Sides v. Contemporary Homes, Inc.

Decision Date04 March 1958
Docket NumberNo. 29911,29911
CitationSides v. Contemporary Homes, Inc., 311 S.W.2d 117 (Mo. App. 1958)
PartiesHarold R. SIDES, d/b/a Acme Asphalt Paving Co., (Plaintiff) Respondent, v. CONTEMPORARY HOMES, Inc., a Corporation, and Kemp and Edwards Construction Co., a Corporation, (Defendants) Appellants.
CourtMissouri Court of Appeals

Hinkel & Carey, Clifford L. Goetz, St. Louis, for appellants.

Lloyd E. Eaker, St. Louis, for respondent.

JAMES D. CLEMENS, Special Judge.

We feel it necessary to deal first with a point raised by neither party below, and only casually here.Plaintiff sued two corporations, Contemporary Homes, Inc., and Kemp and Edwards Construction Co., alleging joint liability.The evidence of both plaintiff and defendants showed that only Contemporary Homes, Inc., was involved.Joint motions of defendants for directed verdicts were denied.This was clear error as to defendantKemp and Edwards Construction Co.The cause was submitted to the jury only as to Contemporary Homes, Inc., and the verdict was against that defendant only.For reasons for which no explanation is offered, judgment was rendered against both defendants.DefendantKemp and Edwards Construction Co. did not raise the point in the motion for new trial, which was filed jointly by both defendants.We believe the judgment against defendantKemp and Edwards Construction Co., rendered under these circumstances was a manifest miscarriage of justice.Although the point was not raised in the trial court and thus not properly preserved for review, we believe the situation calls for the application of Supreme Court Rule 3.27, 42 V.A.M.S., and the judgment will be reversed as to the inert defendant, Kemp and Edwards Construction Co.

Plaintiff asserted a contract to install 180 driveways.Defendant admitted there was an offer to install 180 driveways but claimed that it had accepted the offer only as to the installation of six driveways, for which it had paid plaintiff.Plaintiff's further services were declined, and he claimed a breach and sought damages.Plaintiff sued for $6,090 and had judgment for $750.AppellantContemporary Homes, Inc., (hereinafter called defendant) here claims error in submitting the case to the jury because there was no evidence of a contract nor of damages beyond speculation, and error in plaintiff's verdict-directing and measure of damage instructions.

Plaintiff was in the paving business.Defendant was building 175 to 180 homes in Robinwood Subdivision, St. Louis County, and wanted paved driveways to each home.On April 1, 1955, defendant's vice-president, Robert R. Edwards, called plaintiff by phone, told him of the driveways to be built, and asked for an estimate on installing asphalt driveways.Edwards told plaintiff the driveways were to be nine feet wide and 'averaged about fifty, fifty-four feet long.'Plaintiff verbally quoted defendant a price of $1.25 a square yard for applying a two-inch asphalt topping on defendant's crushed stone base, or $2.25 a yard if plaintiff furnished the base.Defendant then asked plaintiff to submit a written proposal, which he did, and two signed copies of this instrument were sent to defendant.By the written proposal, plaintiff offered to install the 180 driveways for the alternate prices mentioned, and gave specifications as to materials, quality of workmanship, and insurance.To this point the evidence is generally in agreement, but evidence of further dealings between the parties is discordant, and we must view the evidence in the light most favorable to plaintiff and reject the defendant's evidence contrary thereto.

About a week after sending the proposal plaintiff got a call from Mr. Edwards who said he'd received it and wanted 'the $1.25 job,' by which defendant would lay the foundations.Edwards then asked if plaintiff wanted him to sign a copy of the proposal and sent it back, and plaintiff told Edwards that wasn't necessary, that he trusted Edwards and would take his word for it.On cross-examination, plaintiff was asked: 'Did he say anything further about accepting the terms of the contract?'Plaintiff answered: 'He said 'I will accept it; do you want me to sign it and sent it back?'' The conversation turned to when plaintiff could start.Edwards said he had six driveways ready.Plaintiff explained that he couldn't 'come for any less than that,' and Edwards said he'd have the driveways ready 'six at a time.'Plaintiff denied that Edwards had asked him to put in the initial six driveways so defendant could see how they looked.He also said that from Edwards' offer to sign the proposal and Edwards' directions to lay the six driveways that were ready, plaintiff assumed defendant was accepting the proposal.

Defendant claims error in submitting the case to the jury because there was no evidence of a definite acceptance of plaintiff's offer, citing Brown v. Childers, Mo.App., 254 S.W.2d 275, andShofler v. Jordon, Mo.App., 284 S.W.2d 612.Those cases hold that an acceptance of a contract cannot be based alone on what one of the parties understood, but must be gathered from what the parties said and did.The trouble with defendant's argument is that its premise is based alone on plaintiff's statement that he assumed defendant was accepting the contract.The argument disregards plaintiff's testimony that Edwards said he was accepting the proposal, offered to sign and return it, told plaintiff to start on six drveways, and said that thereafter he'd have driveways ready six at a time.Whether there was a meeting of the minds is to be determined by what the parties said and did, and if the words and acts judged by a reasonable standard show an intention to agree to the matter in question, the agreement is established.Muegler v. Crosthwait, Mo.App., 179 S.W.2d 761(4).We hold that plaintiff's evidence entitled him to go to the jury on the issue of defendant's acceptance of his offer.

Defendant claims error was committed in submitting the case because there was no evidence of plaintiff's damages, beyond that which could be reached only by speculation.Plaintiff offered evidence tending to show the amount of the contract price and the amount it would have cost him to complete the contract.There were 174 uncompleted driveways, and there was an 'average of fifty to fifty-four' square yards per driveway, and the agreed price was $1.25 per square yard.Simple arithmetic could thus establish the minimum contract price of $62.50 for each driveway.Plaintiff testified as an expert as to what the cost would have been to complete the 174 driveways.He testified it would take him and his crew twenty-five minutes to pave a driveway of fifty square yards.He said that by working on as many as six driveways at a time, the cost of materials for each driveway would be $33.75, his workmen's wages would be $5.75, his machinery costs including depreciation would be $1.50, and his various insurance costs would be 50cents; all for a total cost of $41.50 for each driveway.Plaintiff's theory was that he was entitled to recover the difference of $21.50 for each of 174 driveways.

Where a construction contract is breached by the owner's refusal to permit the builder to perform, the action is basically one for the breach of a promise to pay money.SeeRestatement of the Law, Contracts, pp. 578, 579(g) where it is said:

'In order to put the builder in as good a position as he would have been in had the contract been fully performed, it is necessary to give him the full contract price less the amount that he saves by reason of the other party's repudiation * * *.'

Where an owner breaches a construction contract by preventing the builder from doing the work the plaintiff's measure of damages is the contract price, less the amount it would have cost him to complete the performance of the contract.Crescent Mfg. Co. v. N. O. Nelson Mfg. Co., 100 Mo. 325, 13 S.W. 503(3);Dement v. McNail, Mo.App., 281 S.W. 128(3).Defendant contends that plaintiff kept busy on other jobs and hence was not damaged by the breach.That is true in instances of contracts for personal services, 56 C.J.S.Master and Servant§ 59;Wessler v. City of St. Louis, Mo.App., 242 S.W.2d 289(2).But here, such subsequent gains were not the result of the defendant's breach and do not inure to the benefit of the defendant.Restatement of the Law, Contracts, p. 578;Grinnell Co. v. Vorhees, 3 Cir., 1 F.2d 693.Evidence of such subsequent profits is not admissible in construction contract cases.Crescent Mfg. Co. v. N. O. Nelson Mfg. Co., supra.

In urging the inadequacy of evidence as to damages, the defendant relies on the rule that anticipated profits are recoverable only upon showing of reasonable certainty, citing Wandell v. Ross, 241 Mo.App. 1189, 245 S.W.2d 689.That case and the rule therein relied upon apply to the anticipated profits which might have been made from the over-all operation of a going business.

We believe that the cases on recovery of special damages for anticipated profits of a going business must be distinguished from those where a builder seeks recovery of the gains he would have made but for having been prevented by the owner from performing a specific contract.In the former, a multitude of variable factors enter into the computation, and the courts are strict in evaluating the sufficiency of the evidence.Spruce Co. v. Mays, 333 Mo. 582, 62 S.W.2d 824(6);Tnemec Co. v. North Kansas City Development Co., Mo.Sup., 290 S.W.2d 169(5).In the latter type of case, only the contractor's cost of completing the work is uncertain, and this is a less complicated issue.As said in Kerns & Lorton...

Get this document and AI-powered insights with a free trial of vLex and Vincent AI

Get Started for Free

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex

Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant

  • Access comprehensive legal content with no limitations across vLex's unparalleled global legal database

  • Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength

  • Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities

  • Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting

vLex
23 cases
  • Anderson v. Welty, 7793
    • United States
    • Missouri Court of Appeals
    • 29 Marzo 1960
    ...766, 771(6).10 Supreme Court Rule 1.08, 42 V.A.M.S.; Catanzaro v. Duzer, Mo.App., 329 S.W.2d 257, 261(7); Sides v. Contemporary Homes, Inc., Mo.App., 311 S.W.2d 117, 121-122(10); Lewis v. Watkins, Mo.App., 297 S.W.2d 595, 597; Smyth v. City of St. Joseph, Mo.App., 297 S.W.2d 578, 582(6); Ge......
  • Groh v. Shelton
    • United States
    • Missouri Court of Appeals
    • 20 Mayo 1968
    ...have no duty to seine through the entire brief in an effort to ascertain the points on which an appellant depends. Sides v. Contemporary Homes, Mo.App., 311 S.W.2d 117, 122; Beeler v. Board of Adjustment of City of Joplin, Mo.App., 298 S.W.2d 481, 483(2). But being mindful that 'our primary......
  • State ex rel. State Highway Commission v. Warner
    • United States
    • Missouri Court of Appeals
    • 10 Octubre 1962
    ...has no duty to seine through the entire brief in an effort to ascertain the points on which an appellant depends. Sides v. Contemporary Homes, Mo.App., 311 S.W.2d 117, 122; Beeler v. Board of Adjustment of City of Joplin, Mo.App., 298 S.W.2d 481, The salutary purpose of, and the urgent need......
  • Hoover v. Whisner
    • United States
    • Missouri Court of Appeals
    • 2 Diciembre 1963
    ...has no duty to seine through the entire brief in an effort to ascertain the points on which an appellant depends. Sides v. Contemporary Homes, Mo.App., 311 S.W.2d 117, 122; Beeler v. Board of Adjustment of City of Joplin, Mo.App., 298 S.W.2d 481, 483(2). The quoted 'points' in instant defen......
  • Get Started for Free
3 books & journal articles
  • Section 16 Proving the Extent of Loss
    • United States
    • The Missouri Bar Practice Books Damages Deskbook Chapter 14 Loss of Profits
    • Invalid date
    ...that would have occurred from performance are saved by the nonperformance, they must be deducted, Sides v. Contemporary Homes, Inc., 311 S.W.2d 117 (Mo. App. E.D. 1958), just as increased expenses over earlier periods that would have been required in completing performance must be deducted,......
  • Section 8 Damages That Are Natural and Probable Result
    • United States
    • The Missouri Bar Practice Books Damages Deskbook Chapter 14 Loss of Profits
    • Invalid date
    ...is to earn a profit, the profit is the natural and probable result of the performance. See, e.g., Sides v. Contemporary Homes, Inc., 311 S.W.2d 117 (Mo. App. E.D. 1958).Anticipated profits, however, are not generally recoverable because they are too uncertain, speculative, and dependent on ......
  • Section 10 Rules in Specific Cases
    • United States
    • The Missouri Bar Practice Books Damages Deskbook Chapter 14 Loss of Profits
    • Invalid date
    ...contract. See, e.g., Juengel Constr. Co. v. Mt. Etna, Inc., 622 S.W.2d 510, 514 (Mo. App. E.D. 1981); Sides v. Contemporary Homes, Inc., 311 S.W.2d 117, 120 (Mo. App. E.D. 1958).On the other hand, when a purchaser refuses to purchase land, the measure of damage is simply the difference betw......