in its rate base, to be depreciated, for the purpose of figuring a rate of return based on this new substantial asset. The temporary problem created is the accounting treatment of the new asset until a new rate, after a hearing and subsequent order by PSC, goes into effect. The Commission has the regulatory authority to grant a form of relief to the utility in the form of an accounting technique, an Accounting Authority Order, (hereinafter called an "AAO") which allows the utility to defer and capitalize certain expenses until the time it files its next rate case. The AAO technique protects the utility from earnings shortfalls and softens the blow which results from extraordinary construction programs. However, AAOs are not a guarantee of an ultimate recovery of a certain amount by the utility.

In this case there was a substantial time lag following construction. Also complicating matters, the utility underwent changes in ownership during this period, and as part of gaining approval of the transfers, the new owners agreed to put off any rate request. During this period the PSC granted two AAOs authorizing a 10.54% rate of return for MGE. When MGE's 1996 rate request was made, the PSC only allowed MGE a rate of return of 4% for 1994 and 6% for 1995 and 1996 on its carrying costs. These figures, which according to PSC equate to MGE's AFUDC rates, will allow less recovery than MGE anticipated.

The long and short of the points raised by MGE is that the treatment afforded it in the two AAOs approved by the Commission was neither made permanent nor incorporated in the same percentages in the ultimate rates approved by the Commission for MGE. It argues that the resulting loss is unfair. The respondent PSC and the intervenor respondent Public Counsel, assert there is no guarantee to a utility in the grant of an AAO that the later rate case will contain the same figures. The circuit court affirmed the action of the Commission, and this appeal followed.

The order of the Public Service Commission has a presumption of validity--the burden is on the appellant to prove invalidity. State ex. rel. Mobile Home Estates, Inc. v. Public Service Com'n, 921 S.W.2d 5, 9 (Mo.App.1996). Judicial review is to determine lawfulness of the order under the statutes, as well as reasonableness of the order and whether it is supported by competent and substantial evidence on the whole record. State ex. rel. Utility Consumers' Council of Missouri, Inc. v. Public Service Com'n, 585 S.W.2d 41, 47 (Mo. banc 1979).

MGE raises seven points in this appeal, some of which are overlapping, but all decry the fact that the degree of relief from the mandated safety expense afforded MGE by the Commission via the AAOs was not reflected in the results of the later rate application. Before entering a discussion of the points, it is helpful to first examine the leading case on Accounting Orders and the effect of AAOs on later rate applications to the PSC.

In State ex. rel. Office of the Public Counsel v. Public Service Com'n of Missouri, 858 S.W.2d 806 (Mo.App.1993), an electric utility sought, and was granted, an accounting authority order to defer depreciation expenses and carrying costs of two of its expensive construction projects. One project would greatly extend the life of a generating site and the other would convert the coal generating station for use of a low-sulfur coal to come into compliance with the Clean Air Act. The PSC, under its statutory authority, adopted an AAO which allowed the utility to defer and record depreciation expenses and carrying costs until subsequent years. Id. at 808 and 811-12. This court upheld the authority of the PSC, as granted by § 393.140, RSMo.1986, to hear an application by a utility and grant to a utility the permission to defer extraordinary expenses from one period to another. The PSC's decision to defer until the rate case, was affirmed by this court on the basis that the costs were both substantial and unusual. Id. at 811. This court specifically stated that by allowing a deferral under an AAO, the PSC was not granting "rate relief" to the utility, and was not determining the "actual amount of the deferred costs" that would be recovered. Instead, the rate decision would "be determined in a later rate case," which the PSC ordered to be filed by the end of the calendar year. Id. at 812. As is applicable to the case at bar, the opinion stated that the AAO, "did not presume to determine a new rate but effectively permitted" the utility to file a rate case by the end of the year, "and then to present evidence and argue that the deferred costs recorded ... should be considered by the Commission in approving a rate change." Id. at 813. The court reiterated the holding that nothing in the AAO order served to automatically entitle the utility to recover in the subsequent rate case the full amount of the deferred charges allowed by the previous AAO. Id.

The relevant events in the case at bar are as follows: (1) in 1989 the PSC granted MGE's predecessor, KP Western, an AAO which authorized a carrying cost rate of 10.96%; (2) in a 1991 rate case the PSC lowered the figure to 10.54%; (3) in 1992 a second AAO was granted which purported to keep the same figure until the next rate case which came in 1993; (4) the 1993 rate case, which was approved by the PSC in 1994, was concluded in a "negotiated settlement" since ownership of this utility was being changed from KP Western to Southern Union; in early 1994 KP Western applied for a third AAO, which was ultimately approved with the 10.54% figure; (5) in 1996 MGE filed the rate case now under review, and the PSC lowered the rate of return to 4% for 1994 and 6% for 1995 and 1996. Again, as stated earlier, MGE's points on appeal contain the central theme that the earlier, higher rate of return was required to be included in the 1997 rate award because of its use in the preceding AAOs. A summary of the points is now set out:

Points I-IV covers matters that would call for reversal and our entering the 10.54% rate.

I The Commission's determination of a carrying cost rate of 10.54% in the earlier Accounting Order was a final order that was binding on the Commission in this action.
II The Commission was "contractually bound" to its prior Order of 10.54%.
III The Commission was "equitably estopped" from reducing the 10.54% Order.
IV The Commission violated the Missouri Constitution, Art. I Section 13, by changing the Accounting Order of 10.54%, which had become vested.

MGE asserts Points V-VII relate to evidentiary matters and would call for a reversal and new hearing.

V The PSC's Order was not explicit in stating why or which staff proposal it was adopting, the staff having proposed three alternatives, the 4% or 6% short term rate, the 10.54% AFUDC rate and the 9.46% rate of return on invested capital.

VI Insufficient competent or substantial evidence in the record to support the PSC's conclusion that the 4% or 6% short term rate was more reflective of MGE's carrying costs than the--10.54% rate approved in the 1994 AAO.

VII The Commission was arbitrary in using the 4% or 6% rate as those figures represented solely its short term cost, and the rule is that short term costs are to be weighted with long term cost (9.46% was an alternative staff proposal on return of long term capital and equity for test year ), and the short term costs amounted to less than ten percent of total capital investment.

I.

This point asserts the 1994 AAO was a final order adopting the 10.54% figure, and that § 386.550 invokes the doctrine of collateral estoppel, since the new figures of 4% and 6%, are a collateral attack on the prior final amount. It is true no one appealed the 1994 AAO. However, it does not follow that the 10.54% figure was then required in this cause, a subsequent rate case. In the Public Counsel case, the court made it clear that AAOs are not the same as ratemaking decisions, and that AAOs create no...

To continue reading

Request your trial
11 cases
  • Office of Pub. Counsel v. Evergy Mo. W., Inc.
    • United States
    • Missouri Court of Appeals
    • July 28, 2020
    ...being considered to set rates to be charged in the future. Id. at 335-36 (citations omitted); see also Mo. Gas Energy v. Pub. Serv. Comm'n , 978 S.W.2d 434, 438 (Mo. App. W.D. 1998) (emphasizing that "AAOs are not the same as ratemaking decisions, and that AAOs create no expectation that de......
  • 257 1999 v. 257 1999 v. Wd56691
    • United States
    • Missouri Court of Appeals
    • December 28, 1999
    ...Ins. Ass'n. v. Director of Revenue, State of Missouri, 742 S.W.2d 141, 143 (Mo. banc 1987)); Missouri Gas Energy v. Public Service Comm'n, State of Missouri, 978 S.W.2d 434, 439 (Mo.App.W.D. 1998). A party relying on the doctrine of estoppel has the burden of proving all of the essential el......
  • State ex rel. Aquila, Inc. v. Pub. Serv. Com'n of State
    • United States
    • Missouri Court of Appeals
    • August 31, 2010
    ...occur outside the "test year" utilized in that future rate case). As we explained in Missouri Gas Energy v. Public Service Commission, 978 S.W.2d 434 (Mo.App. W.D.1998), when a utility incurs extraordinary expenses associated with the acquisition or construction of a new, productive asset,[......
  • Bi-State Dev. Agency of the Missouri-Illinois Metro. Dist. v. Warren
    • United States
    • Missouri Court of Appeals
    • May 21, 2019
    ...injustice will result." Gosal v City of Sedalia , 291 S.W.3d 822, 828 (Mo. App. W.D. 2009) (quoting Mo. Gas Energy v. Pub. Serv. Comm'n , 978 S.W.2d 434, 439 (Mo. App. W.D. 1998) ). "Equitable estoppel is not applicable if it will interfere with the proper discharge of governmental duties, ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT