T.D.J. Development Corp. v. Conservation Com'n of North Andover

Decision Date26 May 1994
Docket NumberNo. 92-P-1094,92-P-1094
Citation36 Mass.App.Ct. 124,629 N.E.2d 328
PartiesT.D.J. DEVELOPMENT CORPORATION v. CONSERVATION COMMISSION OF NORTH ANDOVER & another. 1
CourtAppeals Court of Massachusetts

Joel B. Bard, Boston, for defendants.

Mark B. Johnson, Andover, for plaintiff.

Before DREBEN, KASS and PORADA, JJ.

PORADA, Justice.

Pursuant to the Wetlands Protection Act, G.L. c. 131, § 40, and the town's wetland protection by-law, chapter 178, the plaintiff filed a notice of intent with the conservation commission of North Andover for the filling of 250 square feet of bordering vegetative wetlands and the performance of work in the buffer zone adjacent to the wetlands in order to construct a roadway in its subdivision. The commission approved the work subject to forty-six conditions.

To a number of those conditions the plaintiff objected and filed an appeal with the Department of Environmental Protection (department) under G.L. c. 131, § 40. The plaintiff also lodged a complaint in the Superior Court for a declaratory judgment and for a review in the nature of certiorari of the commission's decision under the town's by-law. Upon review under § 40, the department issued a superseding order of conditions, eliminating the offending conditions, from which no appeal was taken. Cross motions for summary judgment were then filed in the Superior Court action. In granting summary judgment to the plaintiff, the judge ruled that the town's by-law was less stringent than the Wetlands Protection Act, and, thus, that the department's superseding order of conditions governed the project. The judge also ruled that, if he were in error in determining the relative stringency of the by-law and the act, the commission's imposition of two of its conditions (numbers 15 and 29) was arbitrary and capricious and, hence, invalid. A third condition (number 37) he found not to be unreasonable or arbitrary and capricious.

On appeal from the ensuing judgment entered in the Superior Court in favor of the plaintiff, the commission challenges only the judge's determination that the town's by-law is less stringent than the Wetlands Protection Act and the judge's denial as to three of the conditions imposed by the commission on the project, namely: (1) condition 15, a twenty-five foot no-cut and a fifty foot no-construction zone from the edge of the adjacent wetland resource areas, except for the approved wetland crossing and drainage discharge at the entrance of the subdivision; (2) condition 29, the placement of a filter fabric fence backed by a single row of staked hay bales between all construction areas and wetland areas; and (3) condition 37, the maintenance during the construction period of dumpsters outside the wetlands resource area for the storage and removal of waste generated by the construction. We discuss each of these claims.

1. The by-law. The Wetlands Protection Act, G.L. c. 131, § 40, "establishes minimum Statewide standards leaving local communities free to adopt more stringent controls." Golden v. Selectmen of Falmouth, 358 Mass. 519, 526, 265 N.E.2d 573 (1970). Lovequist v. Conservation Commn. of Dennis, 379 Mass. 7, 14-16, 393 N.E.2d 858 (1979). When a municipality adopts a by-law or ordinance that is consistent with the Wetlands Protection Act, but that imposes more stringent controls than the standards set by the Legislature, the local requirement trumps what is required under G.L. c. 131, § 40. Hamilton v. Conservation Commn. of Orleans, 12 Mass.App.Ct. 359, 368, 425 N.E.2d 358 (1981). DeGrace v. Conservation Commn. of Harwich, 31 Mass.App.Ct. 132, 135-136, 575 N.E.2d 373 (1991). Here, the commission acted both under § 40 and the town's by-law, c. 178-3A. 2 It is the commission's position that the by-law provides greater protection to wetlands in North Andover than the act. In determining whether the commission is correct, we focus only on those provisions of the by-law and act that relate to the three contested conditions. See Lovequist v. Conservation Commn. of Dennis, supra, 379 Mass. at 14-16, 393 N.E.2d 858.

The commission rests its argument on the ground that its by-law regulates all activity within the buffer zone, see § 178-3A, while the State regulations provide for regulation of activity in a buffer zone only if the activity will "alter" a wetland resource area, see 310 Code Mass.Regs. § 10.02(2)(b) (1989). This is a significant difference. Under the State regulations, a party is required to file a notice of intent for work in the buffer zone only when it has been shown that the work will alter a protected area. 310 Code Mass.Regs. § 10.02(2)(b) (1989). While the word "alter" under the State regulations is given an expansive definition, see 310 Code Mass.Regs. § 10.04 (1989), the regulation necessitates proof that an alteration of a wetlands protected area will occur and that the specific activity within the buffer zone will be the cause of the alteration. See Hollands, Comparison of Jurisdiction Between Local, State and Federal Wetland Laws and Regulations In Massachusetts from a Scientific View Point, in Regulation of Work in Massachusetts Wetlands and Floodplains 1, 9-10 (Mass.Continuing Legal Educ.1988). The town by-law, on the other hand, requires the filing of a notice of intent whenever work is to be performed in the buffer zone, without a showing that the work will have an impact on a wetland resource area. See note 2, supra. Consequently, the by-law's scope of control is more expansive than that of the act and eliminates the burden of proof problems associated with the State regulation.

The commission also argues that its by-law is more stringent than the act because it adds erosion control, sedimentation control, and recreation, § 178-1, 3 to the eight interests protected by the act, G.L. c. 138, § 40, and 310 Code Mass.Regs. § 10.01(2) (1989). By expanding the interests to be protected under the by-law, the commission may impose conditions which might not be permissible under the act. See Kreiger, Local Wetlands By-Laws and Hearings, in Wetlands, A Guide to Understanding a Complex Federal, State and Local Regulatory Scheme 39, 43 (Mass.Continuing Legal Educ.1991).

Insofar as the by-law regulates all activity performed in the buffer zone and provides for the protection of additional interests not covered by the act, the conservation commission was acting pursuant to a by-law which provided greater protection to the wetland resource areas than the act.

2. The challenged conditions. The judge determined that the imposition of the no-cut and no-construction limitation in the buffer zone and the requirement of a double siltation barrier were invalid conditions because they were "arbitrary, unreasonable or capricious, not grounded in evidence and therefore not supportable." He determined that the requirement of placement of dumpsters outside the wetland resource areas for the storage and removal of waste material was reasonable.

In reviewing his decision, the first issue to be addressed is the standard of review applicable to the plaintiff's complaint for relief in the nature of certiorari under G.L. c. 249, § 4. The standard of review varies according to the nature of the action for which review is sought. McSweeney v. Town Manager of Lexington, 379 Mass. 794, 800,...

To continue reading

Request your trial
103 cases
  • Overstreet v. Shoney's
    • United States
    • Court of Appeals of Tennessee
    • June 4, 1999
    ...(Ill. Ct. App. 1994); Fusaro v. First Family Mortgage Corp., 897 P.2d 123, 132 (Kan. 1995); T.D.J. Dev. Corp. v. Conservation Comm'n of N. Andover, 629 N.E.2d 328, 331-32 (Mass. Ct. App. 1994); Phillips v. Deihm, 541 N.W.2d 566, 571 (Mich. Ct. App. 1995); Bridge v. Karl's, Inc., 538 N.W.2d ......
  • City of Cambridge v. Civil Service Com'n
    • United States
    • Appeals Court of Massachusetts
    • August 5, 1997
    ...Howe v. Health Facilities Appeal Bd., 20 Mass.App.Ct. 531, 534, 481 N.E.2d 510 (1985). T.D.J. Dev. Corp. v. Conservation Commn. of N. Andover, 36 Mass.App.Ct. 124, 128-129, 629 N.E.2d 328 (1994). The city was hardly espousing a position devoid of reason when it held that a demonstrated will......
  • Mello Constr., Inc. v. Div. of Capital Asset Mgmt., 12–P–1429.
    • United States
    • Appeals Court of Massachusetts
    • December 18, 2013
    ...“there is no ground which ‘reasonable men might deem proper’ to support it.” T.D.J. Dev. Corp. v. Conservation Commn. of N. Andover, 36 Mass.App.Ct. 124, 128–129, 629 N.E.2d 328 (1994), quoting from Cotter v. Chelsea, 329 Mass. 314, 318, 108 N.E.2d 47 (1952). In denying Mello's application,......
  • Conservation Comm'n of Falmouth v. Pacheco
    • United States
    • Appeals Court of Massachusetts
    • February 7, 2000
    ...a "more expansive jurisdictional scheme" than that of 40 (which local communities are free to do, T.D.J. Dev. Corp. v. Conservation Commn. of N. Andover, 36 Mass. App. Ct. 124, 125-126 [1994]), by adding "wet meadows," "bogs," "vernal pools," "lands subject to flooding or inundation by grou......
  • Request a trial to view additional results
1 books & journal articles

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT