Sweatt v. International Development Corp.

Decision Date14 March 2000
Docket NumberNo. A99A1672.,A99A1672.
Citation242 Ga. App. 753,531 S.E.2d 192
PartiesSWEATT et al. v. INTERNATIONAL DEVELOPMENT CORPORATION et al.
CourtGeorgia Court of Appeals

OPINION TEXT STARTS HERE

Altman, Kritzer & Levick, Joseph S. Carr, Jeanine L. Gibbs, Atlanta, for appellants.

Smith, Ronick & Corbin, Howard R. Ronick, Atlanta, for appellees.

Christopher J. Bruns, pro se.

SMITH, Judge.

Would-be home buyers W. David Sweatt and Alicia P. Sweatt filed suit against International Development Corporation ("IDC") and Christopher J. Bruns.1 The Sweatts alleged that IDC and Bruns breached a real property purchase and construction agreement for a house being built for them by Bruns. IDC and Bruns counterclaimed for breach of contract and specific performance, and the Sweatts filed a lis pendens against the property. The Sweatts asked the court to order arbitration of all the controversies and claims arising from the purchase agreement or any alleged breach of it. The trial court ordered the parties to complete binding arbitration.

Before arbitration was concluded, both sides agreed to a consent order recognizing that IDC and Bruns had entered into a purchase and sale agreement for the property at issue with a third party and requiring IDC and Bruns to deposit the net proceeds of that sale into the registry of the court. IDC and Bruns subsequently sold the property for $373,000, or about $8,000 more than the contract price of $365,900 with the Sweatts. After payoff of the construction loan and payment of a real estate commission, the net proceeds realized by that sale, $89,017.77, were deposited into the registry of the court.

A few months later, the arbitrator found in favor of IDC and Bruns and against the Sweatts. The arbitrator awarded $25,000 to IDC and Bruns and ordered the release to IDC and Bruns of the funds being held by the court. As a consequence of that award, the Sweatts forfeited their $35,000 in earnest money and about $5,000 they had paid to Bruns for upgrades to the house during construction.

Asserting multiple grounds, the Sweatts moved to vacate or, in the alternative, to modify the arbitration award. They contended that the arbitrator had overstepped his authority, that the award demonstrated a manifest disregard of the law, and that the award was improperly calculated so as to constitute a double recovery. After reviewing the record and hearing argument of counsel, the trial court denied the Sweatts' motion and confirmed the "Final Judgment and Award" issued by the arbitrator. The Sweatts appeal that judgment.

1. In two enumerations of error, the Sweatts contend the trial court erred in denying their motion to vacate the arbitration award because the arbitrator overstepped his authority and the award demonstrates a manifest disregard of the law.

OCGA § 9-9-13(b) sets forth the exclusive grounds upon which an arbitration award may be vacated. Greene v. Hundley, 266 Ga. 592, 595-596(3), 468 S.E.2d 350 (1996); Akintobi v. Phoenix Fire Restoration Co., 236 Ga.App. 760, 761, 513 S.E.2d 507 (1999). Unless prejudice is shown and one of the four statutory grounds for vacating or modifying an award is established, the Georgia Arbitration Code requires a trial court to confirm an award upon timely application by a party. Haddon v. Shaheen & Co., 231 Ga.App. 596-597(1), 499 S.E.2d 693 (1998); see Gilbert v. Montlick, 232 Ga.App. 91, 93(1), 499 S.E.2d 731 (1998).

Here, the Sweatts rely on the statutory ground that authorizes a trial court to vacate an award when the court finds that the rights of a party were prejudiced by "[a]n overstepping by the arbitrators of their authority." OCGA § 9-9-13(b)(3). In this context, "overstepping" means that the arbitrator addressed issues not properly before him. Ralston v. City of Dahlonega, 236 Ga. App. 386, 388(3), 512 S.E.2d 300 (1999). The Sweatts contend the arbitrator overstepped his authority by awarding damages not allowed by the contract. Compare Atlanta Gas Light Co. v. Trinity Christian &c. Church, 231 Ga.App. 617, 620(2), 500 S.E.2d 374 (1998). They claim that an award to IDC and Bruns of actual damages violated the express terms of the contract which permitted only the recovery of liquidated damages. We agree. Compare City of College Park v. Batson-Cook Co., 196 Ga.App. 138, 140, 395 S.E.2d 385 (1990) (trial court correctly affirmed an award supported by record of arbitration proceedings that showed the arbitrators did not ignore contract terms or applicable law).

During arbitration proceedings, the general rules of contract construction apply. Martin v. RocCorp, Inc., 212 Ga.App. 177, 179, 441 S.E.2d 671 (1994). An arbitration award should be consistent with terms of the underlying agreement and reflect the "essence" of that contract; it must not demonstrate an "imperfect execution" of the arbitrator's authority. Atlanta Gas Light, supra. Although an arbitrator has some latitude in fashioning remedies, he is not free to ignore the express terms of a valid and enforceable contract. Banderas v. Doman, 224 Ga.App. 198, 201(4), 480 S.E.2d 252 (1997).

In this case, the underlying contract required the submission of "[a]ny controversy or claim arising out of or relating to this contract, or the breach thereof," to binding arbitration. This was done. But the contract also required the application of OCGA § 13-6-7, the liquidated damages statute, and provided for liquidated damages in the event of breach by the buyer. This was not done.

It is undisputed that Section 4 of this contract, entitled "Liquidated Damages," set forth the seller's damages in the event of a breach by the Sweatts. This section provided in pertinent part:

Seller and Buyer acknowledge that it would be extremely impractical and difficult to ascertain the actual damages that would be suffered by Seller if Buyer fails to or refuses to consummate the purchase of the Property.... Seller and Buyer have considered carefully the loss to Seller as a consequence of the negotiation and execution of this Agreement; the personal expenses Seller incurred in connection with the preparation of this Agreement; Seller's performance hereunder; and the other damages, general and special, which Seller and Buyer realize and recognize that Seller would sustain, but Seller cannot calculate with absolute certainty. Based upon all those considerations, Seller and Buyer have agreed that the damage to Seller would reasonably be expected to be equal to the amount of the earnest money. [In the event that Buyer breaches the agreement and Seller has fully performed its obligations,] then Seller shall be entitled to retain the earnest money as full and complete liquidated damages for such default of Buyer. Such retention of the earnest money is intended not as a penalty, but as full liquidated damages pursuant to O.C.G.A. § 13-6-7. However, in lieu of retaining the earnest money as liquidated damages, Seller shall have the right to bring an action for specific performance of the terms of the Agreement.

(Emphasis supplied.)

"If the parties agree in their contract what the damages for a breach shall be, they are said to be liquidated and, unless the agreement violates some principle of law, the parties are bound thereby." OCGA § 13-6-7. "A non-breaching party who has agreed to accept liquidated damages cannot elect after a breach to take actual damages should they prove greater than the sum specified." Southeastern Land Fund v. Real Estate World, 237 Ga. 227, 230, 227 S.E.2d 340 (1976). "The liquidated damages become the `maximum as well as the minimum sum that can be collected.' [Cit.]" Id.

After the arbitrator determined the Sweatts breached the contract and were in...

To continue reading

Request your trial
23 cases
  • Wells v. Wells-Wilson
    • United States
    • Georgia Court of Appeals
    • June 30, 2021
    ...transferred stock to Magwell. (a) Overstepping. Magwell relies heavily upon this Court's decision in Sweatt v. Intl. Dev. Corp. , 242 Ga. App. 753, 531 S.E.2d 192 (2000), to assert that the arbitrator overstepped his authority by interpreting the Operating Agreement and Consent in a manner ......
  • King v. King
    • United States
    • Georgia Court of Appeals
    • February 27, 2020
    ...free to ignore the express terms of a valid and enforceable contract.(Citation and punctuation omitted.) Sweatt v. Intl. Dev. Corp. , 242 Ga. App. 753, 755 (1), 531 S.E.2d 192 (2000). Here, the Arbitration Award was inconsistent with the express provision of the parties’ arbitration agreeme......
  • Patterson v. Long
    • United States
    • Georgia Court of Appeals
    • March 29, 2013
    ...waived her argument for modification predicated on OCGA § 9–9–14(b)(2). By extension, her reliance on Sweatt v. Intl. Dev. Corp., 242 Ga.App. 753, 757–758(2), 531 S.E.2d 192 (2000), which applied that statutory provision, is misplaced. 7. Long relies upon West v. Jamison, 182 Ga.App. 565, 5......
  • Berger v. Welsh
    • United States
    • Georgia Court of Appeals
    • March 17, 2014
    ...claims, no construction of the release contract is permissible, and they connect that general principle to Sweatt v. Intl. Dev. Corp. 242 Ga.App. 753, 757(1), 531 S.E.2d 192 (2000), in which this Court vacated an arbitrator's award finding that he impermissibly ignored the explicit, unambig......