Rose v. Colorado Factory Homes

Decision Date17 February 2000
Docket NumberNo. 98CA1662.,98CA1662.
Citation10 P.3d 680
PartiesCarl ROSE and Pamela Rose, Plaintiffs-Appellees, v. COLORADO FACTORY HOMES, d/b/a New Vision Homes, Inc., a Colorado corporation, Defendant-Appellant.
CourtColorado Court of Appeals

Fisher & Sweetbaum, P.C., Alan Sweetbaum, Brad Ramming, Denver, Colorado, for Plaintiffs-Appellees.

Thomas R. French, P.C., Thomas R. French, Fort Collins, Colorado, for Defendant-Appellant.

Opinion by Judge KAPELKE.

In this action for negligence and revocation of acceptance arising from the sale of a modular home, defendant, Colorado Factory Homes d/b/a/ New Vision Homes, Inc. (seller), appeals from the trial court judgment entered upon a jury verdict in favor of plaintiffs, Carl and Pamela Rose (buyers). We affirm.

In 1994, the parties entered into a written purchase contract for the sale of a modular home. After the buyers moved into the home, they noticed a number of cosmetic and structural defects. They reported the defects to seller's president, who indicated that they would be remedied.

After repairs had been made, buyers informed seller that they accepted the home. In October 1995, however, buyers complained that additional work was needed with respect to structural components of the home. Buyers then filed this action against seller and also against the manufacturer of the modular home.

In their original complaint, buyers asserted claims against seller for negligence and breach of warranty and also claims against the manufacturer for breach of warranty and revocation of acceptance. Prior to trial, buyers settled their claim against the manufacturer and amended their complaint to add a claim against seller for revocation of acceptance.

Following trial, the jury returned a verdict in favor of the buyers on their claim of revocation of acceptance. The jury also found in favor of buyers on their claim of negligence, but found that they had not incurred damages as to that claim. This appeal followed.

I.

Seller first contends it is entitled to a new trial because a juror engaged in misconduct by failing to give full and accurate answers to questions asked during voir dire.

A juror's failure to answer material questions truthfully during voir dire, if discovered during trial, may justify the removal of that juror and replacement with an alternate or result in a declaration of mistrial. However, a prospective juror's untruthful answers on voir dire do not automatically entitle a party to a new trial. Allen v. Ramada Inn, Inc., 778 P.2d 291 (Colo.App.1989).

If a juror's nondisclosure was inadvertent, it must be shown that the undisclosed facts were such as to have created an actual bias. Absent such a showing, it will be assumed that the juror followed the instructions of the court and decided the case based solely on the evidence and the law. People v. Christopher, 896 P.2d 876 (Colo. 1995); People v. Dunoyair, 660 P.2d 890 (Colo.1983).

Further, the trial court is in the best position to view the demeanor of the juror, and its decision will not be disturbed on appeal unless the record affirmatively demonstrates that the court abused its discretion. People v. Christopher, supra; People v. Russo, 713 P.2d 356 (Colo.1986).

Here, during voir dire, seller's counsel asked the juror if she knew any of the witnesses, and she responded that she knew the independent contractor hired by seller to set up the buyers' home. She also stated that she had purchased a modular home and that the same contractor had performed most of the service warranty work. In addition, she said she had not had any problems with the home and was generally satisfied with it.

In support of its motion for new trial, seller submitted affidavits of its president and of the wife of the independent contractor who had done the set-up work on buyers' home. According to the affidavits, seller had assumed dealer-related responsibility for the modular home sold to the juror, and the juror had complained orally and in writing of defects in her own modular home and had also had warranty work performed. In addition, the seller's president stated in his affidavit that the juror's mother-in-law had bought a modular home from seller and had had problems with the work performed by seller and others. Attached to seller's affidavit was a letter the juror had sent to seller's service department requesting repair of certain items of the modular home she had purchased.

In response to the motion for new trial, buyers submitted an affidavit of the juror herself. She stated, among other things, that: (1) she "completely and honestly answered all the questions which were put to [her] during voir dire by the court;" (2) she was "completely satisfied with the quality of the warranty work which was performed by [seller];" (3) she was "completely satisfied with the home;" (4) her "failure to disclose that [her] mother-in-law [had] purchased a home was not deliberate and was not intended in any way to be a deliberate non-disclosure of a relevant fact;" and (5) her verdict was based upon what she "believed to be a fair and impartial review of the evidence and the instructions."

Under these circumstances, we conclude that seller has not established that any nondisclosures by the juror were intentional or that any undisclosed fact created an actual bias. See People v. Christopher, supra. Accordingly, we find no basis for concluding that the trial court abused its discretion in denying the motion for new trial.

II.

Seller next contends that a new trial is required because the verdicts on the buyers' claims are inconsistent. We perceive no basis for reversal.

Jury verdicts will not be disturbed for inconsistency if a review of the record indicates any basis for the verdicts. Our duty, as a reviewing court, is to try to reconcile the jury's verdicts if at all possible. Gutierrez v. Bussey, 837 P.2d 272 (Colo.App.1992).

Here, the court instructed the jury on both the negligence and revocation of acceptance claims. As noted, on the claim of negligence, the jury found that seller had been negligent but awarded no damages. On the claim of revocation of acceptance, the jury found that the value of the home was substantially impaired as a result of defects and that buyers were therefore entitled to revoke their acceptance and recover the amount they had paid.

In its order denying seller's motion for new trial, the trial court found that the jury's verdicts could be reconciled: the jury could have consistently found that the value of the buyers' modular home had been substantially impaired and that the buyers were therefore entitled to revoke their acceptance, and also found that because the buyers were entitled to a refund of their monies, they were not also entitled to an award of damages on their negligence claim. We agree with the trial court's analysis. Therefore, because the jury's verdicts may be reconciled on this basis, we conclude that they were consistent. Accordingly, a new trial is not required.

III.

Seller next contends that the trial court improperly denied its motions for directed verdict and judgment notwithstanding the verdict. We disagree.

Specifically, seller urges that the court erred in denying its motions since a provision of the purchase contract effectively excluded the buyers' right to revoke their acceptance. In support of this argument, seller relies on § 4-2-719(1)(a), C.R.S.1999, which allows parties to limit a buyer's remedies. A paragraph of the contract for the purchase of the home stated, in pertinent part, as follows:

I ALSO AGREE THAT ONCE I HAVE ACCEPTED THE UNIT, EVEN THOUGH THE MANUFACTURER(S)' WARRANTY DOES NOT ACCOMPLISH ITS PURPOSE, THAT I CANNOT RETURN THE UNIT TO YOU AND SEEK A REFUND FOR ANY REASON.

The trial court found that this provision purporting to disallow return of the modular home was ambiguous and should not be read to preclude the remedy of revocation of acceptance. We conclude that even if the provision can be read to exclude the remedy of revocation of acceptance, it would be unenforceable under the circumstances here.

When a limitation of remedies that would exclude revocation
...

To continue reading

Request your trial
8 cases
  • Murray v. Crawford
    • United States
    • U.S. District Court — District of Colorado
    • February 12, 2010
    ...depend upon circumstances of each particular case, and is generally a question of fact for the jury."). See also Rose v. Colorado Factory Homes, 10 P.3d 680, 685 (Colo.App.2000) (jury instructed to determine whether revocation of acceptance occurred within a reasonable Contrary to the argum......
  • Steward Software Co. v. Kopcho
    • United States
    • Colorado Court of Appeals
    • September 2, 2010
    ...• A reviewing court's duty is to reconcile any inconsistency in the jury's verdict, if at all possible. Rose v. Colo. Factory Homes, 10 P.3d 680, 683 (Colo.App.2000). Therefore, and with respect, I dissent from that portion of the majority opinion which would allow a new trial on damages as......
  • City of Westminster v. Centric-Jones, No. 01CA0502
    • United States
    • Colorado Court of Appeals
    • September 11, 2003
    ...jury verdict will not be disturbed for inconsistency if a review of the record indicates any basis for the verdict. Rose v. Colo. Factory Homes, 10 P.3d 680 (Colo.App.2000). Here, the instructions regarding the special verdict indicate that Special Verdict Form A did not need to be 1. Do yo......
  • Black v. Waterman, 02CA0172.
    • United States
    • Colorado Court of Appeals
    • March 27, 2003
    ...this showing, we presume the juror followed the instructions and based a decision on the evidence and the law. Rose v. Colo. Factory Homes, 10 P.3d 680 (Colo.App. 2000). Evaluation of juror misrepresentation or concealment often implicates CRE 606(b), which Upon an inquiry into the validity......
  • Request a trial to view additional results
8 books & journal articles
  • Chapter 4 - § 4.3 • BREACH OF IMPLIED WARRANTIES
    • United States
    • Colorado Bar Association Residential Construction Law in Colorado (CBA) Chapter 4 Contract Claims Arising From the Construction and Sale of a Home
    • Invalid date
    ...736, 741-48 (Colo. 1991) (contractual limitation of remedy may be void if it fails of its essential purpose); Rose v. Colo. Factory Homes, 10 P.3d 680, 684 (Colo. App. 2000) (buyers had the right to revoke contract acceptance notwithstanding contract provision purporting to exclude that rem......
  • Chapter 14 - § 14.4 • CONTRACT CLAIMS ARISING FROM THE CONSTRUCTION AND SALE OF A HOME
    • United States
    • Colorado Bar Association Practitioner's Guide to Colorado Construction Law (CBA) Chapter 14 Residential Construction
    • Invalid date
    ...736, 741-48 (Colo. 1991) (contractual limitation of remedy may be void if it fails of its essential purpose); Rose v. Colo. Factory Homes, 10 P.3d 680, 684 (Colo. App. 2000) (buyers had the right to revoke contract acceptance notwithstanding contract provision purporting to exclude that rem......
  • Chapter 3 - § 3.5 CHALLENGES FOR CAUSE
    • United States
    • Colorado Bar Association Colorado Courtroom Handbook for Civil Trials (2022 ed.) (CBA) Chapter 3 Jury Selection
    • Invalid date
    ...court. Day v. Johnson, 232 P.3d 175 (Colo. App. 2009), aff'd on other grounds, 255 P.3d 1064 (Colo. 2011); Rose v. Colorado Factory Homes, 10 P.3d 680 (Colo. App. 2000); State Dep't of Highways v. Copper Mountain, Inc., 624 P.2d 936, 937 (Colo. App. 1981). ➢ General; Grounds. Sustaining a c......
  • Chapter 3 - § 3.5 • CHALLENGES FOR CAUSE
    • United States
    • Colorado Bar Association Colorado Courtroom Handbook for Civil Trials (CBA) Chapter 3 Jury Selection
    • Invalid date
    ...court. Day v. Johnson, 232 P.3d 175 (Colo. App. 2009), aff'd on other grounds, 255 P.3d 1064 (Colo. 2011); Rose v. Colorado Factory Homes, 10 P.3d 680 (Colo. App. 2000); State Dep't of Highways v. Copper Mountain, Inc., 624 P.2d 936, 937 (Colo. App. 1981). ➢ General; Grounds. Sustaining a c......
  • Request a trial to view additional results