Okee Industries, Inc. v. National Grange Mut. Ins. Co.

Decision Date13 April 1993
Docket NumberNo. 14583,14583
Citation225 Conn. 367,623 A.2d 483
CourtConnecticut Supreme Court
PartiesOKEE INDUSTRIES, INC. v. NATIONAL GRANGE MUTUAL INSURANCE COMPANY et al.

John C. Yavis, Jr., with whom, on the brief, was Mark D. Nielsen, Hartford, for appellant (plaintiff).

James N. Royster, Hartford, for appellee (named defendant).

Before PETERS, C.J., and BORDEN, BERDON, NORCOTT and KATZ, JJ.

PETERS, Chief Justice.

The issue in this appeal is whether an unpaid subcontractor seeking to recover on a payment bond furnished for a public construction contract has adequately complied with the notice requirements contained in General Statutes § 49-42(a). 1 Alleging non-payment for materials supplied to the worksite, the plaintiff, Okee Industries, Inc., doing business as Hardware Specialities, Inc. (subcontractor), brought an action against the defendant Jon Butler Building and Remodeling (general contractor) and the named defendant, National Grange Mutual Insurance Company (surety). 2 After a hearing, the trial court rendered summary judgment in favor of the surety, from which the subcontractor appealed to the Appellate Court. We transferred the appeal to this court pursuant to Practice Book § 4023 and General Statutes § 51-199(c) and now reverse.

The trial court's memorandum of decision and the record establish the following facts. Pursuant to General Statutes § 49-41, 3 the surety executed a payment bond for a state financed construction project in East Windsor, naming the general contractor as principal and designating the suppliers of labor and materials as the beneficiaries of the bond. According to its complaint, the subcontractor supplied hardware items for the project in accordance with its contract with the general contractor, but remains unpaid to the extent of $37,742.90.

After unsuccessfully demanding payment from the general contractor, 4 the subcontractor sent written notice of its claim to the surety on six separate occasions. Even though only one of these notices was sent by certified or registered mail, the notices were timely and adequately apprised the surety of the substance of the subcontractor's claim. 5 The surety refused to pay the subcontractor.

In the subcontractor's action against the surety for breach of the surety's obligations under the payment bond, the trial court concluded that the subcontractor was not entitled to enforce its right to payment under the bond because it had failed to serve timely notice on the general contractor, as required by § 49-42(a). Because the statute requires a claimant to give proper notice both to the principal on the bond and to the surety, the court granted the surety's motion for summary judgment and denied the subcontractor's motion for partial summary judgment.

The subcontractor, in its appeal from the judgment, does not dispute that § 49-42(a) makes compliance with the statutory notice requirements a precondition to its recovery on the surety bond. American Masons' Supply Co. v. F.W. Brown Co., 174 Conn. 219, 224, 384 A.2d 378 (1978); Pittsburgh Plate Glass Co. v. Dahm, 159 Conn. 563, 565, 271 A.2d 55 (1970). The subcontractor's obligation to give notice to the general contractor of its claim on a payment bond, even if the subcontractor and the general contractor have a direct contractual relationship, was added by an amendment to the statute in 1987. Public Acts 1987, No. 87-345, § 2. 6 Accordingly, § 49-42(a) now expressly provides that any "person who has furnished labor or material ... may enforce his right to payment under the bond by serving a notice of claim within one hundred eighty days after the date on which he ... furnished the last of the material for which the claim is made, on the surety that issued the bond and a copy of the notice on the contractor named as principal in the bond." (Emphasis added.) The statute thus permits the surety to assert as a defense to an action on the bond not only a lack of timely notice to the surety itself, but also a lack of "a copy of the notice" to the general contractor.

The issue before us, therefore, is whether the subcontractor, after having repeatedly notified the surety in writing of a claim for payment in the amount of $37,742.90, adequately gave "a copy of the notice" to the general contractor. The statutory requirement would have been met, on its face, if the subcontractor, in one of its timely written notices of claim to the surety, had appended a legend indicating that a copy was being sent to the general contractor, and had then proceeded to forward a copy as indicated. In this case, however, the subcontractor instead sent a letter that, although timely, was the mirror image of what the statute contemplates. On July 9, 1990, the subcontractor wrote a letter to the general contractor, challenging the general contractor's calculation of the amount remaining unpaid and demanding immediate payment by the general contractor. At the bottom of this letter, the subcontractor appended a notation indicating that a copy was being sent to the surety. 7

Whether the July 9, 1990 letter meets the statutory requirement that the general contractor be served with "a copy of the notice" that a claim is being asserted against the surety depends upon an assessment of how the letter fits into two somewhat conflicting lines of cases. On the one hand, as the surety notes, § 49-42 is a statutory cause of action that had no antecedents at common law. "The statute having created the cause of action and prescribed the procedure, the mode of proceeding is mandatory and must be strictly complied with." Pittsburgh Plate Glass Co. v. Dahm, supra; New Britain Lumber Co. v. American Surety Co., 113 Conn. 1, 7-8, 154 A. 147 (1931); Wickes Mfg. Co. v. Currier Electric Co., 25 Conn.App. 751, 757, 596 A.2d 1331 (1991). On the other hand, as the subcontractor notes, § 49-42 is a remedial statute enacted to provide security for workers and materials suppliers unable to avail themselves of the protection of a mechanic's lien. Nor'easter Group, Inc. v. Colossale Concrete, Inc., 207 Conn. 468, 477-79, 542 A.2d 692 (1988). Because "[t]he statutory requirement of a bond is designed to protect and benefit those who furnish materials and labor to the contractor on public work, in that they may be sure of payment of their just claims, without defeat or undue delay ... such statutory provisions are to be liberally construed." (Citations omitted; internal quotation marks omitted.) American Masons' Supply Co. v. F.W. Brown Co., supra, 174 Conn. at 227, 384 A.2d 378; International Harvester Co. v. L.G. DeFelice & Son, Inc., 151 Conn. 325, 333, 197 A.2d 638 (1964).

We have not often applied maxims of strict construction and liberal construction to one and the same statute. As modern jurisprudence counsels, the explanation for this apparent paradox is found in an examination of the underlying fact patterns in the relevant cases. We have relied on the rule of strict construction when the issue was whether the claimant's notice complied with the specific time requirements of the statute. Pittsburgh Plate Glass Co. v. Dahm, supra, 159 Conn. at 566, 271 A.2d 55; New Britain Lumber Co. v. American Surety Co., supra; Wickes Mfg. Co. v. Currier Electric Co., supra, 25 Conn.App. at 759, 596 A.2d 1331. We have, however, relied on the rule of liberal construction when the issue was the eligibility for statutory coverage of a particular class of subcontractors; American Masons' Supply Co. v. F.W. Brown Co., supra; or a particular type of supplier of materials. International Harvester Co. v. L.G. DeFelice & Son, Inc., supra, 151 Conn. at 333-36, 197 A.2d 638. In other words, if the statute itself imposes specific constraints, we have held these constraints to be mandatory; if the statute leaves room for construction, we have construed its requirements liberally in order to implement the statute's remedial purpose.

Because § 49-42 was patterned after federal legislation popularly known as the Miller Act; 40 U.S.C. §§ 270a through 270d; we have regularly consulted federal precedents to determine the proper scope of our statute. American Masons' Supply Co. v. F.W. Brown Co., supra, 174 Conn. at 223-24, 384 A.2d 378; Pittsburgh Plate Glass Co. v. Dahm, supra, 159 Conn. at 567-68, 271 A.2d 55; International Harvester Co. v. L.G. DeFelice & Son, Inc., supra, 151 Conn. at 332-34, 197 A.2d 638. The federal precedents, like our own, counsel liberal construction of statutory requirements other than those relating to specific time constraints. As the Supreme Court of the United States observed in Fleisher Engineering & Construction Co. v. United States ex rel. Hallenbeck, 311 U.S. 15, 18, 61 S.Ct. 81, 83, 85 L.Ed. 12 (1940), "a requirement which is clearly made a condition precedent to the right to sue must be given effect, but in determining whether a provision is of that character the statute must be liberally construed so as to accomplish its purpose."

Following Fleisher, the lower federal courts, except in cases involving the timeliness of notice, have eschewed the rule of strict construction. 8 As the court observed in United States ex rel. Hopper Bros. Quarries v. Peerless Casualty Co., 255 F.2d 137, 143 (8th Cir.), cert. denied, 358 U.S. 831, 79 S.Ct. 51, 3 L.Ed.2d 69 (1958): "It may be that Congress thought the procedural requirements it prescribed for laborers and materialmen to enforce the right to sue for their pay which is accorded them by the Miller Act were so plain, simple, and easy to comply with that there would seldom be questions about them. But experience is to the contrary and the courts are continually called on to determine whether one deviation or another from the strict letter of the Act necessitates denial of the protection to laborers and materialmen, which the Act aims to provide. The doctrine to which the courts are unanimously committed is that the protection of the laborers...

To continue reading

Request your trial
26 cases
  • Commission on Human Rights & Opportunities v. Sullivan Associates
    • United States
    • Connecticut Supreme Court
    • October 12, 1999
    ... ... for the Connecticut Fair Housing Center, Inc., et al. as amici curiae ...          ... Development pursuant to section 8 of the National Housing Act, as amended in 1974 and codified at ... 466, 474, 696 A.2d 1249 (1997); Okee Industries, Inc. v. National Grange Mutual Ins ... ...
  • Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
    • United States
    • Connecticut Supreme Court
    • January 21, 1997
    ... ... 750, 757, 674 A.2d 1313 (1996); see National Fire Proofing Co. v. Huntington, 81 Conn. 632, ... 325, 332-34, 197 A.2d 638 (1964) ]." Okee Industries, Inc. v. National Grange Mutual Ins ... ...
  • Elec. Contractors, Inc. v. Ins. Co. of Pa.
    • United States
    • Connecticut Supreme Court
    • December 16, 2014
    ... ... 314 Conn. 771 Okee Industries, Inc. v. National Grange Mutual Ins. Co., 225 ... ...
  • Angelsea Productions, Inc. v. Commission on Human Rights and Opportunities
    • United States
    • Connecticut Supreme Court
    • April 23, 1996
    ... ... Liberty Mutual Fire Ins. Co., 174 Conn. 229, 233, 384 A.2d 384 (1978) ... Okee Industries, Inc. v. National Grange Mutual Ins ... ...
  • Request a trial to view additional results
2 books & journal articles
  • Contractors at Risk- the 1993 Amendment to Section 49-41 of the Connecticut General Statutes
    • United States
    • Connecticut Bar Association Connecticut Bar Journal No. 68, 1993
    • Invalid date
    ...(1964); Nor'easter Group, Inc. v. Colossale Concrete, Inc., 207 Conn. 468 (1988); and Okee Indust., Inc. v. National Group Mut. Ins. Co., 225 Conn. 367, 373 (1993 . 5. National Fireproofing Co. v. Huntington, 81 Conn. 632 (1909). 6. Seaman v. Climate Control Corporation, 181 Conn. 592,595,5......
  • Annual survey of fidelity and surety law, 1993.
    • United States
    • Defense Counsel Journal Vol. 61 No. 1, January 1994
    • January 1, 1994
    ...88 (10th Cir. 1993). (5.)140 F.2d 115 (10th Cir. 1944). (6.)20 Cal.Rptr.2d 200 (Cal.App. 1993). (7.)854 P.2d 1185 (Ariz.App. 1993). (8.)623 A.2d 483 (Conn. 1993). (9.)499 N.W.2d 8 (Iowa 1993). (10.)Perkins Builders Supply & Fuel Co. v. Indep. Sch. Dist., 221 N.W. 793 (Iowa 1928). (11.)9......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT