Storms, Inc. v. Mathy Constr. Co.

Decision Date17 August 2016
Docket NumberNo. A15–0484.,A15–0484.
Citation883 N.W.2d 772
PartiesSTORMS, INC., Respondent, v. MATHY CONSTRUCTION CO., Appellant.
CourtMinnesota Supreme Court

Scott M. Flaherty, Daniel N. Moak, Cyrus C. Malek, Jordan L. Weber, Briggs & Morgan, P.A., Minneapolis, MN; and Michael A. Murphy, Hammell & Murphy, P.L.L.P., Caledonia, MN, for respondent.

Bruce Jones, Patrick J. O'Connor, Faegre Baker Daniels, LLP, Minneapolis, MN; and Justin W. Peterson, Moen Sheehan Meyer, Ltd., LaCrosse, Wisconsin, for appellant.

Erik M. Johnson, Assistant Attorney General, St. Paul, MN, for amicus curiae State of Minnesota Commissioner of Transportation.

Robert J. Huber, Stinson Leonard Street LLP, and Dean B. Thompson, Fabyanske, Westra, Hart & Thomson, P.A., Minneapolis, MN, for amici curiae Associated General Contractors of Minnesota and Minnesota Asphalt Pavement Association.

OPINION

LILLEHAUG

, Justice.

This dispute is about a general contractor's change order that reduced the subcontract price on a public highway project. The Minnesota Department of Transportation (MnDOT) contracted with Mathy Construction Company (Mathy) for a highway-repair project in Houston County. Mathy subcontracted with Storms, Inc. (Storms) for excavation and fill work.

After the project was under way, MnDOT's project engineer discovered errors in the estimated quantities of excavation and fill required for Storms' work. After Storms completed its work, MnDOT issued a deductive change order1 reducing Mathy's contract amount by $327,064.42. Mathy reduced Storms' subcontract by the same amount. Alleging that Mathy's corresponding deductive change order breached the subcontract, Storms sued Mathy for the reduction in the subcontract price.

On cross-motions for summary judgment, the district court granted Storms' motion, concluding that Mathy had breached the subcontract. But the district court reserved judgment on the question of damages. After a bench trial, the district court concluded that Storms was entitled to recover its fixed costs, but had failed to present evidence to support its claim and thus failed to meet its burden of proof. The court of appeals affirmed in part, holding that Mathy had breached the subcontract. But it reversed in part and remanded, concluding that the district court erred on its damages analysis. We granted review. Because we conclude that Mathy did not breach the subcontract, we reverse the court of appeals and remand to the district court.

On January 28, 2011, MnDOT solicited bids from contractors on a project to repair portions of Minnesota Highways 44 and 76 in Houston County. Mathy, a general contractor, decided to bid. Mathy solicited bids from prospective subcontractors, which were provided copies of MnDOT's Statement of Estimated Quantities. That document laid out the quantities of materials that would be required for the project. Storms submitted a bid to Mathy that was based on the information in the Statement of Estimated Quantities. Mathy used Storms' bid and secured the general contract with MnDOT.

Mathy and Storms then entered into a subcontract. They agreed that the Highway 44 portion of the project was to be completed by May 2011, and the Highway 76 portion by August 2011. Mathy agreed to pay Storms $1,007,890.79 for the work. Section 2 of the subcontract incorporated the terms of the general contract, including MnDOT's Standard Specifications for Construction. Section 12 of the subcontract provided that [w]here a provision of the General Contract is inconsistent with the provision of this Subcontract, this Subcontract shall govern.”

When Storms began work on May 16, 2011, it quickly became apparent to Storms, Mathy, and MnDOT that much smaller quantities of material were required than the amounts listed in the Statement of Estimated Quantities. Storms completed its work on May 26, 2011.

MnDOT's project engineer reviewed MnDOT's quantity estimates and concluded that they were incorrect. MnDOT recalculated the quantities. In June 2011, MnDOT informed Mathy of the errors in the Statement of Estimated Quantities and its recalculation.

In November 2011, MnDOT, Mathy, and Storms met to discuss payment for the miscalculated quantities. MnDOT informed Mathy and Storms that it was reducing the contract price, but that Storms, presumably through Mathy, could apply to MnDOT to recover its fixed costs incurred as a result of the change. MnDOT requested that Storms furnish proof of its fixed costs. Storms did not do so.

In January 2012, Mathy submitted a request to MnDOT for payment of the full price in the original contract. MnDOT, Mathy, and Storms met again to discuss payment, but did not reach a resolution.

On May 11, 2012, MnDOT issued a deductive change order that limited payment to Mathy for Storms' work to the actual quantity of material on the project and reduced the general contract price by $327,064.42. By change order, Mathy passed on the decrease to Storms. Storms sued Mathy for breach of contract in order to recover the original subcontract price.

Mathy moved for summary judgment, claiming that under MnDOT Specification 1901, which allows MnDOT to order a change in material quantities, the corresponding reduction in the subcontract price did not constitute a breach. Storms responded with a cross-motion for summary judgment, arguing that Mathy had failed to comply with MnDOT Specification 1402, which requires that alterations in the scope of a project be issued during the course of the work. In January 2014 the district court filed an order for partial summary judgment concluding that Specification 1402 applied and that Mathy had breached the subcontract. The court scheduled the matter for a bench trial on the issue of damages. See Storms, Inc. v. Mathy Construction Co., No. 28–CV–13–235, Order (Hous. Cty. Dist. Ct. filed Jan. 8, 2014).

After the bench trial, the district court reached somewhat different conclusions than in the summary judgment order. Specifically, the court noted that at the time of the summary judgment order, it had not been provided with a MnDOT affidavit, nor had the parties provided the relevant 2005 versions of the MnDOT Specifications in their entirety. Storms, Inc. v. Mathy Construction Co., No. 28–CV–13–235, Order at 3 (Hous. Cty. Dist. Ct. filed Oct. 8, 2014). Based on the new evidence received at the bench trial, the court concluded that Specification 1402 was inapplicable to this case. Id. at 4. Instead, the court determined that Specification 1901 applied, and that therefore Storms was entitled only to its fixed costs under MnDOT Specification 1903.2(A).2 Id. at 5. The court also concluded that, based on the available evidence:

[Storms] failed to present any evidence regarding fixed costs. [Storms] failed to meet the burden of proving damages. [Storms] presented no evidence of costs he incurred that did not vary depending on quantity. The damages sought by [Storms] were either initially paid by [Mathy], such as materials and trucking, or were items that would have been affected by a change in quantities.

Id. at 9. Accordingly, the district court dismissed Storms' claim for damages. Id. at 11.

Storms appealed, arguing that the district court erred by not awarding Storms the full subcontract price. Mathy filed a notice of related appeal arguing that the district court erred in holding that Mathy had breached the subcontract. The court of appeals affirmed in part and reversed in part. See Storms, Inc. v. Mathy Construction Co., No. A15–0484, 2015 WL 7693550 (Minn.App. Nov. 30, 2015)

. The court of appeals agreed with the district court's holding that Mathy had breached the subcontract, but based its decision on what it called the “plain language” of the subcontract rather than on Specification 1402. Id. at *5. The court also reversed the district court's denial of damages and remanded the matter for further proceedings on “contract damages.” Id. We granted Mathy's petition for review.

As a preliminary matter, Storms asserts that we should dismiss Mathy's appeal as improvidently granted. We see no reason to revisit our decision to grant review. The record is adequate to resolve the issues presented, and how we interpret MnDOT's Specifications has statewide impact. See Minn. R. Civ.App. P. 117, subd. 2

.

I.

We must decide whether Mathy breached its subcontract with Storms. Storms argues that Mathy cannot pass on to Storms MnDOT's deductive change order. Mathy, of course, disagrees.

On appeal from summary judgment, we review de novo “whether there are any genuine issues of material fact and whether the district court erred in its application of the law to the facts.” Commerce Bank v. W. Bend Mut. Ins. Co., 870 N.W.2d 770, 773 (Minn.2015)

. Whether language in a contract is plain or ambiguous is a question of law that we review de novo. Carlson v. Allstate Ins. Co., 749 N.W.2d 41, 45 (Minn.2008).

Our law on contract interpretation is well established. We look to the language of the contract to determine the parties' intent. Dykes v. Sukup Mfg. Co., 781 N.W.2d 578, 582 (Minn.2010)

. Put differently, [w]here there is a written instrument, the intent of the parties is determined from the plain language of the instrument itself.” Travertine Corp. v. Lexington–Silverwood, 683 N.W.2d 267, 271 (Minn.2004). “When the language is clear and unambiguous, we enforce the agreement of the parties as expressed in the language of the contract.” Dykes, 781 N.W.2d at 582. When a contractual provision is unambiguous, we do not “rewrite, modify, or limit its effect by a strained construction.” Valspar Refinish, Inc. v. Gaylord's, Inc., 764 N.W.2d 359, 364–65 (Minn.2009). We construe a contract as a whole and attempt to harmonize all of its clauses. Chergosky v. Crosstown Bell, Inc., 463 N.W.2d 522, 525 (Minn.1990).

...

To continue reading

Request your trial
58 cases
  • Luis v. RBC Capital Markets, LLC
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • December 28, 2020
    ...[this court] enforce[s] the agreement of the parties as expressed in the language of the contract." Storms, Inc. v. Mathy Const. Co. , 883 N.W.2d 772, 776 (Minn. 2016) (citation omitted). For unambiguous contract language, this court "should not rewrite, modify, or limit its effect by a str......
  • Glacial Plains Coop. v. Chippewa Valley Ethanol Co., LLLP
    • United States
    • Minnesota Supreme Court
    • June 6, 2018
    ...93 (2015)."Whether language in a contract is plain or ambiguous is a question of law that we review de novo." Storms, Inc. v. Mathy Constr. Co. , 883 N.W.2d 772, 776 (Minn. 2016). "The language of a contract is ambiguous if it is susceptible to two or more reasonable interpretations." Dykes......
  • Jensen v. Minn. Dep't of Human Servs.
    • United States
    • U.S. District Court — District of Minnesota
    • June 28, 2017
    ...321 (Minn. 1982)). A court should "construe a contract as a whole and attempt to harmonize all of its clauses." Storms, Inc. v. Mathy Const. Co., 883 N.W.2d 772, 776 (Minn. 2016). In addition, unambiguous provisions should not be given "a strained construction." Id. (quoting Valspar Refinis......
  • Glacial Plains Coop. v. Chippewa Valley Ethanol Co., A16-1626
    • United States
    • Minnesota Court of Appeals
    • June 12, 2017
    ...Where there is a written contract, this court must look to the language of the contract to determine intent. Storms, Inc. v. Mathy Constr. Co. , 883 N.W.2d 772, 776 (Minn. 2016). We "construe a contract as a whole and attempt to harmonize all of its clauses." Id.The Minnesota Supreme Court ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT