Royalite Co. v. Federal Ins. Co.

Decision Date16 July 1990
Docket NumberDocket No. 114174
Citation184 Mich.App. 69,457 N.W.2d 96
PartiesROYALITE COMPANY, Plaintiff-Appellee, v. FEDERAL INSURANCE COMPANY, Defendant-Appellant.
CourtCourt of Appeal of Michigan — District of US

Dean, Dean, Segar, Hart & Shulman, P.C. by Robert L. Segar, Flint, for plaintiff-appellee.

Willingham & Cote, P.C. by Patrick K. Ehlmann, East Lansing, for defendant-appellant.

Before HOOD, P.J., and MAHER and CYNAR, JJ.

CYNAR, Judge.

Defendant appeals as of right from a circuit court order granting plaintiff summary disposition on its construction bond claim. We affirm.

The facts in this case are not in dispute. Granger Construction Company was the primary contractor on a project involving the construction of the Genesee County jail. As required by the Michigan public works bond act, M.C.L. Sec. 129.201 et seq.; M.S.A. Sec. 5.2321(1) et seq., Granger furnished a payment bond, issued by defendant as surety, for the protection of certain claimants supplying labor or materials for the project. M.C.L. Secs. 129.201, 129.203; M.S.A. Secs. 5.2321(1), 5.2321(3). In connection with the project, plaintiff supplied materials to Hatzel-Buehler, Inc., a subcontractor to Granger. After Hatzel-Buehler failed to pay plaintiff for the materials supplied, plaintiff commenced the instant action seeking recovery under the payment bond.

Section 7 of the act, M.C.L. Sec. 129.207; M.S.A. Sec. 5.2321(7), specifies the procedure by which a claimant not having a direct contractual relationship with the primary contractor may perfect a claim against the payment bond:

A claimant who has furnished labor or material in the prosecution of the work provided for in such contract in respect of which payment bond is furnished under the provisions of section 3, and who has not been paid in full therefore before the expiration of a period of 90 days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which claim is made, may sue on the payment bond for the amount, or the balance thereof, unpaid at the time of institution of the civil action, prosecute such action to final judgment for the sum justly due him and have execution thereon. A claimant not having a direct contractual relationship with the principal contractor shall not have a right of action upon the payment bond unless (a) he has within 30 days after furnishing the first of such material or performing the first of such labor, served on the principal contractor a written notice, which shall inform the principal of the nature of the materials being furnished ..., and (b) he has given written notice to the principal contractor and the governmental unit involved within 90 days from the date on which the claimant performed the last of the labor or furnished the last of the material for which the claim is made, stating with substantial accuracy the amount claimed....

Among the conditions concerning giving notice contained in the payment bond issued by defendant was the following:

3. No suit or action shall be commenced hereunder by any claimant:

a) Unless claimant, other than one having a direct contract with the Principal, shall have given written notice to any two of the following, the Principal, the Owner, or the Surety above named, within ninety (90) days after such claimant did or performed the last of the work or labor, or furnished the last of the materials for which said claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the materials were furnished, or for whom the work or labor was done or performed.

While the bond referenced that portion of the statute requiring ninety days notice, it did not include a similar provision referring to the thirty-day notice requirement also set forth in the statute.

It is undisputed that plaintiff met the statutory definition of a claimant entitled to bring suit on the bond. M.C.L. Sec. 129.206; M.S.A. Sec. 5.2321(6). It is also undisputed that plaintiff did not have a direct contractual relationship with the principal contractor. Finally, the parties agree that, although plaintiff complied with the ninety-day notice requirement set forth in both the statute and the bond, it did not comply with the portion of the statute requiring thirty days notice from the date materials were first supplied.

Cross-motions for summary disposition were brought by the parties. Defendant argued that plaintiff's failure to comply with the thirty-day notice requirement precluded it from maintaining an action on the bond. However, it was plaintiff's position that, because the actual payment bond only contained a ninety-day notice provision and it had complied with that provision, it was entitled to recovery. On the basis of Hub Electric Co. Inc. v. Gust Construction Co., Inc., 585 F.2d 183 (C.A.6, 1978), cert. den. 440 U.S. 936, 99 S.Ct. 1282, 59 L.Ed.2d 495 (1979), the trial court granted the motion in favor of plaintiff and awarded it judgment in the amount of $23,433.94.

Where there is no surety bond contract language covering a subcontractor, our Court has held the statute to be constitutional and required that its notice requirements be strictly construed. Square D Environmental Corp. v. Aero Mechanical, Inc., 119 Mich.App. 740, 326 N.W.2d 629 (1982). The purpose and intent of the Michigan public works bond act is to safeguard and protect contractors and material suppliers in the public sector. Adamo Equipment Rental Co. v. Mack Development Co. Inc., 122 Mich.App. 233, 236, 333 N.W.2d 40 (1982); Skyline Steel Corp. v. A J Dupuis Co., 648 F.Supp. 360, 370 (E.D.Mich., 1986).

In Pi-Con, Inc. v. A J Anderson Construction Co., 169 Mich.App. 389, 394, 425 N.W.2d 563 (1988), lv. gtd. 432 Mich. 891 (1989), our Court held that strict compliance with the statute's notice requirements was required. Liberal construction was appropriate only where the statutory language was susceptible to different interpretations. Pi-Con, supra at 395, 425 N.W.2d 563. However, in Pi-Con, supra, there was a contract between the principal and the surety which directly covered the notice requirements of a claimant other than one having a direct contract with the claimant. Here, the bond itself contains specific language in which the surety grants the principal more liberal coverage than the statute. In Pi-Con, supra, the issue was whether the statutory notice requirements could be met by sending notice by regular mail as opposed to the statutorily required certified mail.

In Tempco Heating & Cooling, Inc. v. A Rea Construction, Inc., 178 Mich.App. 181, 443 N.W.2d 486 (1989), this Court held that strict compliance with the notice requirements of the statute was necessary in a case where the bond was written in direct compliance with the statute. There was a genuine issue of material fact related to both the thirty-day and ninety-day notices given. Tempco, supra at 190-192, 443 N.W.2d 486.

Here, the circuit court found the Sixth Circuit's opinion persuasive. The question in Hub Electric, supra, was whether a subcontractor's satisfaction of the ninety-day notice requirement in the bond executed between the parties, the principal and the surety, was sufficient to permit the subcontractor to recover on its claim, or whether the thirty-day notice requirement of the statute must also be met. The Sixth Circuit stated:

We therefore hold that the surety by its bonding contract may agree to accept a greater liability than that required under the Michigan bonding statute, although for reasons of public policy it may not contract for less. The statute specifically provides that the payment bond is solely for the benefit of the claimants, and nothing suggests that the Act was intended to establish a ceiling as well as a floor upon the liability which a surety may undertake by contract. Because the bond here provided only for the 90-day notice and the trial court has correctly held that the plaintiff had complied in all respects with the conditions of the bond as written, plaintiff is entitled to recover upon it. [Hub Electric, supra at 188.]

Although this Court is not bound by a federal court decision construing a Michigan statute, it may follow the decision if the reasoning is persuasive. Hardy v. Maxheimer, 429 Mich. 422, 432, 416 N.W.2d 299 (1987); Continental Motors Corp. v. Muskegon Twp., 365 Mich. 191, 112 N.W.2d 429 (1961). We are persuaded the decision in Hub Electric, supra, is correct. The failure to reference the thirty-day notice requirement within the bond itself excused compliance with that requirement.

Affirmed.

HOOD, P.J., concurs.

MAHER, Judge (dissenting).

I cannot agree with the majority's conclusion that defendant's failure to include within its payment bond a provision reciting the statutory thirty-day notice requirement excused compliance with this requirement.

The payment bond that was issued in this case was a statutory bond that was required under the Michigan public works bond act, M.C.L. Sec. 129.201 et seq.; M.S.A. Sec. 5.2321(1) et seq. Exactly who is entitled to look to the bond for protection and the manner in which a claim under the bond must be perfected is expressly governed by the statute. M.C.L. Secs. 129.206, 129.207; M.S.A. Secs. 5.2321(6), 5.2321(7). The act expressly requires that, when a claimant does not have a direct contractual relationship with the primary contractor, a claimant must comply with both thirty- and ninety-day notice requirements as a prerequisite to a "right of action" on the bond. M.C.L. Sec. 129.207; M.S.A. Sec. 5.2321(7). This Court has repeatedly held that these notice requirements must be strictly complied with. Tempco Heating & Cooling , Inc. v. A Rea Construction, Inc., 178 Mich.App. 181, 190, 443 N.W.2d 486 (1989); Pi-Con, Inc. v. A.J. Anderson Construction Co., 169 Mich.App. 389, 394, 425 N.W.2d 563 (1988), lv. gtd. 432...

To continue reading

Request your trial
5 cases
  • Trustees v. Warranty Builders
    • United States
    • U.S. District Court — Eastern District of Michigan
    • March 29, 1996
    ...nearly identical facts. In Hub Electric Co., Inc. v. Gust Const. Co., Inc., 585 F.2d 183 (6th Cir.1978), and Royalite Co. v. Federal Ins. Co., 184 Mich.App. 69, 457 N.W.2d 96 (1990), both the Sixth Circuit and the Michigan Court of Appeals held respectively that where the bond on a public c......
  • Allen v. Owens-Corning Fiberglas Corp.
    • United States
    • Court of Appeal of Michigan — District of US
    • September 12, 1997
    ...court decision construing Michigan law, it may follow the decision if the reasoning is persuasive. See Royalite Co. v. Federal Ins. Co., 184 Mich.App. 69, 75, 457 N.W.2d 96 (1990). We are persuaded that the decision in Laney is correct. To exclude evidence of other exposures to asbestos is ......
  • Hayes Pipe Supply, Inc. v. Aegis Sec. Ins. Co. (In re Pinnacle Constructors, Inc.)
    • United States
    • U.S. Bankruptcy Court — Middle District of Tennessee
    • November 17, 2022
    ...identical facts. In Hub Electric Co., Inc. v. Gust Const. Co., Inc. , 585 F.2d 183 (6th Cir. 1978), and Royalite Co. v. Federal Ins. Co. , 184 Mich. App. 69, 457 N.W.2d 96 (1990), both the Sixth Circuit and the Michigan Court of Appeals held respectively that where the bond on a public cons......
  • W.T. Andrew Co., Inc. v. Mid-State Sur. Corp.
    • United States
    • Court of Appeal of Michigan — District of US
    • March 10, 1995
    ...review the matter de novo. Id.; Spruytte v. Owens, 190 Mich.App. 127, 132, 475 N.W.2d 382 (1991). Citing Royalite Co. v. Federal Ins. Co., 184 Mich.App. 69, 457 N.W.2d 96 (1990), the trial court concluded that plaintiff had given sufficient notice to the surety within ninety days of furnish......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT