Bishop Contracting Co., Inc. v. Center Bros., Inc.

Decision Date14 June 1994
Docket NumberNo. A94A0881,A94A0881
CourtGeorgia Court of Appeals
PartiesBISHOP CONTRACTING COMPANY, INC. v. CENTER BROTHERS, INC.

Varner, Stephens, Wingfield & Humphries, William W. Hopson, Dorothy H. Bishop, Atlanta, for appellant.

Tony Center, Atlanta, for appellee.

BLACKBURN, Judge.

This case involves a dispute between a general contractor, Bishop Contracting Company, Inc., and its subcontractor, Center Brothers, Inc., regarding the amount owed by Bishop to Center Brothers under a construction contract. Center Brothers brought the underlying action against Bishop to collect on six extra work orders. The jury returned a verdict in favor of Center Brothers for $8,510.68 as contract damages and $13,530.82 as expenses of litigation. Bishop appeals asserting several enumerations of error.

1. In its first enumeration of error, Bishop contends the trial court erred in denying its motion to enforce the arbitration clause of the construction contract. We agree.

The construction contract was an American Institute of Architects' (AIA) standard form agreement between contractor and subcontractor, and was entered on February 3, 1988. The contract provided that Center Brothers would perform all work required by the contract documents for "drywall, ceilings, acoustical wall panels, demountable partitions, and plaster." The contract further established procedures for changes or increases in the work and payment for such changes. Specifically, the contract required that Center Brothers, "prior to the commencement of such changed or revised Work, shall submit promptly to the Contractor written copies of any claim for adjustment to the Contract Sum and Contract Time for such revised Work in a manner consistent with the Contract Documents."

Of particular relevance to our inquiry, the contract established that "[a]ll claims, disputes and other matters in question arising out of, or relating to, this Subcontract, or the breach thereof, shall be decided by arbitration, which shall be conducted in the same manner and under the same procedures as provided in the Contract Documents with respect to disputes between the Owner and the Contractor, except that a decision by the Architect shall not be a condition precedent to arbitration. If the contract documents do not provide for arbitration or fail to specify the manner and procedure for arbitration, it shall be conducted in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining unless the parties mutually agree otherwise.... The award rendered by the arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof."

This contract is governed by former OCGA § 9-9-82 which provided "[a] written agreement to submit any existing controversy to arbitration or a provision in a written contract to submit any controversy thereafter arising to arbitration is enforceable and confers jurisdiction on the courts of the state to enforce it and to enter judgment on an award." Former OCGA § 9-9-86(a) provided that upon motion by an aggrieved party, the court shall compel arbitration of an issue upon its determination that the agreement to arbitrate was valid and that the claim was not barred by time limitations.

After the present action was filed in Cobb State Court, Bishop filed a motion to stay, pending arbitration. The court denied the motion and determined that...

To continue reading

Request your trial
8 cases
  • Langfitt v. Jackson
    • United States
    • Georgia Court of Appeals
    • 28 Marzo 2007
    ...to stay and compel arbitration does not waive the right to raise the issue on a final appeal. Bishop Contracting Co. v. Center Bros., Inc., 213 Ga.App. 804, 805(1), 445 S.E.2d 780 (1994). Accordingly, we find that the defendants' actions did not waive their right to 2. Turning to the issue ......
  • Wedemeyer v. Gulfstream Aerospace Corp.
    • United States
    • Georgia Court of Appeals
    • 27 Septiembre 2013
    ...required to uphold valid arbitration provisions in contracts[.]” (Citation and punctuation omitted.) Bishop Contracting Co. v. Center Bros., 213 Ga.App. 804, 805(1), 445 S.E.2d 780 (1994). “The standard of review from the denial of a motion to compel arbitration is whether the trial court w......
  • Atlanta Flooring Design Ctrs., Inc. v. R.G. Williams Constr., Inc.
    • United States
    • Georgia Court of Appeals
    • 16 Julio 2015
    ...provisions agreed upon by two commercial parties such as those before us in this case. See Bishop Contracting Co. v. Center Bros. Inc., 213 Ga.App. 804, 805(1), 445 S.E.2d 780 (1994) (upholding arbitration provision in contract between contractor and subcontractor). But this case also prese......
  • CHOATE CONST. v. Ideal Elec. Contractors, A00A1307.
    • United States
    • Georgia Court of Appeals
    • 2 Noviembre 2000
    ...appeal under OCGA § 5-6-34(b), the denial may also be appealed after final judgment. Bishop Contracting Co. v. Center Bros., Inc., 213 Ga.App. 804, 805-806(1), 445 S.E.2d 780 (1994). 2. In Choate's motion to dismiss or, in the alternative, to compel arbitration, it sought to enforce certain......
  • Request a trial to view additional results
1 books & journal articles
  • Construction Law - Brian J. Morrissey
    • United States
    • Mercer University School of Law Mercer Law Reviews No. 47-1, September 1995
    • Invalid date
    ...155. 215 Ga. App. at 439, 450 S.E.2d at 829. See O.C.G.A. Sec. 5-6-34(a)(4) (1995). 156. 215 Ga. App. at 439-40, 450 S.E.2d at 829. 157. 213 Ga. App. 804, 445 S.E.2d 780 (1994). 158. Id. at 804, 455 S.E.2d at 781. 159. Id. at 805-06, 445 S.E.2d at 782. 160. 215 Ga. App. 30, 449 S.E.2d 631 (......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT