Southern Surety Co. v. Nalle & Co.

Decision Date16 May 1921
Docket Number(No. 6223.)
Citation231 S.W. 402
PartiesSOUTHERN SURETY CO. v. NALLE & CO. et al.
CourtTexas Court of Appeals

Appeal from District Court, Travis County; Geo. Calhoun, Judge.

Action by Nalle & Co. and others against the Southern Surety Company. Judgment for plaintiffs, and defendant appeals. Affirmed.

Barrett, Eskridge & Barrett, of San Antonio, and Hart & Patterson, of Austin, for appellant.

Brooks, Hart & Woodward, W. A. Barlow, Samuel B. Dickens, and Fiset & Shelley, all of Austin, Mantor & Briggs, Critz, Lawhon & McNair, and S. I. Reinhardt, all of Taylor. Holloway & Holloway, of Dallas, and W. D. Caldwell, of Fort Worth, for appellees.

On Motion for Rehearing.

JENKINS, J.

As the Supreme Court, since our original opinion herein was written, has held that Rev. St. art. 5623a, as added by Laws 1915, c. 143, § 2 (Vernon's Ann. Civ. St. Supp. 1918, art. 5623a), is unconstitutional, we withdraw that opinion, and substitute the opinion herein for same, and also for our opinion on rehearing, which will be incorporated herein.

Findings of Fact.

On March 23, 1917, Howard Bland, T. W. Marse, and A. J. Zilker, hereinafter called the "owners," entered into a contract with John W. Hood, John W. Hood, Jr., F. J. Strassel, and F. Greenwell, composing the Capital City Building Company, hereinafter referred to as the contractors, for the erection of a three-story fireproof hotel building, on certain lots in the town of Taylor, Williamson county, in accordance with plans and specifications drawn by Henry T. Phelps, architect, for the sum of $47,825. The contractors were to provide and pay for all material and work done, and complete the building in 125 days. Payments to the amount of 85 per cent. of the work done and material placed on the ground were to be made on the 1st and 15th days of each month, as the work progressed.

Of even date with the contractor, the contractors executed to the owners a bond, in the sum of $23,912.50, with the Southern Surety Company, hereinafter referred to as the "surety company," as surety, conditioned for the faithful performance of the contract, and specially that those who furnish material for or performed labor thereon should be paid for same, and might bring suit thereon as though specially mentioned therein. F. M. Coleman, of San Antonio, was the general agent of the surety company. The contractors entered at once upon the performance of their contract.

On May 10, 1917, the owners formed a corporation, under the name of the Blazilmar Hotel Company, hereinafter called the "hotel company," and subscribed for all of the stock of said hotel company, and thereafter remained the sole owners of such stock.

On the 10th day of May, 1917, the owners conveyed the lots upon which the hotel was to be built, and the contract for building the same, to the hotel company. On August 3, 1917, the hotel company entered into a contract with the contractors wherein it was agreed that they should build a fourth story to the hotel, and receive for the walls thereof $8,211.55, with the option of the hotel company to have the same finished in accordance with the specifications for the third story; for which, if so finished, the contractors were to be paid the further sum of $6,740.45. This contract declared that it was a part of the original contract, and the work was to be done as therein provided, and the time for the completion of the building was extended 45 days.

The surety company had no knowledge of the execution of the contract for the fourth story at the time of its execution. It did, however, learn that a fourth story was being added, and received additional pay, by reason of the increased cost of the fourth story.

On or about the _____ day of _____, 1917, the contractors assigned to the surety company all funds and estimates due or to become due for work done or material furnished, or to be furnished or done in the performance of their contract; and on April 20, 1917, the contractors and the surety company notified the owners of such assignment, and that thereafter all money due on said contract should be paid to the surety company, which was done, including work and material for the fourth story.

The contractors abandoned work on the hotel, and the same was finished by the hotel company at a loss of $1,343.69.

The following parties intervened in this cause, and there was due them by the contractors, at the time of the trial hereof, the amounts set opposite their respective names, to wit: The Blazilmar Hotel Company, $1,343.69; Nalle & Co., $5,107.25; James A. Thompson, $2,954.62; F. B. Seward, $239.13; Fairchild Lumber Company, $454.31; Prewitt Hardware Company, $345.60; Elgin Standard Brick Company, $518; J. Desco & Son, $1,499.85; Torbett & Germond Company, $410.06; C. M. Gossett, $464.33; K. J. Peterson, $48.10; Federal Glass & Paint Company, $828.15; Mosher Manufacturing Company, $350; Southern Architectural Cement Stone Company, $165; Austin Builders Supply Company, $160.85. For which sums the court rendered judgment against the contractors, in favor of said respective parties. Judgment was also rendered in favor of said parties for said respective amounts against the surety company.

The case was tried before the court without a jury. The court filed findings of fact and conclusions of law.

Opinion.

On authority of Williams v. Baldwin, 228 S. W. 557, not yet officially published, we sustain appellant's assignments to the effect that the following portion of the Act of March 31, 1915, art. 5623a, is unconstitutional, to wit:

"No change or alteration in the plans, building, construction or method of payment shall in any way avoid or affect the liability on said bond, and the sureties on said bond shall be limited to such defenses only as the principal on said bond could make." R. S. art. 5623a.

The plans and specifications, which are referred to in the contract and made a part thereof, contain the following clause:

"The owners reserve the right, by conferring with the superintending architect, to alter or modify the plans and this specification in any particular, and the architect shall be at liberty to make any deviation in the construction, detail or execution without in either case invalidating or rendering void the contract, and in case any such alteration shall increase or diminish the cost of doing the work, the amount to be allowed to the contractor or owner shall be such as may be equitable and just, and be determined by the architect."

It has long been customary to insert similar provisions in builder's contracts. This, in part at least, has been occasioned by the rule of strictissimi juris, adopted by courts in reference to sureties, whereby the surety was released if "any" change was made in the contract, though the same may have been immaterial and in nowise to his detriment. By a provision in the contract similar to that above set out, the surety agrees in advance that "some" changes may be made in the contract. What changes? Not necessarily immaterial ones. They might be very material without avoiding the contract, as for instance in the cost of construction. Stocking v. Fouts (Wash.) 169 Pac. 595, in which the increase in the cost was 20 per cent., though, as said in Doyle v. Faust, 187 Mich. 108, 153 N. W. 725, "there is a * * * limit beyond which, if alterations are made, the surety will be released." The question in all such cases is: What alterations were in contemplation of the parties, as evidenced by the language used in the contract, read in the light of what changes are frequently found to be desirable during the construction of buildings?

We think the test is: Do the changes "alter or modify the plans and specifications" of the building contracted to be erected, or do they amount to a contract for a different building? As has been said: Do the changes destroy the identity of the building?

It was held in the following cases, in which the contracts provide for changes substantially as in the instant case, that the changes did not amount to a new contract, nor release the surety: Dorsey v. McGee, 30 Neb. 657, 46 N. W. 1018 (the change was an addition of a stairway, a change in the character of the hardware, and the location of the cistern); Stocking v. Fouts, supra (the change was in the interior finish); Milavetz v. Oberg, 138 Minn. 215, 164 N. W. 912 (the contract required the changes to be ordered in writing; they were ordered orally); Doyle v. Faust, supra (the change was in the partition walls, windows, and chimney). In Stocking v. Fouts, supra, the court said:

"There was no change in the outward appearance and design of the building, its size, main walls, foundations or floors."

In Doyle v. Faust, supra, it is said:

"There was no change in the character or exterior dimensions of the building."

In the following cases it was held that the changes released the surety: House v. Surety Co., 21 Tex. Civ. App. 590, 54 S. W. 303 (the change was from a three to a four story building); Miller v. Ice Co., 66 Ark. 287, 50 S. W. 508 (the change was from a one-story to a two-story building); Rhodes v. Clute, 17 Utah, 137, 53 Pac. 990 (the change was from a frame to a brick building, nearly doubling the cost); Sweatt v. Bonne, 60 Wash. 18, 110 Pac. 617 (a two-story building and a cellar were added); Contracting Co. v. Hudson River Co., 192 N. Y. 209, 84 N. E. 965 (the change was from a masonry to an earth dam with a masonry core).

In House v. Surety Co., supra, the court said:

"The identity of the building was destroyed."

In Rhodes v. Clute, supra, the court said:

They (the changes) were so variant, "both in price and construction, as to amount to an abandonment of the contract, and the creation of a new one."

Many other cases in point might be cited, but these are sufficient to show the correctness of the test hereinbefore stated. Applying this test to the instant case, we do not think that a four-story building is a...

To continue reading

Request your trial
4 cases
  • Southern Surety Co. v. Nalle & Co.
    • United States
    • Texas Supreme Court
    • June 12, 1922
    ...the contractor and against the Southern Surety Company as surety on the contractors' bond was affirmed by the Court of Civil Appeals, 231 S. W. 402, and the Southern Surety Company brings error. Reversed, and cause remanded to the district court for another Hart & Patterson, of Austin, and ......
  • Lamson v. Maryland Casualty Co.
    • United States
    • Iowa Supreme Court
    • June 22, 1923
    ...House v. American Surety Co., 21 Tex. Civ. App. 590 (54 S.W. 303); Sweatt v. Bonne, 60 Wash. 18 (110 P. 617); Southern Surety Co. v. Nalle & Co., (Tex. Civ. App.) 231 S.W. 402; United States Poe, 138 Md. 466 (114 A. 705). In but one of the cases last cited was the word "additions" used in t......
  • Lamson v. Md. Cas. Co.
    • United States
    • Iowa Supreme Court
    • June 22, 1923
    ...v. American Surety Co., 21 Tex. Civ. App. 590, 54 S. W. 303;Sweatt v. Bonne, 60 Wash. 18, 110 Pac. 617;Southern Surety Co. v. Nalle & Co. (Tex. Civ. App.) 231 S. W. 402;United States v. Poe, 138 Md. 466, 114 Atl. 705. In but one of the cases last cited was the word “additions” used in the c......
  • Johnson v. Gattegno
    • United States
    • Texas Court of Appeals
    • October 29, 1924
    ...Civil Appeals the majority of that court ruled contrary to the conclusion of the Commission of Appeals, Chief Justice Key dissenting. See 231 S. W. 402. An examination of the majority and dissenting opinions in the Court of Civil Appeals will serve to emphasize the far-reaching effect of th......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT