Hussey, Gay & Bell v. Georgia Ports Authority, CLAY-RI

Decision Date08 June 1992
Docket NumberA92A0365,CLAY-RI,INC,Nos. A92A0308,s. A92A0308
Citation204 Ga.App. 504,420 S.E.2d 50
PartiesHUSSEY, GAY & BELL v. GEORGIA PORTS AUTHORITY.v. GEORGIA PORTS AUTHORITY.
CourtGeorgia Court of Appeals

Brannen, Searcy & Smith, Joseph J. Berrigan, Savannah, for appellant (case no. A92A0308).

Edenfield, Stone & Cox, Gerald M. Edenfield, Susan W. Cox, James B. Rutledge III, E. Lee Davis, Jr., Statesboro, for appellant (case no. A92A0365).

Michael J. Bowers, Atty. Gen., Atlanta, George H. Chamlee, Savannah, for appellee.

COOPER, Judge.

These two appeals mark the second and third appearances of cases arising out of a 1982 contract between Georgia Ports Authority ("GPA") and Pinehurst Corporation ("Pinehurst") for the construction of a warehouse extension at GPA's ocean terminal facility. The construction was to be performed by Pinehurst pursuant to plans and specifications prepared by the architectural engineering firm of Hussey, Gay & Bell ("HG & B"). The plans required that the warehouse have a paved floor which was installed by Clay-Ric, Inc. ("Clay-Ric") under a subcontract between Clay-Ric and Pinehurst. After installation, the floor became wet due to work being performed on the job site by Pinehurst and other subcontractors and did not pass the load test performed by HG & B. At Pinehurst's direction, Clay-Ric repaved the floor and incurred costs in excess of $40,000. However, Pinehurst did not pay Clay-Ric for the repaving work, and Clay-Ric subsequently filed a four-count complaint against Pinehurst, HG & B and GPA to recover the amounts owed for the repaving work. Clay-Ric contended that the repaving work was beyond the scope of its original contract with Pinehurst and that it performed the repair work because each of the named defendants represented to Clay-Ric that it would be fully compensated for the work. GPA answered the complaint, denying that it had made any such representations to Clay-Ric, and filed a third-party complaint against Safeco Insurance Company of America based on the payment bond given by Pinehurst pursuant to OCGA § 36-82-101. 1 GPA subsequently amended its complaint to add as a defense the failure of Clay-Ric to satisfy the bonding requirements for public works contracts with a public body and moved for summary judgment. The trial court granted GPA's motion for summary judgment. In Case Nos. A92A0308 and A92A0365, HG & B and Clay-Ric, respectively, appeal from the grant of summary judgment to GPA.

Case No. A92A0365

1. The crux of Clay-Ric's complaint against GPA is that GPA directly and through its agents authorized the paving repair work and represented that Clay-Ric would be paid for the work. "The burden is on the party who moves for summary judgment to produce evidence which conclusively negates the essential elements entitling the respondent to recover under any theory that may be drawn fairly from the pleadings and the evidence. [Cit.]" Dairyland Ins. Co. v. Gay, 193 Ga.App. 65, 67, 386 S.E.2d 909 (1989). In support of its motion for summary judgment, GPA submitted the affidavit of its Director of Engineering and Construction, who stated therein that Clay-Ric was a subcontractor of Pinehurst; that GPA never had a contract with Clay-Ric for any of the work covered by GPA's contract with Pinehurst or for any extra work related to that contract; that GPA never authorized any contract with Clay-Ric; that contrary to the allegations in Clay-Ric's complaint, GPA neither authorized the paving repair work nor represented that GPA would pay Clay-Ric for the repair work; and that HG & B had no authority to contract with Clay-Ric on GPA's behalf. " 'Once the moving party for summary judgment has carried its burden of making out a prima facie case, the burden shifts and the opposite party must come forward with rebuttal evidence or suffer judgment against him. [Cits.]' [Cit.]" Powell v. Sadlier, 195 Ga.App. 680, 681, 394 S.E.2d 614 (1990). In opposition to GPA's motion for summary judgment, Clay-Ric submitted the affidavit of the president of Clay-Ric who stated that he was instructed by representatives of HG & B that the repair work was to be paid for by GPA. Clay-Ric also submitted the deposition testimony of a Pinehurst employee who stated that one of HG & B's engineers committed to Clay-Ric's representative that if Clay-Ric performed the work, he would make sure Clay-Ric was paid for it. Clay-Ric presented no evidence which contradicted GPA's contention that GPA did not authorize the repair work or represent that it would pay Clay-Ric for the repairs. However, Clay-Ric argues that genuine issues of fact exist as to whether HG & B had authority to contract with Clay-Ric for the extra work on behalf of GPA. " ' "The bare assertion or denial of the existence of an agency relationship is a statement of fact when made by one of the purported parties to the relationship; but when made by an outsider, bare assertions or denials are merely conclusions of law." [Cits.] "The affidavit ... denying the existence of agency must be received as evidence of a fact, which cannot be overcome by conclusionary affidavits ..." [Cit.]' [Cit.]" Coley Elec. Supply v. Colonial Eggs of Alma, 165 Ga.App. 108 (2), 299 S.E.2d 165 (1983). It is undisputed that HG & B was the designated engineer charged with overseeing the warehouse construction project for GPA. However, HG & B's role as the engineer did not automatically confer upon HG & B the power to enter into contracts on behalf of GPA. See Cannon v. Hunt, 113 Ga. 501, 505-506, 38 S.E. 983 (1901). We conclude that the affidavit of GPA's Director of Engineering constitutes factual evidence that HG & B had no such authority to authorize or contract for any additional work on behalf of GPA and that the affidavits and deposition testimony submitted by Clay-Ric were insufficient to overcome that evidence. See Coley, supra at 110, 299 S.E.2d 165. Nor do we find that any question of fact exists as to whether HG & B had apparent authority to contract for GPA. There is no evidence that GPA held out HG & B as being any more than the engineer charged with overseeing the project. "[A]n apparent agency relationship binding upon the principal of the alleged relationship is proven by the principal's conduct in holding out the alleged agent as such. An apparent agency relationship is not proven in an action against a principal solely by proof of the conduct of the alleged agent. [Cits.]" Id.

2. Clay-Ric also contends that the trial court erred in not finding that GPA is liable under implied contract theories of...

To continue reading

Request your trial
13 cases
  • Shaw v. City of Charleston
    • United States
    • South Carolina Court of Appeals
    • June 24, 2002
    ...distinction regarding appealability and standing turning on whether the co-defendant's rights are affected. In the case of Hussey, Gay & Bell v. Ga. Ports Auth., the Georgia Court of Appeals (A) co-defendant does not have any standing to appeal an order granting summary judgment in favor of......
  • Nissan Motor Acceptance Corp. v. Stovall Nissan, Inc.
    • United States
    • Georgia Court of Appeals
    • January 21, 1997
    ...made by one of the purported parties to the relationship." (Citations and punctuation omitted.) Hussey, Gay, etc. v. Ga. Ports Auth., 204 Ga.App. 504, 506(1), 420 S.E.2d 50 (1992). NMAC having established the absence of an agency relationship, the burden then shifts to Stovall to show evide......
  • City of Coll. Park v. Sekisui SPR Ams., LLC.
    • United States
    • Georgia Court of Appeals
    • March 20, 2015
    ...to the statutory remedies provided by Georgia's lien statute. (Citations and punctuation omitted.) Hussey, Gay & Bell v. Ga. Ports Authority, 204 Ga.App. 504, 506(2), 420 S.E.2d 50 (1992) ; see also Callahan v. Hall, 302 Ga.App. 886, 888, 691 S.E.2d 918 (2010) (subcontractor is precluded fr......
  • National Foundation Co. v. Post, Buckley, Schuh & Jernigan, Inc.
    • United States
    • Georgia Court of Appeals
    • December 11, 1995
    ...to another co-defendant against whom he asserts a right of contribution. See Shackelford, supra; compare Hussey, etc., v. Ga. Ports Auth., 204 Ga.App. 504, 507(4), 420 S.E.2d 50. Thus, the standing requirement has been relaxed in situations "in which the co-defendants are being sued as join......
  • Request a trial to view additional results
2 books & journal articles
  • Construction Law
    • United States
    • Mercer University School of Law Mercer Law Reviews No. 72-1, September 2020
    • Invalid date
    ...Id. at *15, *17.105. Id. at *15 (alterations in original) (quoting Hussey v. Georgia Ports Authority, 240 Ga. App. 504, 506, 420 S.E.2d 50, 53 (1992).106. Id. at *16-17 (alteration in original) (quoting J.W. Bateson Co. v. United States, 434 U.S. 586, 589 (1978)).107. Id. at *17.108. Id.109......
  • Construction Law - Dennis J. Webb, Jr., Justin S. Scott, and Henry L. Balkcom Iv
    • United States
    • Mercer University School of Law Mercer Law Reviews No. 54-1, September 2002
    • Invalid date
    ...contract; rather, it is limited to the statutory remedies provided by Georgia's lien statute." Hussey, Gay & Bell v. Ga. Ports Auth., 204 Ga. App. 504, 506, 420 S.E.2d 50 (1992). In Hussey this court applied the longstanding rule applicable to private contracts and the Georgia mechanics to ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT