Sanitary Services Corp. v. Greenfield Village Ass'n, Inc., 12421

Decision Date20 December 1994
Docket NumberNo. 12421,12421
Citation651 A.2d 269,36 Conn.App. 395
CourtConnecticut Court of Appeals
PartiesSANITARY SERVICES CORPORATION v. GREENFIELD VILLAGE ASSOCIATION, INC.

Thomas P. Moriarty, for appellant (plaintiff).

Kurt F. Zimmermann, for appellee (defendant).

Before DUPONT, C.J., and SCHALLER and SPEAR, JJ.

DUPONT, Chief Judge.

The plaintiff appeals from the judgment rendered in favor of the defendant on the trial court's granting of the defendant's motion for summary judgment. The plaintiff, a refuse collection service, brought an action against the defendant, a condominium association, alleging that the defendant had breached a written contract for refuse collection services. The plaintiff's demand for relief included damages, liquidated damages, attorney's fees, costs and interest.

The defendant moved for summary judgment, admitting a breach of the contract, but asserting two alternative theories to refute the plaintiff's claim for damages, as a matter of law. The defendant contended that the liquidated damages provision in the contract was a penalty, and, in the alternative, that if the liquidated damages provision did apply to an award of damages, then the plaintiff would be entitled to zero damages under the express terms of that provision.

The plaintiff, in opposing the defendant's motion for summary judgment, argued that the liquidated damages clause could not be enforced, and that, therefore, the plaintiff should be given an opportunity to prove actual damages, a question of fact.

The trial court concluded that, under the express terms of the liquidated damages clause, the plaintiff was not entitled to any damages. The court granted summary judgment to the defendant and stated in its memorandum of decision: "There are no damages due the plaintiff under the express terms of the contract as drafted by the plaintiff and signed by the defendant. Where the intent of the parties is expressed in language that is clear and unambiguous, the contract must be given effect according to its terms. Bialowans v. Minor, [209 Conn. 212, 217, 550 A.2d 637 (1988) ]." (Internal quotation marks omitted.) The judgment file states that the court "finds the issues for the defendant."

The plaintiff appealed, arguing that the trial court improperly applied and construed the contract's liquidated damages provision, and improperly determined, as a matter of law, that the plaintiff was not entitled to any damages. We reverse the judgment and remand the case for further proceedings.

The first question to be resolved is whether, in view of the fact that the trial court and the parties agreed that the defendant had breached the contract by notifying the plaintiff prior to the plaintiff's beginning any performance that the defendant was terminating the contract, judgment could be rendered for the defendant, the defaulting party.

" 'Practice Book § 384 provides that summary judgment "shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law." ' " Haesche v. Kissner, 229 Conn. 213, 217, 640 A.2d 89 (1994). In this case, the court should not have found, as it did, the issues for the defendant because the plaintiff had alleged and the defendant had admitted that the defendant had breached the contract. The defendant, therefore, was not entitled to judgment as a matter of law. The court's judgment should have been for the plaintiff, and, in fact, the court acted as though that were the case because it considered what damages, if any, were due to the plaintiff. 1 We, therefore, treat the case as though judgment, albeit a "Pyrrhic victory," had been rendered for the plaintiff. See Tedesco v. Stamford, 215 Conn. 450, 576 A.2d 1273 (1990), on remand, 24 Conn.App. 377, 588 A.2d 656 (1991), rev'd, 222 Conn. 233, 610 A.2d 574 (1992).

The following are relevant facts. In February, 1991, the plaintiff and the defendant entered into a written contract for refuse collection. The signed document was a two page standard form contract, supplied by the plaintiff, which included the following provision near the bottom of the second page: "LIQUIDATED DAMAGES. In the event the Customer terminates this agreement other than as provided above, 2 Customer shall pay to Contractor as liquidated damages, a sum calculated as follows: (a) if the remaining term under this agreement is six or more months, Customer shall pay the greater of its most recent monthly charge multiplied by six, or its most recent monthly charge multiplied by one half of the number of months remaining in the term. (b) if the remaining term under this agreement is less than six months, Customer shall pay its most recent charge multiplied by the number of months remaining in the term." The contract also included a handwritten sentence that stated: "First three (3) months free."

The trial court did not reach the question of actual damages, a common law contract remedy, because it determined that the contract contained a valid liquidated damages clause. Both actual damages and liquidated damages cannot be awarded. Hanson Development Co. v. East Great Plains Shopping Center, Inc., 195 Conn. 60, 64, 485 A.2d 1296 (1985); see also Vines v. Orchard Hills, Inc., 181 Conn. 501, 511, 435 A.2d 1022 (1980) (liquidated damages provisions are "private agreements to supplant judicially determined remedies for breach of contract" [emphasis added].

The plaintiff claims to be due actual damages because the liquidated damages clause could not be enforced on the facts of this case. The trial court concluded that the liquidated damages clause could be enforced but that its provisions provided the plaintiff with zero damages.

The defendant claimed, in its argument and briefs in support of its motion for summary judgment, that because the plaintiff's service under the contract was to be free for the first three months of performance, the charge for those months would be zero. Thus, the defendant argues that zero should be the amount of the "most recent monthly charge" for purposes of the computation of liquidated damages, and when multiplied by any number, as provided in the contract, damages must be zero.

"Where the language of a contract is clear and unambiguous, the contract is to be given effect according to its terms. A court will not torture words to import ambiguity where the ordinary meaning leaves no room for ambiguity and words do not become ambiguous simply because lawyers or laymen contend for different...

To continue reading

Request your trial
11 cases
  • Van Natta v. Great Lakes Reinsurance (UK) SE
    • United States
    • U.S. District Court — District of Connecticut
    • 21 Mayo 2020
    ...simply because it believes it can attack a plaintiff's claim for damages. See, e.g., Sanitary Servs. Corp. v. Greenfield Village Ass'n, Inc. , 36 Conn. App. 395, 400–01, 651 A.2d 269 (1994). "Evidence is considered speculative when there is no documentation or detail in support of it and wh......
  • Smoot v. B & J Restoration Servs., Inc.
    • United States
    • United States State Court of Criminal Appeals of Oklahoma. Court of Civil Appeals of Oklahoma
    • 16 Mayo 2012
    ...N.W.2d 739, 744 (1975) (there cannot be an award of both liquidated and compensatory damages); Sanitary Servs. Corp. v. Greenfield Village Ass'n, Inc., 36 Conn.App. 395, 651 A.2d 269, 271 (1994). By submitting the issue of damages for breach of the Restrictive Covenant to the jury it appear......
  • Ridgefield v. Eppoliti Realty Co.
    • United States
    • Connecticut Court of Appeals
    • 30 Julio 2002
    ...alleged, "[t]he amount, if any, of the [defendant's] actual damages is a question of fact." Sanitary Services Corp. v. Greenfield Village Assn., Inc., 36 Conn. App. 395, 400, 651 A.2d 269 (1994). "[T]he general rule for the measure of damages in contract is that the award should place the i......
  • Sparveri v. Town of Rocky Hill
    • United States
    • U.S. District Court — District of Connecticut
    • 4 Septiembre 2009
    ...parties. Id.; Executive Airlines v. Electric Boat Corp., 271 F.Supp.2d 392, 395 (D.Conn.2003); Sanitary Servs. Corp. v. Greenfield Village Ass'n, Inc., 36 Conn. App. 395, 399, 651 A.2d 269 (1994). 5. A party may not create ambiguity in otherwise plain language by urging different interpreta......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT