State ex rel. Town Concrete Pipe, Inc. v. Andersen

Decision Date01 February 1973
Citation264 Or. 565,96 Or.Adv.Sh. 575,505 P.2d 1162
PartiesSTATE of Oregon, acting through its State Highway Division, ex rel. TOWN CONCRETE PIPE, INC., a corporation, Appellant, v. H. A. ANDERSEN et al., Respondents.
CourtOregon Supreme Court

David J. Buono, Portland, argued the cause for appellant. With him on the brief were Norman L. Lindstedt and Buss, Leichner, Lindstedt & Barker, Portland.

Warde Erwin, Portland, argued the cause for respondents. With him on the brief were Erwin & Gilbert, Portland.

Before O'CONNELL, C.J., and McALLISTER, DENECKE, TONGUE, HOWELL and BRYSON, JJ.

DENECKE, Justice.

This case is an attempt by the plaintiff, Town Concrete Pipe, to hold the defendant General Insurance Company, the surety on the bond of a joint venture performing a state construction project, for a debt owed plaintiff for materials furnished a subcontractor of the joint venture. The trial court, sitting without a jury, held for the surety and plaintiff appeals.

In 1969 the legislature amended the statute and provided that before an unpaid materialman of a subcontractor could recover from the general contractor or its surety, the materialman had to notify the general contractor within 90 days after delivery that the materialman was supplying the subcontractor. ORS 279.526(2). This law became effective August 22, 1969. Plaintiff began deliveries in June 1969 and finished February 28, 1970. No notice was given until February 18, 1970. One issue is, to what deliveries does the notice requirement apply?

The statute contains no language indicating whether the legislature intended the act to apply retroactively. The legislative history likewise provides no insight.

In Joseph v. Lowery, 261 Or. 545, 495 P.2d 273, 274--275 (1972), we quoted with approval from Kempf v. Carpenters & Joiners Local Union, 229 Or. 337, 341--342, 367 P.2d 436 (1961), as follows:

"* * * Unless retroactive construction is mandatory by the terms of the act it should not be applied if such construction will impair existing rights, create new obligations or impose additional duties with respect to past transactions * * *.' 229 Or. at 343, 367 P.2d 436.'

We then explained the law:

'The cases discussed above clearly indicate that this court has refused to give retroactive application to the provisions of statutes which affect the legal rights and obligations arising out of past actions. This is without respect to whether the change might be 'procedural or remedial' or 'substantive' in a strictly technical sense. The labels were applied after the court decided whether it thought a new statute affected legal rights and obligations arising out of past actions.' 495 P.2d at 275.

The notice requirement added by the legislature imposed 'additional duties with respect to past transactions.' The requirement affects the 'legal rights and obligations arising out of past actions.' For these reasons the statute does not apply to those deliveries made before August 22nd. Cf. Dean Vincent, Inc. v. Chamberlain, 96 Or.Adv.Sh. 223, 504 P.2d 722, decided December 21, 1972, and Ainslie & Co. v. Kohn, 16 Or. 363, 19 P. 97 (1888).

Prior to the effective date of the amendment plaintiff entered into an agreement with its subcontractor to supply all the materials for the job. Plaintiff makes some contention that because the agreement to supply the materials was made before the effective date of the act, the act should not be interpreted to apply to any of the deliveries whether made before or after August 22nd. In amending the notice requirement of the Miller Act, 40 U.S.C.A. § 270b, which is the federal counterpart of the Oregon Public Works Statute, Congress expressly provided that amendment would not apply to contracts signed prior to the effective date of the amendment. The Oregon statute does not so provide and the statute is not written in terms of contracts to supply materials.

We hold that the statute applies to all deliveries made after August 22, 1969. Plaintiff cannot recover for those deliveries made after that date and more than 90 days before the notice was given.

The defendants contend that the February 18, 1970, notice of plaintiff's deliveries was insufficient to satisfy the requirements of the amendment. ORS 279.526, as amended, provides that the 'notice shall be served on the contractor personally or by certified or registered mail.' The notice was sent regular mail, but admittedly received by the joint venture.

Defendants attempt to distinguish Stroh v. SAIF, 261 Or. 117, 492 P.2d 472 (1972), we, nevertheless find its principle controlling and hold the notice was effective.

ORS 279.526(1) requires another notice. It provides that a claimant who has supplied materials or performed labor for either the general or subcontractor on Oregon public works must file a notice of claim with the public body 'prior to the expiration of six months immediately following the acceptance of the work by the affirmative action of the public body which let the contract.' The notice in this case was filed prior to the acceptance of the joint venturer's work. We held in Konen Const. Co. v. United States Fid. & Guar. Co., 234 Or. 554, 557--558, 380 P.2d 795, 382 P.2d 858 (1963), that the notice of a subcontractor who has completed his work can be properly filed before the acceptance of the overall project by the public body.

ORS 279.528 concerns the contents of the notice of claim. It provides: '(2) The notice shall be in writing substantially as follows:'. The statute then provides that the notice is to be sent to the state contracting agency, in this case, the State Highway Commission. Plaintiff sent several letters about its claim to the joint venture and its surety with copies to the Highway Commission. The plaintiff did not prove that the commission received copies of these letters; however, plaintiff sent one notice to the commission by certified mail which the commission received.

The suggested statutory form requires, 'a brief description of the labor or materials performed or furnished and the person by whom performed or furnished.' The letter received by the commission stated: 'The claim of our client is for materials supplied and incorporated into the project in question.' This is a minimal description; however, we find it was adequate to comply with the statute. As we stated in School District No. 1 v. Rushlight & Co., 232 Or. 341, 348--351, 375 P.2d 411 (1962), the purpose of this notice is to alert the public body and general contractor to unpaid bills before any retainage is paid out. The retainage, therefore, can be used to pay the unpaid suppliers and laborers. With the notice given, the commission or the general contractor can secure the details of the claim and dispose of the retainage accordingly.

ORS 279.528(2) also suggests that the notice to the commission state the name of the surety. The plaintiff, in giving the commission notice of claim, asked the commission for the name of the surety and a copy...

To continue reading

Request your trial
6 cases
  • North Marion Sch. Dist. #15 v. Acstar Ins.
    • United States
    • Oregon Court of Appeals
    • July 5, 2006
    ...on contractors' bonds. Hillsboro v. Maint. & Const. Serv., 269 Or. 169, 172, 523 P.2d 1036 (1974); see also State ex rel Town Concrete v. Andersen, 264 Or. 565, 505 P.2d 1162 (1973). In other words, it is inferable from the text of the amendments that the intent of the legislature in amendi......
  • Morgan v. Morgan
    • United States
    • Oregon Court of Appeals
    • March 12, 1973
    ...concur in the majority opinion's conclusions as to the effect of Oregon Laws 1971, ch. 280, § 29. See, State ex rel. Town Concrete v. Andersen, 96 Or.Adv.Sh. 575, 505 P.2d 1162 (1973). See also, Sharp v. Sharp, Or.App., 96 Adv.Sh. 1192, 507 P.2d 417, decided this day. Nevertheless, I concur......
  • Adamson v. West Valley Associates, Inc.
    • United States
    • Oregon Supreme Court
    • January 15, 1976
    ...a new trial procedure after the parties had already tried their cause under the then existing law. See State ex rel Town Concrete v. Andersen, 264 Or. 565, 568, 505 P.2d 1162 (1973); Joseph v. Lowery, 261 Or. 545, 547--49, 495 P.2d 273 (1972). See also 2 Sutherland, Statutory Construction §......
  • Wick v. State Acc. Ins. Fund, 75-1827
    • United States
    • Oregon Court of Appeals
    • December 4, 1978
    ...of restrictions on worker's compensation recovery against third persons not given retroactive effect); State ex rel. Town Concrete v. Andersen, 264 Or. 565, 505 P.2d 1162 (1973) (requirement of notice by materialman as condition of recovery not given retroactive effect); State ex rel. Riley......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT