Suffolk Const. Co., Inc. v. Lanco Scaffolding Co., Inc.

Decision Date15 September 1999
Docket NumberNo. 97-P-807,97-P-807
Citation47 Mass.App.Ct. 726,716 N.E.2d 130
PartiesSUFFOLK CONSTRUCTION COMPANY, INC. v. LANCO SCAFFOLDING CO., INC. 1
CourtAppeals Court of Massachusetts

Lawrence J. Kenney, Jr., Boston (Robert G. Eaton & Roger H. Randall with him) for the defendant.

John E. Keenan, Jr., Salem, for the plaintiff.

Present: KASS, PORADA, & LENK, JJ.

LENK, J.

The central question on appeal is whether a contract between a general contractor and its scaffolding subcontractor should be given retroactive effect such that an indemnification clause in that contract would apply to losses incurred before the date of the written contract.

On May 22, 1991, while working at a construction site for a public school, Stephen Hast fell off some scaffolding and was injured. Hast thereafter brought suit against the general contractor, Suffolk Construction Company, Inc. (Suffolk), and against the subcontractor that built the scaffolding, Lanco Scaffolding Co., Inc. (Lanco). Suffolk cross claimed against Lanco for, insofar as relevant to this appeal, express indemnification and breach of Lanco's contractual obligation to list Suffolk with its insurer as an additional insured. Suffolk took the view that its written subcontract with Lanco was in effect on May 22, 1991, the day of Hast's accident, while Lanco maintained that the written subcontract did not go into effect until May 24, 1991, at the earliest, two days after the accident.

At trial, the judge concluded that the written subcontract was ambiguous as to its effective date and left it for the jury to determine whether the parties intended the contract to cover the period on and before the May 22, 1991, accident. The jury found that the parties did intend retroactive effect but that Lanco had not breached its obligation to list Suffolk as an additional insured. 2 The jury also found, with respect to Suffolk's claims against Lanco, that Lanco was negligent and that its negligence proximately caused Hast's injuries. 3 Judgment entered for Suffolk on its cross claim against Lanco for indemnification. On appeal, Lanco contends that the judge erred in submitting the issue of the contract's effective date to the jury and in denying its motions for a directed verdict and subsequently for judgment notwithstanding the verdict and for new trial because, among other things, the written subcontract is unambiguous and did not become effective until after the date of the accident, and because there was, in any event, insufficient evidence that the written subcontract constituted a memorialization of an earlier agreement by Lanco to indemnify Suffolk.

The relevant facts are few. Lanco began work on the construction project sometime prior to May 7, 1991, a time when the parties had not yet entered into a formal written subcontract agreement for the scaffolding work. Suffolk sent Lanco a formal written subcontract agreement on June 6, 1991. It states at the top of the first page of the agreement that it was "made this 24th day of May 1991." Above the signature lines appear the words "[e]xecuted under seal as of the date first above written." The subcontract contains, among other things, an indemnification provision and an insurance provision. 4

After hearing voir dire testimony from Suffolk's project manager, the judge concluded, over objection, that the subcontract was ambiguous and that the issue of its effective date was for the jury to determine. The judge observed that there existed "sufficient ambiguity as to what was intended by the parties between Suffolk and Lanco as to whether or not this agreement, in spite of being dated May 24 and saying it was made as of that date, whether there was a mutual meeting of the minds that the agreement covered the entire span of the work preceding that date."

The interpretation of a contract is generally a question of law. See Daley v. J.F. White Contr. Co., 347 Mass. 285, 288, 197 N.E.2d 699 (1964); Freelander v. G. & K. Realty Corp., 357 Mass. 512, 516, 258 N.E.2d 786 (1970); Edmonds v. United States, 642 F.2d 877, 881 (1st Cir.1981). As such, the trial judge's determination that the subcontract at issue is ambiguous is subject to plenary review. See RCI Northeast Servs. Div. v. Boston Edison Co., 822 F.2d 199, 202 (1st Cir.1987).

Contracts that are free from ambiguity must be interpreted according to their plain terms. See Freelander v. G.K. Realty Corp., 357 Mass. at 516, 258 N.E.2d 786; Fairfield 274-278 Clarendon Trust v. Dwek, 970 F.2d 990, 993 (1st Cir.1992). In interpreting a contract, the court must construe all words that are plain and free from ambiguity according to their usual and ordinary sense. Morse v. Boston, 260 Mass. 255, 262, 157 N.E. 523 (1927). Levin v. Century Indem. Co., 279 Mass. 256, 258, 181 N.E. 223 (1932). Contract language is ambiguous where "an agreement's terms are inconsistent on their face or where the phraseology can support reasonable difference of opinion as to the meaning of the words employed and the obligations undertaken." Fashion House, Inc. v. K mart Corp., 892 F.2d 1076, 1083 (1st Cir.1989). However, "an ambiguity is not created simply because a controversy exists between parties, each favoring an interpretation contrary to the other's." Jefferson Ins. Co. v. Holyoke, 23 Mass.App.Ct. 472, 475, 503 N.E.2d 474 (1987).

We discern no ambiguity in the subcontract as to its effective date. The only date mentioned in the agreement is May 24, 1991, the date it was "made" and "[e]xecuted under seal." There are no other dates in the agreement whatever that might create ambiguity or confusion as to a different effective date for the contract. The ordinary meaning and usage of the words "made" and "executed," considered together, makes plain that the subcontract was produced, created or "made," and signed, put into effect or "executed" on May 24, 1991. The contract by its terms became effective two days after the accident.

This case is controlled in all material respects by Greater Boston Cable Corp. v. White Mountain Cable Constr. Corp., 414 Mass. 76, 604 N.E.2d 1315 (1992), the facts of which closely parallel those here. Greater Boston had hired White Mountain, a subcontractor, to rebuild part of a town's cable system. Id. at 77, 604 N.E.2d 1315. White Mountain started working on the project before the terms of the agreement were put in writing, and it was during this time, on April 8, 1985, that a White Mountain employee, Paradis, was injured on the job. Ibid. After the accident, Greater Boston prepared and sent to White Mountain, and the parties executed, a "Construction Agreement" that contained an indemnification clause. Id. at 78, 604 N.E.2d 1315. On appeal, the court rejected Greater Boston's argument that it was entitled to express contract-based indemnity, stating that:

"[P]rior to Paradis's accident Greater Boston and White Mountain were operating without a formal written agreement. After the accident, Greater Boston sent White Mountain a written 'Construction Agreement' which contained an indemnification clause. The construction agreement, by its terms, became effective three days after the accident."

Id. at 79, 604 N.E.2d 1315.

The trial judge was of the view that Greater Boston Cable Corp. v. White Mountain Cable Constr. Corp., supra, had no application because of the difference in the contract's language. Specifically, the judge found that "[u]nlike the contract in Greater Boston Cable Corp. v. White Mountain Cable, 414 Mass. 76, 604 N.E.2d 1315 (1992) which specified the date it was 'effective,' the contract in this case only indicated the date the contract was signed and 'made' ...." Although the opinion in Greater Boston Cable Corp. v. White Mountain Cable Constr. Corp., supra, uses the term "effective," id. at 78, 604 N.E.2d 1315, the language of the actual contract there at issue, which is attached as an addendum to Lanco's brief, uses the words, "made and entered." 5 We conclude that any distinction urged by Suffolk between "made and...

To continue reading

Request your trial
99 cases
  • Rectrix Aerodome Centers, Inc. v. Bmac
    • United States
    • U.S. District Court — District of Massachusetts
    • 10 July 2009
    ...words that are plain and free from ambiguity according to their usual and ordinary sense." Suffolk Constr. Co., Inc. v. Lanco Scaffolding Co., Inc., 47 Mass.App.Ct. 726, 729, 716 N.E.2d 130 (1999). The Minimum Standards plainly reserve to the BMAC the right to limit any fuel to be sold.9 Th......
  • Bank v. Thermo Elemental Inc.
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • 16 June 2008
    ...President & Fellows of Harvard College v. PECO Energy Co., supra at 896, 787 N.E.2d 595, quoting Suffolk Constr. Co. v. Lanco Scaffolding Co., 47 Mass.App.Ct. 726, 729, 716 N.E.2d 130 (1999). See In re Navigation Tech. Corp., 880 F.2d 1491, 1495 (1st In the present case, an examination of t......
  • Doe v. W. New Eng. Univ.
    • United States
    • U.S. District Court — District of Massachusetts
    • 10 January 2017
    ...terms being construed against the University. See Brandeis , 177 F.Supp.3d at 594 (citing cases); Suffolk Constr. Co. v. Lanco Scaffolding Co. , 47 Mass.App.Ct. 726, 716 N.E.2d 130, 133 (1999) ("Contract language is ambiguous where ‘an agreement's terms are inconsistent on their face or whe......
  • Lexington Ins. v. General Acc. Ins. Co. of America
    • United States
    • U.S. Court of Appeals — First Circuit
    • 4 August 2003
    ...A.2d 422 (1997). Absent a genuine issue as to meaning, there is no ambiguity. See, e.g., Suffolk Const. Co. v. Lanco Scaffolding Co., 47 Mass.App.Ct. 726, 716 N.E.2d 130, 133 (Mass.App.Ct. 1999) (stating that contract language is ambiguous only where "an agreement's terms are inconsistent o......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT