Sure–shock Electric Inc. v. Diamond Lofts Venture Llc, 10CA0593.

Decision Date23 June 2011
Docket NumberNo. 10CA0593.,10CA0593.
Citation259 P.3d 546
PartiesSURE–SHOCK ELECTRIC, INC., Plaintiff–Appellee,v.DIAMOND LOFTS VENTURE, LLC, Defendant–Appellant.
CourtColorado Court of Appeals

OPINION TEXT STARTS HERE

Sweetbaum, Levin & Sands, P.C., Alan D. Sweetbaum, Jonathan G. Nash, Denver, Colorado, for PlaintiffAppellee.Rothgerber Johnson & Lyons LLP, Kris J. Kostolansky, Stephen E. Csajaghy, Justin H. Boyd, Denver, Colorado, for DefendantAppellant.Opinion by Chief Judge DAVIDSON.

Defendant, Diamond Lofts Venture, LLC (DLV), appeals from the trial court's order confirming an arbitration award as to the amount of the mechanic's lien claimed by plaintiff, Sure–Shock Electric, Inc. (Sure–Shock), and determining that Sure–Shock was entitled to participate in foreclosure proceedings. We affirm.

I. Background

DLV was the owner of certain real property on which it constructed Diamond Lofts, and Sure–Shock was the electrical subcontractor for the construction project. In their contract, the parties agreed to arbitrate [a]ny claim arising out of or related to the [s]ubcontract.”

DLV did not pay Sure–Shock as required, and Sure–Shock recorded a mechanic's lien on the property and filed a complaint in district court, asserting claims for breach of contract, unjust enrichment, and foreclosure of the lien. Sure–Shock attached both the statement of lien and the notice of intent to file a lien to its complaint.

DLV moved to stay proceedings and compel arbitration pursuant to the contract, the district court granted the motion, and both parties participated in arbitration. The arbitrator found that Sure–Shock had proved its claim, and DLV had proved none of its defenses or offsets. His interim award stated that Sure–Shock's claims were “for breach of contract and unjust enrichment” and did not mention foreclosure of the lien. However, the arbitrator made detailed findings of fact regarding the filing of the lien, including its amount and the date it was recorded. The arbitrator awarded Sure–Shock the principal amount claimed in the lien, plus interest at the statutory rate of twelve percent “from October 17, 2007, the date [the] lien was recorded.”

Sure–Shock moved for confirmation of the award, and the court granted the motion, ordering, as relevant here, that “the arbitration award is confirmed as to the amount of Sure–Shock's mechanics' lien” and that “Sure–Shock will be entitled to participate in the foreclosure of that lien.”

On appeal, DLV argues that the parties' agreement to arbitrate all their claims and disputes divested the court of jurisdiction to determine the “validity, amount and enforceability” of the lien. DLV further argues that, because Sure–Shock did not affirmatively raise the argument that the lien was procedurally valid in arbitration, it is now barred by the doctrines of claim preclusion and waiver from seeking a decree of foreclosure. We disagree.

II. Standard of Review

An arbitration agreement is a contract, the interpretation of which is a matter of law that we review de novo. Allen v. Pacheco, 71 P.3d 375, 378 (Colo.2003). We also review de novo a district court's legal conclusions on a motion to confirm or vacate an arbitration award. Barrett v. Investment Mgmt. Consultants, Ltd., 190 P.3d 800, 802 (Colo.App.2008).

III. Merits

As an initial matter, we reject DLV's argument that the amount of the lien was not submitted to arbitration. A mechanic's lien is a security on a debt, and foreclosure of such a lien is an in rem action that is distinct from the in personam contract claim that establishes the existence and amount of the debt. Mountain Ranch Corp. v. Amalgam Enterprises, Inc., 143 P.3d 1065, 1068 (Colo.App.2005). By determining the amount of debt owed by DLV to Sure–Shock on the underlying contract and unjust enrichment claims, the arbitrator necessarily decided the amount of any mechanic's lien. See Midwest Curtainwalls, Inc. v. Pinnacle 701, L.L.C., 2009–Ohio–3740, 2009 WL 2332049, at *6 (Ohio Ct.App. July 30, 2009) (unpublished opinion); Crowne Pond v. Paradigm Contract Mgmt. Co., No. CV 990174482S, 1999 WL 1207128 (Conn.Super.Ct. Dec. 1, 1999) (unpublished order).

Moreover, the arbitration award clearly noted the filing of the lien, the amount listed on the lien statement, and the date it was recorded, and awarded interest from the date of recordation “at the statutory rate of 12%.” Although the award did not indicate the statute under which interest was awarded, we note that the general rate of statutory interest, pursuant to section 5–12–102, C.R.S.2010, is eight percent. The only possibly relevant statute that sets an interest rate of twelve percent concerns mechanic's liens. See § 38–22–101(5), C.R.S.2010 (“All claimants who establish the right to a lien or claim under any of the provisions of this article shall be entitled to receive interest on any such lien or claim ... at the rate of twelve percent per annum.”). Thus, we read the arbitrator's award to conclude that Sure–Shock had established the right to a lien or claim under the mechanic's lien statute.

The only remaining issue to be decided with regard to that lien, then, was the issue of procedural validity, that is, whether Sure–Shock complied with the procedural requirements of providing notice and recording its lien such that it is now entitled to a decree of foreclosure.

As Sure–Shock correctly asserts, submission of a facially proper notice of intent to file a lien and lien statement, time stamped by the county recorder's office, satisfies a mechanic's lien claimant's initial burden of proving the lien's procedural validity. AAA Crane Serv., Inc. v. Omnibank Univ. Hills, 723 P.2d 156, 159 (Colo.App.1986). Here, Sure–Shock attached its notice of intent to file a lien statement to its complaint. The notice of intent included affidavits of service stating that DLV, as owner of the property, and Solen, Inc., as the principal contractor, were served on October 5, 2007. Sure–Shock also attached its statement of lien, which was recorded on October 17, 2007, more than ten days after service.

It was DLV that moved to compel arbitration and made the demand for arbitration, which, while claiming that another mechanic's lien by another contractor (which participated in arbitration but is not a party to this appeal) was spurious, did not challenge the procedural validity of Sure–Shock's lien. However, although the arbitrator was aware of the lien, including the amount listed and date of recordation, and we have on appeal no record of the arbitration, because Sure–Shock does not dispute that the procedural validity issue was not arbitrated, we will assume that Sure–Shock did not provide copies of the notice of intent and lien statement to the arbitrator.

Therefore, the question we must answer is whether the procedural validity issue may be properly decided by the court as part of the foreclosure proceedings, or whether either Sure–Shock or DLV was required to raise it in arbitration under their agreement requiring all claims and disputes to be submitted to arbitration. The question is one of first impression in Colorado, although, as DLV acknowledges, our statutes provide that only a court may issue a decree of foreclosure. § 38–22–114(1), C.R.S.2010; see also Mountain Plains Constructors, Inc. v. Torrez, 785 P.2d 928, 931 (Colo.1990) (proper procedure is not to dismiss, but to stay action pending completion of arbitration, so as to preserve plaintiff's right to foreclose on its mechanic's lien).

We conclude that, here, the issue of procedural validity may be properly determined by the court. Given that only a court is...

To continue reading

Request your trial
3 cases
  • Wainscott v. Centura Health Corp.
    • United States
    • Colorado Court of Appeals
    • August 14, 2014
    ...not have a public purpose but instead protect only contractual rights between private parties. See Sure–Shock Elec., Inc. v. Diamond Lofts Venture, LLC, 259 P.3d 546, 548 (Colo.App.2011) (contract claim establishes the existence of the debt underlying a mechanic's lien); Via Christi I, 247 ......
  • Estate of Guido v. Exempla, Inc.
    • United States
    • Colorado Court of Appeals
    • March 15, 2012
    ...review de novo a district court's legal conclusions on a motion to confirm an arbitration award. Sure–Shock Elec., Inc. v. Diamond Lofts Venture, LLC, 259 P.3d 546, 548 (Colo.App.2011); Barrett v. Inv. Mgmt. Consultants, Ltd., 190 P.3d 800, 802 (Colo.App.2008).A. Confirmation Motion Is Not ......
  • Sure-Shock Elec., Inc. v. Diamond Lofts Venture, LLC
    • United States
    • Colorado Court of Appeals
    • August 28, 2014
    ...arbitration award and remanded to the trial court the issue whether the lien was procedurally valid. Sure–Shock Elec., Inc. v. Diamond Lofts Venture, LLC, 259 P.3d 546, 550 (Colo.App.2011).¶ 5 After a bench trial, the trial court found that Sure–Shock's lien was procedurally valid, and it a......
6 books & journal articles
  • Chapter 20 - § 20.8 • SCOPE OF REVIEW
    • United States
    • Colorado Bar Association Colorado and Federal Arbitration Law and Practice (CBA) Chapter 20 Appeal of Trial Court Orders and Judgments
    • Invalid date
    ...Shopping Ctr., LLC v. Neiman-Marcus Grp., Inc., 251 P.3d 1091 (Colo. App. 2010); Sure-Shock Elec., Inc. v. Diamond Lofts Venture, LLC, 259 P.3d 546 (Colo. App. 2011); Burlington N. & Santa Fe Ry. Co. v. Pub. Serv. Co. of Okla., 636 F.3d 562 (10th Cir. 2010); CEEG (Shanghai) Solar Sci. & Tec......
  • Chapter 19 - § 19.7 • LIEN FORECLOSURE LAWSUIT
    • United States
    • Colorado Bar Association Practitioner's Guide to Colorado Construction Law (CBA) Chapter 19 Mechanics' Liens
    • Invalid date
    ...Mountain Plains Constructors, Inc. v. Torrez, 785 P.2d 928, 931 (Colo. 1990).[251] Sure-Shock Elec., Inc. v. Diamond Lofts Venture, LLC, 259 P.3d 546 (Colo. App. 2010).[252] C.R.S. § 38-22-115.[253] See, e.g., Belfor USA Grp., Inc. v. Rocky Mountain Caulking & Waterproofing, LLC, 159 P.3d 6......
  • Chapter 6 - § 6.6 • ARBITRATION OF MECHANICS' LIENS, MILLER ACT CLAIMS, AND FORECLOSURES
    • United States
    • Colorado Bar Association Colorado and Federal Arbitration Law and Practice (CBA) Chapter 6 Arbitration of Particular Kinds of Claims and Between Particular Entities
    • Invalid date
    ...Constr. Co., 875 A.2d 789 (Md. App. 2005), aff'd, 898 A.2d 472 (Md. 2006).[79] Sure-Shock Elec., Inc. v. Dramond Lofts Venture, LLC, 259 P.3d 546 (Colo. App. 2011).[80] Id. at 548-49.[81] Id. at 549.[82] Id.[83] 40 U.S.C. § 3131; U.S. ex rel. Tanner v. Daco Const., Inc., 38 F. Supp. 2d 1299......
  • Chapter 21 - § 21.3 • ARBITRATION OF CONSTRUCTION DISPUTES
    • United States
    • Colorado Bar Association Practitioner's Guide to Colorado Construction Law (CBA) Chapter 21 Arbitration and Mediation of Construction Disputes
    • Invalid date
    ...v. Batson-Cook Co., 291 S.E.2d 249 (Ga. App. 1982); Brendsel, 875 A.2d 789.[387] Sure-Shock Elec., Inc. v. Diamond Lofts Venture, LLC, 259 P.3d 546 (Colo. App. 2011).[388] Id. at 549.[389] Id. at 548.[390] Id. at 549.[391] Id.[392] Id.[393] Id.[394] 40 U.S.C. § 3131; U.S. ex rel. Tanner v. ......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT