Smith v. Robinson

Decision Date01 May 1979
Docket NumberNo. 50959,50959
Citation594 P.2d 364
PartiesJ. E. SMITH, d/b/a Midwest and Komantica Construction Co., Appellant, v. Roberta D. ROBINSON, Individually, and Roberta D. Robinson, Successor in Interest of the Estate of William M. Robinson, and Virginia D. Holland, Appellees.
CourtOklahoma Supreme Court

On certiorari to the Court of Appeals, Division 1.

In a mechanic's and materialman's lien foreclosure suit where cash and bond stood, pursuant to 42 O.S.1971 § 147, as substituted security, District Court, Tulsa County, Hon. Richard Comfort, trial judge, entered judgment for contractor in the amount previously tendered by landowner to whom attorney's fee and costs were awarded. Court of Appeals reversed and awarded contractor an attorney's fee.

Certiorari granted, Opinion of Court of Appeals vacated and trial court's judgment affirmed.

Williams, Paddock & Dale by William J. Dale, Tulsa, for appellant.

Bruce Miller Townsend, Tulsa, for appellee, Roberta D. Robinson.

Smith, Brown, Martin, Adkisson & Birmingham by Darven L. Brown, Tom A. Mann, Tulsa, for appellee, Virginia D. Holland.

OPALA, Justice:

In this case we are called upon the answer the following questions: (a) is a landowner's pre-suit tender to contractor in redemption of the premises from a mechanic's and materialman's lien sufficient in law although it fails to include two expense items incurred in the filing of the lien? 1 (b) if the tender so made, though adequate in law, be met with refusal and landowner then discharges the lien by complying with the procedure set forth in 42 O.S.1971 § 147 2, does the prior tender continue to shield him from liability for court costs, including contractor's counsel fee, when contractor recovers in foreclosure suit the full amount claimed in the lien? and (c) if the landowner's pre-suit tender does in fact protect him from liability for costs, may he as the "prevailing" party, within the meaning of 42 O.S.1971 § 176, recover against the contractor for the services of his own attorney?

The trial court resolved all these issues in favor of the landowner. The Court of Appeals reversed and awarded an attorney's fee to the contractor. We granted certiorari to settle what appear, in the context presented, to be questions of first impression.

The material facts none in dispute have their inception in a July 7, 1976 oral landowner/contractor agreement to provide labor and materials on the premises for $655.00. For the work, completed that day an invoice was rendered July 20 3 and a mechanic's and materialman's lien for the unpaid contract price was filed August 6.

Landowner's initial pre-suit offer to pay the lien claim in full occurred August 11. It was coupled with a comment about "a small minor detail" that remains undone and a demand for "lien waivers from all persons working on the job." Though contractor responded by providing his affidavit that negates the existence of any "unpaid bills" which would constitute "lienable claims" against the premises, he refused the offer because its amount did not include the $2.00 filing fee for the lien and the $50.00 fee for attorney's services. On the very same ground contractor refused landowner's second pre-suit offer of $655.00 made in unconditional terms on September 15. 4 Two months later (November 15) landowner discharged the lien in compliance with the procedure prescribed in 42 O.S.1971 § 147 by depositing in court the amount of the claim ($655.00) in cash and posting a bond with penalty in the same amount for attorney's fee and costs.

The foreclosure suit under review was filed November 22. In her answer, which sets up in detail all the rejected pre-suit offers to pay the $655.00 lien claim, landowner did "again tender into court and offer judgment to be taken" for that amount but without costs. Included in the prayer is her plea for a reasonable attorney's fee to be taxed against contractor.

Since landowner's August 11 offer could be termed as conditional in form, there may be some question about its sufficiency as a "tender". In its strict, technical sense tender of money must be an unconditional offer by obligor to pay the obligee. 5 We need not concern ourselves here with the efficacy of the August 11 act because the second pre-suit offer of September 15 doubtless meets the legal requirements of a "legal tender" if its amount was sufficient (although it did not include the two items of lien-filing expense). Nor are we called upon to decide whether contractor's admitted refusal of this tender operated in law to discharge his lien. 6 While under some circumstances a lien discharge may result by force of law from an obligee's rejection of a valid tender, that question is not before us. 7 Neither here nor below did landowner urge that this consequence should be attached to contractor's rejection of his tender.

By the terms of 42 O.S.1971 §§ 18 and 20 a person may redeem his property from a lien by offering to pay the obligation for which the lien stands as security together with allowable "damages for delay". This is the very amount landowner tendered in her redemption attempt. This much and nothing more is statutorily required to effect a valid redemption in advance of a suit. Absent a different contractual arrangement, damages recoverable for breach of obligation to pay money only is the amount due, with interest thereon. 23 O.S.1971 § 22.

There is here no claim that interest was due on September 15. Contractor's sole argument is that he was entitled to the lien-filing expenses. We are constrained to hold that inasmuch as landowner had neither contractual liability for payment of contractor's attorney's fee and lien filing costs nor for any interest asserted to be due, her pre-suit tender of September 15 in the principal amount of the admitted obligation was sufficient in law to redeem the premises from the lien. 8

Landowner's subsequent actions, all consistent with her September 15 offer, entitle her to the benefits of her pre-suit legal tender. Our law is clear that where, as here, obligee's recovery does not exceed the amount of the tender, a legal tender will operate to relieve the debtor of liability for interest accruing thereafter and for costs afterwards incurred. 9

Contractor's claim to an attorney's fee seems to be based on his argument that the terms of 42 O.S.1971 § 147 assure him of "a reasonable attorney's fee" upon recovery of "the full amount of the cash deposited". We cannot accede to that view. The cited section may not be invoked to negate the effect of a pre-suit tender. A contrary holding would effectively defeat a...

To continue reading

Request your trial
3 cases
  • Phillips Petroleum Company v. Shutts, 84-233
    • United States
    • U.S. Supreme Court
    • June 26, 1985
    ...Tit. 15, § 266 (Supp.1984-1985); Rendezvous Trails of America, Inc. v. Ayers, 612 P.2d 1384, 1385 (Okla.App.1980); Smith v. Robinson, 594 P.2d 364 (Okla.1979); West Edmond Hunton Lime Unit v. Young, 325 P.2d 1047 Additionally, petitioner points to an Oklahoma statute which excuses liability......
  • Allen v. State ex rel. Bd. of Trustees of Oklahoma Uniform Retirement System for Justices and Judges, 66522
    • United States
    • Oklahoma Supreme Court
    • September 20, 1988
    ...was prevented by the other party).29 See Hooper v. Commercial Lumber Company, Okl., 341 P.2d 596, 598 [1959].30 See Smith v. Robinson, Okl., 594 P.2d 364, 367 [1979] (interest was suspended by the landlord's refusal to accept tender for rent) and Abraham v. Stewart Bros. Cotton Co., 165 Okl......
  • Benefiel v. Boulton
    • United States
    • Oklahoma Supreme Court
    • May 12, 2015
    ...and on May 30, 2013, COCA issued a substitute opinion reversing the trial court's judgment. Relying on our holding in Smith v. Robinson, 1979 OK 57, 594 P.2d 364, COCA found that Boulton's payment of the $5,000.00 judgment lien amount with interest was sufficient to “redeem the real propert......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT