Myers v. Union Elec. Light & Power Co.
Decision Date | 22 December 1933 |
Citation | 66 S.W.2d 565,334 Mo. 622 |
Parties | R. S. Myers and M. L. Guthrie v. Union Electric Light & Power Company, a Corporation, Appellant |
Court | Missouri Supreme Court |
Appeal from Miller Circuit Court; Hon. R. A. Breuer, Judge.
Reversed and remanded.
Theodore Rassieur, George M. Rassieur and Alfred C Wilson for appellant.
(1) When a written contract requires that performance of work meet certain specifications, as determined by Government engineers, it is a condition precedent to recovery under the contract that the Government engineers approve the work, and plaintiffs are not entitled to recover on their contract when the evidence not only fails to show an approval of the work by the Government engineers, but affirmatively shows that plaintiffs' work was rejected by the Government engineers because the work did not meet the requirements of the specifications contained in the contract. Dinsmore v Livingston County, 60 Mo. 241; Hunt v. Owen Bldg. & Inv. Co., 219 S.W. 138; Berger Mfg. Co. v Crites, 178 Mo.App. 218, 165 S.W. 1163; Heidbrink v. Schaffner, 147 Mo.App. 632, 127 S.W. 418; St. Joseph Iron Co. v. Halverson & Co., 48 Mo.App. 383. (2) The written contract provided for settlement for the area cleared according to engineers' estimates based on measurements made during the progress of the work, and such estimates were made and settlements based thereon accepted without complaint. There being no evidence of fraud or mistake in the estimates so made, it was error to admit the testimony of others as to their estimate or guess as to the total number of acres cleared. Williams v. Ry. Co., 112 Mo. 463, 20 S.W. 631; Chapman v. Railroad Co., 114 Mo. 542, 21 S.W. 858; McGregor v. Ware Construction Co., 188 Mo. 611, 87 S.W. 981; St. Joseph Iron Co. v. Halverson & Co., 48 Mo.App. 383; Eldridge v. Fuhr, 59 Mo.App. 44; Mackler v. Railroad Co., 62 Mo.App. 677; Leffler Bros. v. Lane & Co., 167 N.C. 267, 83 S.E. 463; 9 C. J. 826. (a) An objection to such testimony clearly made need not be repeated to subsequent similar testimony. McKee v. Rudd, 222 Mo. 344, 121 S.W. 312. (3) Instructions are erroneous which entirely ignore the written contract of the parties providing for settlement for the area cleared on the basis of engineers' estimates thereof, which estimates the evidence showed were made and accepted without complaint and which were not impeached by evidence of fraud or mistake. See cases cited supra 2. (4) The acceptance of payments for work done based on engineers' estimates furnished as required by contract estopped plaintiff from disputing the correctness thereof. McGregor v. Ware Construction Co., 188 Mo. 611, 87 S.W. 981.
Baker & Baker and Rubey M. Hulen for respondents.
(1) Contract between plaintiffs and defendant provided a remedy in the event United States Government engineers refused to accept project as completed by plaintiffs. Defendant adopted the remedy, provided by the contract, completed the work to meet United States Government engineers requirements, filed counter claim for expenses incurred, produced evidence in support thereof, issue was submitted to the jury and full allowance made for expenses. (a) Defendant is bound on appeal by theory of case adopted in trial court. Allen v. Meredith 32 S.W.2d 103; Hof v. St. Louis Transit Co., 213 Mo. 445; Hudson v. Wabash, 101 Mo. 13; Packer v. Ry. Co., 265 S.W. 119; Maas v. Moon Motor Car Co., 258 S.W. 50. (b) Evidence offered by plaintiffs, as to acreage cleared, was in accord with contract, received without objection and sufficient to support verdict. 27 Mo. Digest -- Trial 156-62; Davenport v. Electric Co., 242 Mo. 122; Smith v. Ohio Miller Inc. Co., 6 S.W.2d 928: Faulkner v. Western Union Tel. Co., 13 S.W.2d 1092. (2) The contract does not provide for settlement according to "engineers' estimates," but calls for payments twice monthly on "preliminary" inspection of "company's representatives." Wentzel v. Lake Dev. Co., 48 S.W.2d 200; Smith v. Ohio Miller's Mut. Fire Ins. Co., 6 S.W.2d 920; Milling Co. v. Fid. & Cas. Co., 161 Mo.App. 185. (3) The instructions given on behalf of the plaintiffs were proper declarations of law under the pleadings and evidence. Wentzel v. Lake Dev. Co., 48 S.W.2d 199; Meffert v. Lawson, 315 Mo. 1091; Diehl v. Fire Brick Co., 299 Mo. 641, 253 S.W. 984; Barz v. Fleischmann Yeast Co., 271 S.W. 364; Payne v. Railroad Co., 136 Mo. 594; State v. Musick, 101 Mo. 271; State v. Patrick, 107 Mo. 174; State v. Alexander, 119 Mo. 461; State v. Paxton, 126 Mo. 514; State v. Good, 132 Mo. 125; State v. Taylor, 134 Mo. 148; Comstock v. State, 14 Neb. 209; Fullington v. Ozark Poultry Supply Co., 39 S.W.2d 783. (a) Plaintiffs' Instruction 3 was a proper declaration of law. Crapson v. Wallace Bros., 81 Mo.App. 680; Deatherage Lumber Co. v. Snyder, 65 Mo.App. 568; Am. Paper Products Co. v. Carroll, 234 S.W. 800. (4) The record in this case does not show facts constituting estoppel and is not pleaded by the defendant in its answer. Kinloch v. City of St. Louis, 268 Mo. 485.
Hyde, C. Ferguson and Sturgis, CC., concur.
This is an action for a balance of $ 9,941.20 claimed to be due under a contract for clearing timber in the Bagnell Dam reservoir. Defendant set up a counterclaim of $ 1,015.32 for work alleged to have been done by it to complete the contract. Plaintiffs obtained a verdict of $ 8,450. From judgment entered therefor, defendant has appealed.
The contract sued upon was made pursuant to the following advertisement:
The specifications for doing the work were as follows:
"Class A. Clearing will include the area between a line 15' outside of the 660 ft. contour and the 628 ft. contour, according to U.S. Survey datum. In this area all timber, brush and floatable material is to be cut and burned clean. Stumps are to be not more than 12 inches high on up hill side. . . .
staples are to be used when necessary to keep the wire from slipping. . . .
Plaintiffs made a written proposal containing the following statement:
Thereafter, a contract was entered into between plaintiffs and defendant, such parts of which are material to this controversy, and were as follows:
To continue reading
Request your trial-
Vondera v. Chapman
... ... Trower, 297 F. 558; ... Hanson v. Northern States Power Co., 198 198 Minn ... 24, 268 N.W. 642; Serr v. Biwabik, ... Koehring v ... Muemminghoff, 61 Mo. 403; St. Louis Union Trust Co ... v. MacGovern Co., 297 Mo. 527, 249 S.W. 68 ... terms must be given effect. Myers v. Union E.L. & P ... Co., 334 Mo. 622, 66 S.W.2d 565; ... ...
-
Gillioz v. State Highway Com'n
... ... 238; Arey v. DeLoriea, 55 F ... 323; Brown v. Union States, 298 F. 428. (5) It was ... error to admit in ... 598; ... Kuhlman v. Water, Light & Transit Co., 307 Mo. 607; ... State ex rel. v. Daues, ... 463; McCormack v. St ... Louis, 166 Mo. 315; Myers v. Union Electric L. & P ... Co., 66 S.W.2d 565; United ... ...
-
State ex rel. Brotherhood of Locomotive Firemen and Enginemen v. Shain
... ... Assn. v ... Trimble, 334 Mo. 920, 68 S.W.2d 688; Myers v. Union ... E., L. & P. Co., 334 Mo. 622, 66 S.W.2d 569; ... from or directing any work, but that he could do light ... work." The ... [123 S.W.2d 3] ... evidence on the ... 677] of Appeals in ... Terminal Ice & Power Co. v. American Fire Ins. Co. (Mo ... App.), 187 S.W ... ...
- Myers v. Union Electric Light & Power Co.