National Foundation Co. v. Post, Buckley, Schuh & Jernigan, Inc.

Decision Date11 December 1995
Docket NumberNo. A95A2196,A95A2196
Citation219 Ga.App. 431,465 S.E.2d 726
CourtGeorgia Court of Appeals
PartiesNATIONAL FOUNDATION COMPANY v. POST, BUCKLEY, SCHUH & JERNIGAN, INC. et al.

Pursley, Howell, Lowery & Meeks, John R. Lowery, Susan S. Jones, Atlanta, for appellant.

Sutherland, Asbill & Brennan, William R. Wildman, Charles T. Lester, Jr., Atlanta, for appellees.

BIRDSONG, Presiding Judge.

Appellant National Foundation Company d/b/a Nicholson Construction Company (construction company) filed notice of appeal solely from the order of the trial court granting summary judgment to appellees Post, Buckley, Schuh & Jernigan, Inc. et al.

On June 25, 1990, John Wesley Murphy, a carpenter employed by the general contractor, E.R. Snell Contractor, Inc., fell from an unguarded walkway along a shoring wall at the Peachtree Road bridge-Georgia 400 construction project (project); as a result, he was rendered a brain-damaged quadriplegic. The shoring wall was part of a construction project designed by appellee Post, Buckley, Schuh & Jernigan, a professional engineering firm, under contract with the Georgia Department of Transportation. Appellees Stephen Hale, project manager, and Joseph McGrew, bridge designer, were professional engineers employed by appellee engineering firm.

On November 17, 1992, Kimber Fortner, legal guardian of Murphy, sued appellees and appellant construction company averring professional malpractice in the design, preparation and subsequent shop drawings for the shoring wall, and that appellant construction company was negligent in maintaining a safe work area. Appellant served as both the designer of the shoring wall and as the supervising contractor for its construction. The OCGA § 9-11-9.1 expert affidavit recites that appellee Hale was the engineer of record, certain of the drawings relating to the project were made by appellee McGrew, and the project plans were prepared by appellee engineering firm for whom Hale and McGrew acted as agents in designing, preparing and approving construction drawings for the project. The affidavit also recites that the details of the shoring wall from which Murphy fell were prepared in the form of shop drawings by an engineer-employee of appellant construction company as part of, and in implementation of, the overall project design prepared by appellee engineering firm. These shop drawings were submitted to appellee engineering firm and were reviewed and approved by their agent McGrew. The expert's affidavit concluded that appellee engineering firm and its agents were negligent as follows: failing to design and show on the drawings a protective barrier or handrail for the top of the shoring wall; failing to provide for barriers at each end of the shoring wall to keep workers from the top of the wall; and failing when reviewing the shop drawings prepared by appellant construction company to require protective barriers or handrails on the top of the wall or barriers at each end thereof to keep workers from the wall top. The expert's subsequent deposition testimony was not inconsistent with his affidavit. Appellee engineering company submitted inter alia affidavits from McGrew and Hale in which they stated they were not negligent in connection with their design of the project or with the review of the shop drawings. They also claimed no responsibility or obligation to design barricades or handrails for the shoring wall, and that their review of appellant's shop drawings did not require them to check for safety items such as barricades or handrails.

The trial court granted summary judgment to appellees and denied summary judgment to appellant. Thereafter, appellant and another defendant settled the case with plaintiff. As a material part of this settlement plaintiff, with consent of the trial court, dismissed its suit with prejudice after having executed a broad release of appellant and all persons and legal entities listed expressly by name in the release and settlement agreement document. Both appellant and appellees were among those entities expressly listed by name in the release and settlement agreement. Thereafter, appellant filed notice of appeal from the grant of summary judgment to appellees. See generally Shackelford v. Green, 180 Ga.App. 617, 618-619, 349 S.E.2d 781, aff'd 257 Ga. 9, 356 S.E.2d 27.

Appellant asserts the trial court erred in concluding there were no genuine issues of material fact presented by the evidence, and that appellees were not entitled to summary judgment; appellees contend inter alia that this appeal should be dismissed. Held:

1. "Direct appeals from orders granting partial or complete summary judgment may be taken either within 30 days of rendition of the judgment or after the rendition of the final judgment in the case." Studdard v. Satcher, etc., Inc., 217 Ga.App. 1, 2, 456 S.E.2d 71. Notice of appeal was filed within 30 days of plaintiff's voluntary dismissal of this suit with prejudice.

As a general rule, voluntary dismissal with prejudice (particularly when entered with trial court approval) of an entire suit constitutes a form of "final judgment" under the appellate practice act. Marchman & Sons v. Nelson, 251 Ga. 475, 306 S.E.2d 290; cf. Fowler v. Vineyard, 261 Ga. 454(2), 405 S.E.2d 678 (Voluntary dismissal with prejudice constitutes judgment on the merits for purposes of res judicata.). As "the right of contribution arises out of, but exists separately from," the rights present in an underlying suit ex delicto involving joint tortfeasors, "dismissal with prejudice of the underlying suit is not a bar to an action for contribution by one joint tortfeasor against another joint tortfeasor." Marchman, supra at 477, 478, 306 S.E.2d 290.

Appellee engineering firm asserts, however, that because appellant secured the dismissal of all parties, including itself, from the case, no case or issue remains to be appealed. Appellant contends it is entitled to appeal the grant of summary judgment to the co-defendant, appellee engineering firm, based on the holding of this court in Shackelford, supra. In Shackelford, at 618, 349 S.E.2d 781, it was opined that "[s]tatus as a losing party has been statutorily conferred upon a co-defendant who[, as in this case,] is being sued in the capacity of a joint tort-feasor and who wishes to appeal the grant of summary judgment in favor of one or more of his other co-defendants." A co-defendant in a tort action, as a general rule, is deemed to have standing to appeal the grant of summary judgment to another co-defendant against whom he asserts a right of contribution. See Shackelford, supra; compare Hussey, etc., v. Ga. Ports Auth., 204 Ga.App. 504, 507(4), 420 S.E.2d 50. Thus, the standing requirement has been relaxed in situations "in which the co-defendants are being sued as joint tortfeasors." C.W. Matthews Contracting Co. v. Studard, 201 Ga.App. 741, 742(2), 412 S.E.2d 539.

Appellees, citing inter alia Satcher, etc., Inc., supra; Mitchell v. Wyatt, 192 Ga.App. 127(1), 384 S.E.2d 227 and United States Fire Ins. Co. v. Farris, 146 Ga.App. 177, 245 S.E.2d 868, assert that a party cannot appeal from a voluntary dismissal which it has caused to be procured. Appellant aptly counters that it is appealing from the grant of summary judgment and not from either the order of the court authorizing voluntary dismissal of the suit or the voluntary dismissal thereof. The order granting summary judgment was, by virtue of statute (OCGA § 9-11-56(h)), an appealable order; it is from this order appellant has timely filed this appeal. And appellant, as an alleged joint tortfeasor, is deemed to have appellate status as a "losing party." Shackelford, supra. We decline to dismiss this appeal.

2. Applying the summary judgment standards of Lau's Corp. v. Haskins, 261 Ga. 491, 405 S.E.2d 474, we conclude that the trial court did not err in granting summary judgment to appellees.

In malpractice cases, the breach of duty--that is, the element of failure of the professional to exercise ordinary care, skill, and diligence--must relate...

To continue reading

Request your trial
10 cases
  • SDM Invs. Grp., LLC v. HBN Media, Inc.
    • United States
    • Georgia Court of Appeals
    • January 28, 2021
    ...a voluntary dismissal with prejudice operates as an adjudication on the merits."); Nat'l Found. Co. v. Post, Buckley, Schuh & Jernigan, Inc. , 219 Ga. App. 431, 432 (1), 465 S.E.2d 726 (1995) ("As a general rule, voluntary dismissal with prejudice particularly when entered with trial court ......
  • Gullock v. Spectrum Sciences and Software, Inc.
    • United States
    • U.S. District Court — Middle District of Georgia
    • May 29, 2001
    ...243, 245 (1960)). A party's legal duty may arise by operation of law or by contract. See National Foundation Co. v. Post, Buckley, Schuh & Jernigan, Inc., 219 Ga.App. 431, 465 S.E.2d 726, 729 (1995) (citing Armor Elevator Co. v. Hinton, 213 Ga.App. 27, 443 S.E.2d 670, 672 (1994)). Determini......
  • Lawson v. Entech Enterprises, Inc.
    • United States
    • Georgia Court of Appeals
    • October 30, 2008
    ...omitted.) Adams v. APAC-Georgia, 236 Ga.App. 215, 217, n. 9, 511 S.E.2d 581 (1999), citing Nat. Foundation Co. v. Post, Buckley, etc., 219 Ga.App. 431, 435(2), 465 S.E.2d 726 (1995) (defendant entitled to summary judgment notwithstanding expert testimony that it was chargeable with breach o......
  • Greenhorne & O'Mara v. City of Atlanta
    • United States
    • Georgia Court of Appeals
    • June 9, 2009
    ...were legally liable to the plaintiff. . .") (Citation, punctuation and footnote omitted). 7. Nat. Foundation Co. v. Post, etc., Jernigan, Inc., 219 Ga.App. 431, 433(1), 465 S.E.2d 726 (1995). 8. (Footnotes omitted.) State Auto Mut. Ins. Co., 287 Ga.App. at 577(1), 651 S.E.2d 9. Greenhorne a......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT