Tillman Park v. Dabbs-Williams Gen. Contrs.

Decision Date19 May 2009
Docket NumberNo. A09A0174.,A09A0174.
Citation298 Ga. App. 27,679 S.E.2d 67
PartiesTILLMAN PARK, LLC et al. v. DABBS-WILLIAMS GENERAL CONTRACTORS, LLC.
CourtGeorgia Court of Appeals

Oliver & Maner, Leslie P. Sheehan, William P. Franklin Jr., Savannah, for appellants.

Franklin, Taulbee, Rushing, Snipes & Marsh, James B. Franklin, Daniel B. Snipes, Statesboro, for appellee.

PHIPPS, Judge.

Dabbs-Williams General Contractors, LLC, served as general contractor on a project for construction of a condominium development owned by Tillman Park, LLC. After construction was completed, Dabbs-Williams brought this suit against Tillman Park and its owner, T. Holmes Ramsey, to recover for construction modifications and additions which Dabbs-Williams claims it made pursuant to an oral agreement with Ramsey.

Tillman Park and Ramsey answered Dabbs-Williams's complaint and filed counterclaims charging Dabbs-Williams with, among other things, negligent and defective construction. In addition, in reliance on arbitration provisions in an agreement entered into between Tillman Park and Dabbs-Williams, Tillman Park and Ramsey filed a motion to compel arbitration. Dabbs-Williams opposed the motion, arguing that its dispute with Ramsey is beyond the scope of the arbitration agreement. Dabbs-Williams also argues that the arbitration agreement is unenforceable, because it requires submission of a dispute to a project "architect" as a condition precedent to arbitration, and no architect was named in the parties' agreement.

After conducting hearings, the trial court entered an order finding the arbitration agreement unenforceable for the reason given by Dabbs-Williams and denying the motion to compel. We granted Tillman Park and Ramsey's application for interlocutory appeal. For reasons that follow, we affirm the trial court's denial of the motion to compel Ramsey to arbitrate, but reverse the court's denial of the motion to compel Tillman Park to arbitrate and remand for further proceedings.

Tillman Park, as owner, and Dabbs-Williams, as contractor, entered into the 1997 edition of a standard-form American Institute of Architects (AIA) agreement. The introductory page of the standard-form agreement provides spaces for identification of the owner, the contractor, the project, and a project architect. In the space provided for designation of the architect, "N/A" was typed.

The standard-form agreement also incorporates AIA "general conditions" for construction contracts. The general conditions entrust administration of the contract to the architect as representative of the owner. Under the general conditions, claims by one of the parties "arising out of or relating to the contract" must be submitted to the architect. One of the general conditions provides:

An initial decision by the architect shall be required as a condition precedent to mediation, arbitration or litigation of all claims between the contractor and owner arising prior to the date final payment is due, unless 30 days have passed after the claim has been referred to the architect with no decision having been rendered by the architect.

(Emphasis supplied).

Two hearings were held on the motion to compel. At the first hearing, Tillman Park claimed that it had appointed an architect but that, to reduce expenses so that Dabbs-Williams could construct the condominiums within the limit required by a guaranteed maximum price set forth in the parties' agreement, the architect had not been used to administer the contract. Because of the insufficiency of the evidence to show whether Tillman Park had appointed an architect, the court continued the hearing.

At the next hearing, Tillman Park submitted affidavits executed by Daniel Smith and Wayne Ramsey and the oral testimony of Wallace Wright. Smith testified that the bank of which he was an officer required use of the AIA standard-form contract as a condition to Tillman Park receiving construction financing. Ramsey testified that he was the architect associated with the Tillman Park project and that, even though he had not administered the contract, he had remained "on call" and available for dispute resolution during the project. According to Ramsey, it is not uncommon for construction project owners to use the standard-form AIA contract without employing a project architect and that, when that is done, it is the general practice and understanding in the industry to consider contract provisions relating to the architect as having been waived; otherwise, the entire contract would be invalidated, due to the centrality of the architect's role in administering it. Therefore, according to Ramsey, the general industry practice is to require dispute resolution to go directly to mediation and/or arbitration where no architect has been appointed. Wright, the loan-closing attorney for the bank, testified that the standard-form AIA contract was actually entered into between Tillman Park and Dabbs-Williams at the insistence of the bank after construction had begun. Although Wright further testified that the completed contract was sent to him by Dabbs-Williams, he did not know who had actually inserted the letters "N/A" in the space provided in the contract for designation of an architect.

At the second hearing, counsel for Dabbs-Williams objected to the court's consideration of the two affidavits on the ground that they had not been served on him prior to the hearing. In fact, counsel for Tillman Park had not obtained the affidavits until the evening before the hearing. At the conclusion of the hearing, the court announced that after considering briefs to be submitted by the parties, it would rule on evidentiary issues and decide the motion.

The court subsequently entered its order, ruling that because no architect had been named in the parties' contract or had administered the contract, there had been a failure of a condition precedent to arbitration. As authority in support of this ruling, the court cited North Augusta Assocs. Ltd. Partnership v. 1815 Exchange.1 Consequently, the court denied the motion to compel arbitration. The order, however, contains no reference to the affidavits submitted by Tillman Park or any express ruling on Dabbs-Williams's objection to them.

"A party aggrieved by the failure of another to arbitrate may apply for an order compelling arbitration."2 The application should be granted unless "(1) No valid agreement to submit to arbitration was made; (2) The agreement to arbitrate was not complied with; or (3) The arbitration is barred by limitation of time."3 These issues are to be decided by the court without intervention of a jury.4 Accordingly, in the appeal from the grant or denial of a motion to compel arbitration, our standard of review "becomes whether the trial court was correct as a matter of law."5 "[T]he construction of an arbitration agreement, like any other contract, presents a question of law, which is subject to de novo review."6

The cardinal rule of contract construction is to ascertain the intention of the parties. Contract construction is a three-step process. Initially, the construction of the contract is a question of law for the court. First, if no ambiguity appears, the trial court enforces the contract according to its terms irrespective of all technical or arbitrary rules of construction. That is, where the terms of a written contract are clear and unambiguous, the court will look to the contract alone to find the intention of the parties. Secondly, if ambiguity does appear, the existence or non-existence of an ambiguity is itself a question of law for the court. Finally, a (fact) question arises only when there appears to be an ambiguity in the contract which cannot be negated by the court's application of the statutory rules of construction. This is true even if the contract is difficult to construe. Further, a contract should be construed by examining the agreement in its entirety, and not merely by examining isolated clauses and provisions thereof.7

"`[T]he court should ascertain the parties' intent after considering the whole agreement and interpret each of the provisions so as to harmonize with the others.'"8

Here, in reliance on North Augusta, the court effectively determined that the parties' agreement unambiguously required submission of the parties' dispute to an architect as a condition precedent to arbitration, and that failure of the condition precedent, for whatever reason, dispensed with the requirement that the dispute be arbitrated. The construction agreement in North Augusta, similar to the one here, contained an arbitration provision requiring claims to be...

To continue reading

Request your trial
11 cases
  • Benedict v. State Farm Bank
    • United States
    • Georgia Court of Appeals
    • April 6, 2011
    ...his dispute with State Farm.7 We review de novo the grant of a motion to compel arbitration. Tillman Park, LLC v. Dabbs–Williams Gen. Contractors, 298 Ga.App. 27, 29, 679 S.E.2d 67 (2009). Arbitration is “a matter of consent, not coercion,” Volt Information Sciences v. Bd. of Trustees of Le......
  • Web Iv, LLC v. Samples Constr., LLC.
    • United States
    • Georgia Court of Appeals
    • February 28, 2019
    ... ... at 792 (2), 469 S.E.2d 759, and Tillman Park, LLC v. Dabbs-Williams Gen. Contractors, LLC , 298 ... ...
  • Aaron v. United Health Servs. of Ga., Inc.
    • United States
    • Georgia Court of Appeals
    • March 15, 2019
    ...the standard of review is "whether the trial court was correct as a matter of law." Tillman Park, LLC v. Dabbs-Williams Gen. Contractors , 298 Ga. App. 27, 29–30, 679 S.E.2d 67 (2009) (citation and punctuation omitted). "[T]he construction of an arbitration agreement, like any other contrac......
  • Order Homes, LLC v. Iverson
    • United States
    • Georgia Court of Appeals
    • August 19, 2009
    ...omitted.) Krut v. Whitecap Housing Group, 268 Ga.App. 436, 441(2), 602 S.E.2d 201 (2004); accord Tillman Park v. Dabbs-Williams Gen. Contractors, 298 Ga.App. 27, 679 S.E.2d 67 (2009). 3. (Citation, punctuation, and footnote omitted.) Crawford v. Great American Cash Advance, 284 Ga.App. 690,......
  • Request a trial to view additional results
2 books & journal articles
  • Construction Law - Frank O. Brown Jr.
    • United States
    • Mercer University School of Law Mercer Law Reviews No. 61-1, September 2009
    • Invalid date
    ...81. Id. 82. See id. at 474, 668 S.E.2d at 671. 83. Id. at 471, 668 S.E.2d at 669. 84. See id. at 471 n.3, 668 S.E.2d at 669 n.3. 85. 298 Ga. App. 27, 679 S.E.2d 67 (2009). 86. Id. at 28, 679 S.E.2d at 69. 87. Id. at 27-28, 679 S.E.2d at 68-69. 88. Id. at 32, 679 S.E.2d at 71-72. 89. Id., 67......
  • Chapter 7 - § 7.7 • CONDITIONS PRECEDENT TO THE OBLIGATION TO ARBITRATE
    • United States
    • Colorado Bar Association Colorado and Federal Arbitration Law and Practice (CBA) Chapter 7 Arbitrability of Disputes: the Issues and the Law
    • Invalid date
    ...v. Wolfer, 240 P. 694 (Colo. 1925).[196] Sollenberger, 481 P.2d at 431.[197] Tillman Park, LLC v. Dabbs-Williams Gen. Contractors, LLC, 679 S.E.2d 67 (Ga. App. 2009). Compare Lopez v. 14th Street Dev., LLC, 835 N.Y.S.2d 186 (N.Y. App. Div. 2007). See Brasfield & Gorrie, L.L.C. v. Soho Partn......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT