Wedemeyer v. Gulfstream Aerospace Corp.

Decision Date27 September 2013
Docket NumberNo. A13A0836.,A13A0836.
Citation749 S.E.2d 241,324 Ga.App. 47
PartiesWEDEMEYER v. GULFSTREAM AEROSPACE CORPORATION.
CourtGeorgia Court of Appeals

OPINION TEXT STARTS HERE

Brent J. Savage, Savannah, for Appellant.

Shawn Anton Kachmar, Savannah, for Appellee.

MILLER, Judge.

John Scott Wedemeyer sued Gulfstream Aerospace Corporation, his former employer, for defamation and tortious interference with a business expectancy. Gulfstream moved to dismiss, arguing, inter alia, that Wedemeyer was compelled to arbitrate his claims based on the parties' arbitration agreement that covered all employment-related claims, including claims for intentional torts and defamation. After conducting two hearings on the matter and carefully reviewing the record, the trial court granted Gulfstream's motion to compel arbitration and dismissed the case with prejudice. Wedemeyer appeals, contending that the trial court erred in compelling arbitration. For the reasons that follow, we affirm.

“Georgia courts are required to uphold valid arbitration provisions in contracts[.] (Citation and punctuation omitted.) Bishop Contracting Co. v. Center Bros., 213 Ga.App. 804, 805(1), 445 S.E.2d 780 (1994). “The standard of review from the denial of a motion to compel arbitration is whether the trial court was correct as a matter of law.” (Footnote omitted.) D.S. Ameri Constr. Corp. v. Simpson, 271 Ga.App. 825, 826, 611 S.E.2d 103 (2005). “Unless the parties clearly and unmistakably provide otherwise,” the arbitrability is undeniably an issue for judicial determination. (Citations omitted.) AT & T Technologies v. Communications Workers of America, 475 U.S. 643, 649(II), 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986).

The record shows that Gulfstream manufactures and services Gulfstream aircraft and is headquartered in Chatham County, Georgia. In 2007, Gulfstream hired Wedemeyer as a production test pilot. Upon his employment, Wedemeyer agreed to abide by Gulfstream's Dispute Resolution Policy (hereinafter the “Arbitration Agreement”), which set forth a four-level process culminating in binding arbitration of all employment-related claims, including claims for intentional torts and defamation.

The Arbitration Agreement pertinently provides:

PURPOSE [:] This policy (“DRP” or the “Policy”) applies ... to all employees who were employed by the Company while the Policy or any version was in effect (collectivelyreferred as the “Employee” or “Employees”).

...

DRP is a structured dispute resolution process that applies to Covered Claims and consists of four levels: Level 1: Human Resources Review; ... Level 2: Management Panel Review; ... Level 3: Mediation[;] ... Level 4: Arbitration [.] Employees must complete each level of the process before proceeding to the next level. The Company may elect to bypass one or more steps prior to arbitration for disputes with applicants for employment, with former employees, or if the Company is the initiating party.

...

Covered Claims are employment-related claims between an individual Employee and the Company[.] ... Covered Claims involve a claim of a legal right, obligation or entitlement regarding or arising from the employment relationship. Covered Claims include, but are not limited to, the following: (1) Claims relating to involuntary terminations[;] (5) Tort claims, intentional torts, negligence, defamation, invasion of privacy, infliction or emotional distress[.]

...

Claims excluded from the DRP are the following: ... 5. Claims against the Company ... which do not have any relationship to the Employee's work or relationship to the Company[.]

...

Exclusivity of the Dispute Resolution Policy [:] The DRP is the sole and exclusive forum and remedy for all Covered Claims. The Employee and Company agree and hereby waive any right to jury trial for any Covered Claim.

...

Agreement to Arbitrate in Interstate Commerce [:] This Policy is an agreement to arbitrate pursuant to the Federal Arbitration Act [FAA], 9 U.S.C.A. Sections 1–14[.]

(Emphasis supplied.)

On February 14, 2011, Wedemeyer was piloting a crew airplane during a production test flight in Appleton, Wisconsin. Upon landing, the plane experienced several system failures. Wedemeyer and his co-pilot's response to those issues caused the plane to depart the runway, resulting in damage to the plane. Gulfstream immediately grounded Wedemeyer and subsequently terminated his employment.

Wedemeyer sued Gulfstream, alleging that Gulfstream's dissemination of false conclusions that he was at-fault for the incident had cost him numerous pilot positions. Wedemeyer further alleged that Gulfstream's actions after his employment tortiously interfered with a legitimate business expectancy and that he had lost income from Gulfstream's improper acts. Wedemeyer also alleged Gulfstream defamed him during a pilots' meeting that was held during the evening on the day Wedemeyer was fired. Thereafter, a number of Gulfstream pilots allegedly warned various third parties and Gulfstream counseled its employees to not have anything to do with Wedemeyer because he was suing Gulfstream.

Gulfstream moved to dismiss this action and compel arbitration. The trial court granted the motion and dismissed Wedemeyer's suit.

1. In his sole enumeration of error, Wedemeyer contends that the trial court erred by compelling arbitration because he was not subject to the Arbitration Agreement when his claims against Gulfstream arose and his claims are not covered claims under the Agreement. We disagree.

“Arbitration is a matter of consent, not coercion,” Volt Information Sciences v. Bd. of Trustees of Leland Stanford Junior University, 489 U.S. 468, 479, 109 S.Ct. 1248, 103 L.Ed.2d 488 (1989), and a party can be compelled to arbitrate only upon a showing that he entered into an enforceable agreement to arbitrate. Life Care Centers of America, Inc. v. Smith, 298 Ga.App. 739, 741(1), 681 S.E.2d 182 (2009). Here, we think there is sufficient evidence of the existence of an enforceable agreement between Wedemeyer and Gulfstream to arbitrate.

“Arbitration in Georgia is a matter of contract. As such, the construction of an arbitration clause in a contract is subject to the ordinary rules of contract construction.” (Citations and punctuation omitted.) SCSJ Enterprises v. Hansen & Hansen Enterprises, 319 Ga.App. 210, 212(1), 734 S.E.2d 214 (2012).

First, we must determine if the contract language is ambiguous, and, if so, then we apply the appropriate rules of construction set forth in OCGA § 13–2–2. Where the language of a contract is plain and unambiguous, however, no construction is required or permissible and the terms of the contract must be given an interpretation of ordinary significance.

(Citation and punctuation omitted.) Richard Bowers & Co. v. Creel, 280 Ga.App. 199, 200–201(1), 633 S.E.2d 555 (2006); see also Canton Plaza, Inc. v. Regions Bank, Inc., 315 Ga.App. 303, 308–309(3), 732 S.E.2d 449 (2012) (the contract alone is looked to where the language is clear and unambiguous). Moreover, [i]n construing any contract, words carry their usual and common meaning, and the construction which will uphold a contract in whole and in every part is to be preferred, and the whole contract should be looked to in arriving at the construction of any part.” (Punctuation and footnote omitted.) Mattocks v. Matus, 266 Ga. 346, 349(1), 466 S.E.2d 840 (1996); see also OCGA § 13–2–2(4).

Contrary to Wedemeyer's contention, the Arbitration Agreement is not limited to disputes involving only applicants or current Gulfstream employees. Notably, the contract language at issue here unambiguously provides that the Arbitration Agreement applies to all employees who were employed by Gulfstream while the Arbitration Agreement or any version was in effect. There is no dispute that Wedemeyer was an employee when the contract was in effect. The contract language also provides that Gulfstream may elect to bypass one or more steps prior to arbitration for disputes with former employees. Moreover, covered claims include claims relating to involuntary discharge, i.e., claims brought by a former employee, not an applicant or current employee. Applying the tenets of contract construction as set forth above, it is clear that the Arbitration Agreement applies to disputes involving former Gulfstream employees.

2. Having decided that the Arbitration Agreement applies to former employees, we must next consider whether Wedemeyer's claims arise from his employment at Gulfstream.1 We conclude that they do.

[W]here parties have entered into a valid arbitration agreement, the trial court must determine whether the claims covered by the agreement are actually arbitrable before submitting them to an arbitrator. But in fulfilling this gatekeeping duty, the trial court shall not consider whether the claim with respect to which arbitration is sought is tenable nor otherwise...

To continue reading

Request your trial
9 cases
  • Emory Healthcare, Inc. v. Farrell
    • United States
    • Georgia Court of Appeals
    • June 2, 2021
    ...generally ... should apply ordinary state-law principles that govern the formation of contracts."); Wedemeyer v. Gulfstream Aerospace Corp. , 324 Ga. App. 47, 50 (1), 749 S.E.2d 241 (2013) ("Arbitration in Georgia is a matter of contract. As such, the construction of an arbitration clause i......
  • Emory Healthcare, Inc. v. Farrell
    • United States
    • Georgia Court of Appeals
    • June 2, 2021
    ...ordinary state-law principles that govern the formation of contracts." (punctuation omitted)); Wedemeyer v. Gulfstream Aerospace Corp. , 324 Ga. App. 47, 50 (1), 749 S.E.2d 241 (2013) ("Arbitration in Georgia is a matter of contract. As such, the construction of an arbitration clause in a c......
  • C.R. of Thomasville, LLC v. Hannaford
    • United States
    • Georgia Court of Appeals
    • April 5, 2022
    ...claims." Helms v. Franklin Builders , 305 Ga. App. 863, 865, 700 S.E.2d 609 (2010) ; accord Wedemeyer v. Gulfstream Aerospace Corp. , 324 Ga. App. 47, 49 (1), 749 S.E.2d 241 (2013) ("Arbitration is a matter of consent, not coercion ....") (citation and punctuation omitted).1. We first addre......
  • Norton v. United Health Servs. of Ga., Inc.
    • United States
    • Georgia Court of Appeals
    • March 2, 2016
    ...(2015), quoting Order Homes, LLC v. Iverson, 300 Ga.App. 332, 332–333, 685 S.E.2d 304 (2009) and Wedemeyer v. Gulfstream Aerospace Corp., 324 Ga.App. 47, 50(1), 749 S.E.2d 241 (2013).4 (Punctuation omitted.) DBGS, 333 Ga.App. at 35, 775 S.E.2d 283, quoting Genesco, Inc. v. T. Kakiuchi & Co.......
  • Request a trial to view additional results
1 books & journal articles
  • A Primer on Predispute Employment Arbitration Agreements
    • United States
    • State Bar of Georgia Georgia Bar Journal No. 20-1, August 2014
    • Invalid date
    ...Ga. 2004) affd 428 F.3d 1359 (11th Cir. 2005) (compelling arbitration of employment claims); Wedemeyer v. Gulfstream Aerospace Corp., 749 S.E.2d 241 (Ga. Ct. App. 2013)(discussing the enforceability of an arbitration agreement in the context of the employment relationship). [4] Circuit City......