The Florida Companies v. Orange County, Fla., 81-450

Decision Date31 March 1982
Docket NumberNo. 81-450,81-450
Citation411 So.2d 1008
PartiesTHE FLORIDA COMPANIES, a Florida corporation, Appellant, v. ORANGE COUNTY, FLORIDA, Appellee.
CourtFlorida District Court of Appeals

Darryl M. Bloodworth and Lynn James Hinson of Dean, Mead, Egerton, Bloodworth, Capouano & Bozarth, P. A., Orlando, for appellant.

Karen A. Edwards, Asst. County Atty., Orange County Legal Dept., Orlando, for appellee.

COWART, Judge.

Appellant, The Florida Companies, appeals from an order of the circuit court denying certiorari to review Orange County's refusal to approve appellant's subdivision plat. Appellant contends that the county's refusal to approve the plan constitutes an unconstitutional taking of property, is barred by equitable estoppel and is an improper arbitrary and capricious exercise of the county's police power.

This action involved the county's disapproval of the plat for a subdivision known as "Greenhill Village." The plat was first submitted to the county in 1973 and the developers obtained preliminary approval at that time. The subdivision contained 327 lots and sewage treatment was accomplished by an on-site plant. A substantial amount of work was done on the subdivision, including seventy percent completion of the sewage treatment plant and installation of lines servicing approximately one-half the lots. However, before final approval and sale of the lots took place, the project was halted because of a slump in the land sales market. On May 6, 1976, Guardian Mortgage Investors, the mortgage lender on the subdivision project, foreclosed its mortgage and became fee simple owner of the land.

At the time of preliminary approval, section 6.2.7 of the Orange County Code provided that the final subdivision plans were to be submitted within one year of the preliminary approval. The section further provided that "the Board may void the preliminary plans if substantial work has not been accomplished within one (1) year after approval of such preliminary plans." On November 30, 1976, Hastings, the county "public works director," sent a letter to Guardian citing this section and stating that, in accordance with this section, "the Engineering approval for the subject project is hereby cancelled. It will be necessary for the plans to be resubmitted to this office for approval prior to commencing any construction on this project." On April 30, 1980, Guardian resubmitted the plat for preliminary approval, with minor changes. At the time of both submissions, approximately one-half the property was zoned R-1A and one-half was zoned R-1AA, permitting single family dwellings on 7500 square foot and 10,000 square foot lots, respectively.

Between the first and second submissions, Orange County had passed its "growth management policy." Section 3.1.1 of this policy provides that "Public or approved private central water and sewer systems should not be permitted in the Rural Service Area (including the property in question) until other appropriate urban services are available, or until the Board of County Commissioners determines that a public health hazard exists requiring a central water or sewer system." Based on this policy, the county commission denied approval of the subdivision plat, stating that sewage in the subdivision would have to be handled by septic tanks, which meant that the lots would have to be a minimum of one acre and that some of the lots would require elevation because of the high water table.

Guardian sought review of the county's decision by petition for certiorari, alleging that the county was equitably estopped from denying Guardian use of the sewage treatment plant, since the plant had been erected in reliance on the county's earlier approval and that the county's decision was arbitrary, unreasonable and capricious. 1 Appellant Florida Companies was substituted for Guardian. The circuit court denied certiorari, and Florida Companies appealed.

Appellant's contention that the county's refusal to approve a subdivision on its property only if septic tanks, rather than the existing treatment plant, are used constitutes a "taking" of its property by use of the police power without compensation and without due process of law was not raised in the appellant's petition for writ of certiorari in the circuit court. Consequently, this court cannot consider that issue.

Appellant's petition for writ of certiorari did allege that approximately $251,000 was disbursed by it to the developer, in reliance upon the preliminary subdivision plat approval, to finance construction of the sewage treatment plant and service lines. Appellant now contends that the county's 180 degree policy reversal would result in the complete loss of this investment and thus, since the investment was made in reliance upon the county's approval, the county should be estopped from denying appellant the right to use the treatment plant.

The doctrine of equitable estoppel may be invoked against a governmental body as if it were an individual. Hollywood Beach Hotel Co. v. City of Hollywood, 329 So.2d 10 (Fla.1976). This doctrine will preclude a municipality from exercising its police power to prohibit a particular use of land where:

(A) property owner (1) in good faith (2) upon some act or omission of the government (3) has made such a substantial change in position or has incurred such extensive obligations and expenses that it would be highly inequitable and unjust to destroy the right he acquired.

Hollywood Beach, 329 So.2d at 15-16.

Accord, Sakolsky v. City of Coral Gables, 151 So.2d 433 (Fla.1963); Jones v. First Virginia Mortgage and Real Estate Investment Trust, 399 So.2d 1068 (Fla.2d DCA 1981); Town of Largo v. Imperial Homes Corp., 309 So.2d 571 (Fla.2d DCA 1975). The facts of this case well demonstrate the elements of the doctrine as stated by the supreme court. The county preliminarily approved the subdivision plan, including the use of a package sewage treatment plant. In reliance on this approval, substantial expenditures were made in good faith to construct the plant and service lines.

The county argues that, since only preliminary approval of the subdivision plat was obtained, the developer was not justified in making expenditures until final approval had been obtained. Furthermore, it contends that preliminary approval was revoked under section 6.2.7 of the Orange County Code, providing that preliminary approval may be voided if substantial work has not been accomplished under the approval within one year. First, this alleged revocation cannot in itself affect the application of the doctrine of estoppel, because it occurred after the subject expenditures had been made. Second, the letter which allegedly revoked the preliminary subdivision approval was insufficient to do so because section 6.2.7 provides that preliminary approval can be voided by the board, while the letter was executed by the "public works director"; also, the letter only purports to cancel the "engineering approval" for the project.

The fact that the expenditures were made upon preliminary approval, rather than final approval, would likewise not affect the application of estoppel. In Sakolsky, the supreme court approved the application of estoppel where expenditures had been made upon tentative approval of preliminary plans. Furthermore, in Town of Largo v. Imperial Homes, estoppel was applied even though no building...

To continue reading

Request your trial
12 cases
  • Villas of Lake Jackson, Ltd. v. Leon County
    • United States
    • U.S. District Court — Northern District of Florida
    • 15 Junio 1992
    ...Commissioners of Metropolitan Dade County v. Lutz, 314 So.2d 815 (Fla. 3rd DCA 1975). See also The Florida Companies v. Orange County, Florida, 411 So.2d 1008, 1011 (Fla. 5th DCA 1982); City of North Miami v. Margulies, 289 So.2d 424 (Fla. 3rd DCA It is also noted that only preliminary appr......
  • Resolution Trust Corp. v. Town of Highland Beach
    • United States
    • United States Courts of Appeals. United States Court of Appeals (11th Circuit)
    • 19 Abril 1994
    ...the zoning authority is bound by its representations, whether they be in the form of words or deeds.... Florida Cos. v. Orange County, 411 So.2d 1008, 1011 (Fla. 5th D.C.A. 1982) (quoting Town of Key Largo v. Imperial Homes Corp., 309 So.2d 571, 573 (Fla. 2d D.C.A. 1975)). The record reveal......
  • SK Finance SA v. La Plata County, Bd. of County Com'rs
    • United States
    • United States Courts of Appeals. United States Court of Appeals (10th Circuit)
    • 1 Octubre 1997
    ...developer's reliance was sufficient to create a vested right to complete the project as planned. Similarly, in Florida Companies v. Orange County, 411 So.2d 1008 (Fla.App.1982), equitable estoppel came into play because the sewer treatment facilities were actually built in reliance on preli......
  • Monroe County v. New Port Largo, Inc., 84-946
    • United States
    • Court of Appeal of Florida (US)
    • 9 Abril 1985
    ...Odom v. Deltona Corp., 341 So.2d 977 (Fla.1976); see Daniell v. Sherrill, 48 So.2d 736 (Fla.1950); The Florida Companies v. Orange County, 411 So.2d 1008 (Fla. 5th DCA 1982). We have carefully examined the evidentiary points raised by the appellant and find either no error, no prejudice, se......
  • Request a trial to view additional results
1 books & journal articles
  • Property pieces in compensation statutes: law's eulogy for Oregon's measure 37.
    • United States
    • Environmental Law Vol. 38 No. 4, September 2008
    • 22 Septiembre 2008
    ...that necessary approvals will be forthcoming in due course, and he may safely proceed with the project"); Fla. Cos. v. Orange County, 411 So. 2d 1008, 1010 (Fla. Dist. Ct. App. 1982) (explaining that the doctrine of equitable estoppel will preclude a municipality from changing its regulatio......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT