Scales v. Southern Hotel Co.

Decision Date31 March 1866
Citation37 Mo. 520
PartiesTHOMAS H. SCALES, et al., Respondents, v. THE SOUTHERN HOTEL COMPANY, GARNISHEE, &c., Appellant.
CourtMissouri Supreme Court

Appeal from St. Louis Circuit Court.

The Southern Hotel Company was summoned as garnishee upon execution in favor of plaintiffs, of McBride & Thornburg (a firm composed of Joseph H. McBride and Joseph W. Thornburg), on November 13, 1862. At the return of the fi. fa., the plaintiffs filed fifteen special interrogatories to be answered by the garnishee, inquiring into all of the transactions between the garnishee and defendants. The defendants had been the contractors with the hotel company for doing the brick work of the hotel, and the contract had not been completed at the date of the garnishment. At the time of answering, the contract had been closed; the accounts of the defendants as against the garnishee, amounted to $44,318.67, and the account of the garnishee, for moneys paid and assumed and charged to defendants, amounted to $45,169.69, showing a balance against defendants of $845.02.

The sixth, seventh and eighth, interrogatories inquired, whether any moneys, orders, &c., had been paid since the date of the garnishment. To these the company answered that it had paid moneys to defendants, and their sub-contractors and workmen, in order to prevent liens being filed upon their building. They paid defendants, to be paid to workmen, the payment being thus applied and paid workmen, under superintendence of the agent of the company, November 29, 1862, $412.90; December 6, 1862, $67.55; making a total of $480.45.

In answer to the seventh interrogatory the company answered, that it had undertaken to see to the payment of the material men, and had paid for materials furnished to the building:

November 20, 1862, F. Walkenhorst, for brick,
$365 60
December 2, 1862, W. Stell, for sand,
78 00
December 4, 1862, H. Spelman, for brick,
56 00
December 4, 1862, J. H. Locke, for lime,
151 20
December 27, 1862, C. Best, for brick,
474 60
January 26, 1863, Plaintiffs, for brick,
544 00
$1,669 40
Making with the sum paid workmen,
480 45
Paid after the garnishment,

$2,149 85

Inquiry was made as to liens, none of which were filed or paid, except one, that of plaintiff, for $544.

The garnishee denied all indebtedness to defendants, and alleged that it had overpaid defendants. The replication alleged that the sum of $1,669.40 was illegally paid after garnishment, and alleged a general indebtedness. To this there was a rejoinder. At the trial the only dispute was as to the payments made after the date of the garnishment, November 13, 1862, and a draft of J. Thornburg accepted by defendant J. W. Thornburg in favor of the company, November 19, 1860, and payable out of the money due on the contract at its final payment. This draft was charged against defendant November 19, 1860. At the trial the garnishee offered in evidence to prove, that the persons to whom they paid money after the garnishment, the building not being completed, had the right to file liens upon the building, and also, that the company had agreed with defendants upon the resumption of work in 1862, that, to avoid liens, it would see to the payment of the material men and laborers, and that it had paid them all along upon orders and receipts of defendants. It also gave evidence tending to prove that both defendants assented to the acceptance of the Thornburg draft.

The plaintiff called the defendant J. H. McBride as a witness, to whom the garnishee objected because he was a party to the record, and a party for whose benefit the suit was prosecuted. The objection was overruled, exception taken and saved.

The garnishee objected to McBride testifying to any matters occurring prior to the garnishment, as he was the assignor of a chose in action, and incompetent. The objection was overruled, exception taken and saved.

The court, before whom the case was tried, found that all the payments made by the garnishee after the garnishment were made in its own wrong, and that it was indebted in the sum of $2,148.85, and ordered it to pay plaintiffs $1,034.13 and $38.05 costs. The garnishee filed its motion for a new trial, which being overruled and judgment given, it appealed.

Whittelsey, for appellant.

I. McBride was not a competent witness for plaintiffs.

a. He was a party to the record, in the same manner as if he had sued the garnishee himself. The record would be evidence against him He is but the cat's paw in the monkey's hands--R. C. 1855, p. 1577, § 6; Pratte v. Coffman, 33 Mo. 71; Patrick v. Steamboat Adams, 19 Mo. 73; Kanes v. Pritchard, 36 Mo. 135.

b. If not a party to the record, and the suit was not for his benefit, he must be considered as the assignor of a chose in action, incompetent to testify as to any facts occurring antecedent to the garnishment--R. C. 1855, p. 1577, § 6; Gardner v. Clark, 17 Barb. S. C. 548.

II. The court erred in its finding, that the garnishee paid the laborers and material men, after the garnishment, in its own wrong. There was no issue as to the fact of payment after garnishment. That was admitted. The building had not been complete at that time. The evidence showed that these parties could have filed their liens and enforced payment--Sess. Acts, 1857, p. 668, §§ 1, 2, 3 & 19. The garnishee could not equitably be required to wait until the liens were actually filed and litigated. The lien commenced with the building, and continued until thirty days after completion for laborers, and four months for material men. McBride and Thornburg were insolvent, as appears by the return that no property could be found to make the debt, as well as from the evidence. The creditor can have no greater right against the garnishee, than the defendant in the execution--Drake on Att. §§ 414-5, 677, 696; Firebaugh v. Stowe, 36 Mo. 111. By the mechanics' lien act, 1857, p. 668, § 19, after liens filed, the owner could withhold payment to the contrator. Is not his equity to refuse payment just as good when the contractor is insolvent, and he knows that he will be compelled to pay the material men and laborers, and he does pay them to avoid costs and litigation?

III. The defence, that he had by agreement with the contractors assumed these payments, having been declared as a matter of law against the garnishee, the point is made upon that finding, that the court...

To continue reading

Request your trial
27 cases
  • Goerss v. Indemnity Co. of America
    • United States
    • Missouri Court of Appeals
    • March 6, 1928
    ... ... Hoppe, 132 Mo.App. 458; Marz v. Big Horn Glass ... Co., 269 S.W. 700; Scales v. Southern Hotel ... Co., 37 Mo. 520; McPherson v. Railroad, 66 Mo ... 103; Fenton v ... ...
  • State ex rel. Indemnity Co. of America v. Daues
    • United States
    • Missouri Supreme Court
    • February 11, 1929
    ...v. Tyler, 38 Mo. 545; Johnson v. Pub, Co., 122 Mo. 104; Holker v. Hennessey, 143 Mo. 87; Marz v. Glass Co., 269 S.W. 700; Scales v. Southern Hotel Co., 37 Mo. 520; McPherson v. Railroad, 66 Mo. 103. (4) establishing the conflict of opinions it is not necessary that relator produce a "Grey-m......
  • State ex rel. Government Emp. Ins. Co. v. Lasky
    • United States
    • Missouri Court of Appeals
    • May 26, 1970
    ...A corresponding principle is that the indebtedness must be absolutely due as a money demand to be subject to garnishment. Scales v. Southern Hotel Co., 37 Mo. 520; Raithel v. Hamilton-Schmidt Surgical Co., supra; Reinhart v. Empire Soap Co., 33 Mo.App. 24. Thus it is a long established rule......
  • Ritter v. Boston Underwriters' Ins. Co.
    • United States
    • Kansas Court of Appeals
    • December 5, 1887
    ...v. Ins. Co., 11 Ins. Law Jour. 186; Ranson v. Hays, 39 Mo. 455; Waples on Attach. & Garnish. 341, 378; Herne v. Keath, 63 Mo. 84; Scales v. Hotel, 37 Mo. 520; Weil v. 38 Mo. 545; s. c., 43 Mo. 581; Lackland v. Garesché , 56 Mo. 267; Sheedy v. Bank, 62 Mo. 17. VII. The garnishee cannot be ma......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT