Nolop v. Spettel
Decision Date | 08 June 1954 |
Citation | 267 Wis. 245,64 N.W.2d 859 |
Parties | NOLOP, v. SPETTEL. |
Court | Wisconsin Supreme Court |
Action commenced May 24, 1952, by Osborne Nolop, d/b/a Nolop Construction Company, against Mark Spettel, to recover money allegedly due for the construction, under a cost-plus contract, of a dwelling house and garage. A reference was ordered, and the matter was heard before the referee. Upon motion, judgment in favor of the plaintiff was entered December 28, 1953, confirming the referee's report. Judgment was for $756.82, with interest from April 28, 1952. Defendant had offered judgment in plaintiff's favor for the sum of $585. This offer was rejected. Defendant appeals. The material facts will be stated in the opinion.
Johns, Roraff, Pappas & Flaherty, La Crosse, for appellant.
Hale, Skemp, Nietsch, Hanson & Schnurrer, La Crosse, for respondent.
Although there was never a written contract between the parties to this action, it is stipulated that they agreed to be bound by a written contract that had existed between the respondent and one Doctor Hulick, the pertinent portions of which contract follow:
'The actual net cost to the contractor of the materials actually furnished and labor and cartage actually performed by him hereunder on and for said building, plus a profit of 10%.
'The term actual net cost shall include the following:
'(a) The cost of all labor furnished;
'(b) The actual net cost of all materials purchased as shown by the original invoices;
'(c) The expense incurred by the contractor for cartage of all supplies and other expenses incidental to the erection of the building;
'(d) The cost of rental of any equipment which the contractor deems necessary or beneficial in the erection of the building;
'(e) The cost of insurance including workmen's compensation expended by the contractor in the erection of the building, except sub-contracts.
* * *
During the progress of the construction of the buildings statements showing various charges for labor at an hourly rate were submitted to appellant. The evidence shows that appellant was under the impression that all of the charges made by respondent for labor were the amounts actually paid in wages at the rates claimed; and that appellant continued to make payments without objection until the residence was substantially completed, at which time he learned from one of the painters that the rate per hour charged for his services to appellant was higher than the rate actually paid him by respondent. Appellant, then unwilling to pay the balance claimed by respondent, insisted that an accounting be had. An action was begun, and an adverse examination of respondent was had in May 1953. Then for the first time appellant learned what respondent had in fact paid his employees. The items claimed by respondent were reviewed in detail before a referee, and some of the items were disallowed. The referee made his findings of fact and concluded that appellant was indebted to respondent in the sum of $756.82, with interest from April 28, 1952. The circuit court confirmed the referee's report and ordered judgment accordingly.
The first contention of the respondent, that appellant, by his actions in failing to complain to the contractor and in making payments on the contract and ordering new work to be done, waived any objections to any alleged overcharges or methods of computations, cannot be sustained. The great weight and clear preponderance of evidence does not permit of a finding that appellant, at the time he made those payments, was apprised that the rates per hour and the totals for labor set forth in statements presented to him by respondent included overcharges to cover an excess of incidentals or overhead. He did not learn that he was being so charged until the building was substantially completed. 'A waiver is the intentional relinquishment of a known right.' Swedish American National Bank of Minneapolis v. Koebernick, 136 Wis. 473, 479, 117 N.W. 1020, 1023. 56 Am.Jur. p. 114, sec. 14. At no time did the respondent inform appellant as to what he in fact was paying his men; appellant had no knowledge of the overcharge at the time he paid the bills presented to him; therefore no waiver existed.
Respondent's second contention, that labor includes items other than wages, is an unwarranted interpretation of the contract. He has taken the provision under subparagraph (c) of the contract allowing him 'other expenses incidental to the erection of the building' and treated it as if it were part of (a) which refers to 'the cost of all labor furnished'; then he has insisted that it be included as overhead. Using this method of computation, respondent has billed appellant for labor an amount per laborer greater than the actual amount paid out per laborer in wages.
The contract in question is a cost-plus contract. It provides separately for a profit of 10% to be realized by the contractor on the cost of the erection of the building. The term 'actual cost' governs the entire contract and applies to each of the sub-items, i. e., labor, material, cartage, incidental expenses, rental equipment, and insurance and workmen's compensation. Further, payment by appellant for all of these separate items is subject to their being actually furnished or actually performed on and for said building, as stipulated in the second paragraph of the Dr. Hulick contract.
A review of available cases on cost-plus contracts and analogous cases requires the recognition of the general rules which are to be applied to the instant case. In one of the leading cases on this subject, it is said: Lytle, Campbell, & Co. v. Somers, Fitler & Todd Co., 276 Pa. 409, 120 A. 409, 411, 27 A.L.R. 41. (Emphasis supplied). In the case of The Spica, 2 Cir., 289 F. 436, 446, the contract specifically provided for 'cost to include overhead', and there the court said: In that case, the court gave an illustration to show the divergence between what libelant asserted and tried to prove and what the evidence showed it contracted to do: In Shaw v. G. B. Beaumont Co., 88 N.J.Eq. 333, 102 A. 151, 153, 2 A.L.R. 122, it is said: 'A contractor, when he agrees to build, must, in the absence of a contrary agreement, furnish all the tools and necessary appliances for the work contracted to be done.' See also Marion...
To continue reading
Request your trial-
Walberg v. State
...28 Am.Jur.2d, Estoppel and Waiver, p. 841, sec. 158; Davis v. J. D. Wilson Co. (1957), 1 Wis.2d 443, 85 N.W.2d 459; Nolop v. Spettel (1954), 267 Wis. 245, 64 N.W.2d 859.7 See: Pamanet v. State (1971), 49 Wis.2d 501, 182 N.W.2d 459; Burton v. State Appeal Board (1968), 38 Wis.2d 294, 156 N.W......
-
Mansfield v. Smith
...commission. " 'Waiver' is defined as voluntary and intentional relinquishment of a known right. As said in Nolop v. Spettel (1954), 267 Wis. 245, 249, 64 N.W.2d 859, 862: " ' "A waiver is the intentional relinquishment of a known right. " Swedish American Nat. Bank of Minneapolis v. Koebern......
-
Hanz Trucking, Inc. v. Harris Bros. Co., Crestline Division
...by month basis.' "Waiver' is defined as voluntary and intentional relinquishment of a known right. As said in Nolop v. Spettel, 1954, 267 Wis. 245, 249, 64 N.W.2d 859, 862: "'A waiver is the intentional relinquishment of a known right.' Swedish American Nat. Bank of Minneapolis v. Koebernic......
-
Milas v. Labor Ass'n of Wisconsin, Inc.
...question to determine just where the doctrine of implied waiver ends and that of estoppel begins.10 See also Nolop v. Spettel, 267 Wis. 245, 249, 64 N.W.2d 859 (1954); Mansfield v. Smith, 88 Wis.2d 575, 592, 277 N.W.2d 740 (1979).11 The County never expressly stated its objection to the arb......