Weber v. Eastern Idaho Packing Corp.

Decision Date01 May 1972
Docket NumberNo. 10692,10692
Citation496 P.2d 693,94 Idaho 694
PartiesLeo WEBER, Plaintiff-Respondent, v. EASTERN IDAHO PACKING CORPORATION, Inc., a corporation, and Anderson-Martin Farms, a co-partnership, Defendants-Appellants, and Dan Rietman, Defendant. W. H. CROFT and Glen Croft, dba Croft Construction, Plaintiff-Respondent, v. EASTERN IDAHO PACKING CORPORATION, a corporation, and Anderson-Martin Farma, a co-partnership, Defendants-Appellants, and Leo Weber, Defendant.
CourtIdaho Supreme Court
Herman E. Bedke, Burley, for appellant

William A. Parsons, Parsons & Smith, Burley, for respondent, Croft.

Donald J. Chisholm, Goodman, Duff & Chisholm, Rupert, for respondent, Weber.

McFADDEN, Justice.

These appeals come from two lien foreclosure actions which resulted in judgments for respondents Leo Weber and W. H. Croft and Glen Croft doing business as Croft Construction. The liens were filed to collect payment for subsoiling and rock removal operations on three adjoining parcels Respondents each conduct contract earth leveling and rock removal businesses. The owners of the land in question are Eastern Idaho Packing Corporation, owned by its president Dan Rietman, and Anderson-Martin Farms, a partnership. Rietman was authorized by these organizations to contract with third parties for the improvement of the 200 acres by ripping the topsoil and removing rocks, the goal being to make the land suitable for row crop farming.

of appellants' land totaling 200 acres located in Cassia County. The actions were consolidated and tried to an advisory jury which returned answers to interrogatories essentially favorable to respondents. Those answers were adopted as part of its findings by the district court.

In September, 1968, Weber met with Rietman at the latter's office where Rietman orally offered Weber the ripping and rock removal job. After a personal inspection of the land Weber accepted. Unfortunately, as the district court and its advisory jury found, the two men did not make a definite agreement 'with respect to the rate of compensation to be paid to Weber for the services.' Weber maintained he discussed the potential difficulties of the job and that their agreement was an hourly rate based on the type of equipment used; Rietman insisted he offered only.$7.00 per acre.

Problems were encountered due to the actual conditions of the subsurface of the land. Weber's own equipment proved too light to tear through the rocks inbedded in the subsurface hardpan, many being sizeable. Weber therefore contracted with W. H. Croft who was in the same business but owned heavier equipment, i. e. D-7 and D-8 type tractors with special ripping attachments. Croft supplied the D-7 tractor and driver for $14 per hour and charged $16 per hour for the D-8 tractor with driver. A total of $491.5 hours of actual work time was spent by all respondents.

They never completed the job. In October, 1968, Croft and Weber visited Rietman hoping to get a progress payment on the work. Rietman informed them he had no obligation to the Crofts and only owed Weber $7 for each acre that was actually worked. Respondents, apprehending the schism, ceased operations on October 25, 1968, and timely filed mechanics' liens to recover the reasonable value of their services.

The evidence at trial established the job was indeed a substantial undertaking. Experienced operators using very heavy equipment still encountered rugged, time consuming obstacles. Although respondents did not complete their work the record shows the ripping was completed and what remained was the burying of some rock. Rietman testified he expended $500 to finish the work.

The district court found that while the parties had not agreed on the price, Rietman had ordered the work performed and accepted the benefits. These factors support the conclusion that a contract could be legally implied and that the consideration could be determined using reasonable standards. The district court and the jury found the $14 and $16 hourly rates to be reasonable for the Crofts' claim and $1,352 for the work exclusively performed by Weber, who used different equipment. Judgment was entered for Weber against appellants for foreclosure of his lien in the amount of $1,352 against the 200 acres. Judgment was entered for foreclosure of the Crofts' lien for $6,251. Each also recovered interest, costs, and attorney fees. Additionally, in the event the proceeds of the sheriff's sale on foreclosure proved insufficient, the court ordered deficiency judgments to be entered personally against appellants.

Appellants have assigned eleven errors of the court in their appeal which may be grouped in three categories. Additionally there is before the Court respondents' contested motions for attorney fees on appeal.

ENFORCEABILITY OF THE WEBER-RIETMAN AGREEMENT

The facts of this case fit within the decisions of Fairchild v. Mathews, 91 Idaho 1, 415 P.2d 43 (1966), and Guyman v. Anderson, 75 Idaho 294, 271 P.2d 1020 (1954), where this Court allowed lien claimants to recover on the theory of quantum meruit for land leveling. The former case also concerned the failure of the parties to agree on the price to be paid for land leveling work and held that the district court properly resolved the dispute by allowing the workman to recover the reasonable value of his services performed on the defendant's land which were to defendant's benefit. In that case as in the present record, there was uncontroverted testimony from an impartial witness familiar with leveling work describing the prevailing rates charged for similar work. In the present case, the rates charged by respondents were at the lower end of the rate scale for the area.

Appellants' contention that there can be no lien as the jury found no 'contract' flies in the face of the record. The parties reached an agreement that respondent was to perform certain work. Appellants' agent, Mr. Rietman, apparently an experienced businessman, made daily inspections as the work progressed and observed the heavy equipment being operated. The court found that the work performed improved the land. Considering the number of days worked and the equipment utilized Mr. Rietman was at least put on notice that the rate of.$7.00 per acre was unreasonable, and that an inquiry on his part would have been appropriate.

In cases where one party has accepted valuable services under circumstances where he ought to pay, courts have implied a promise to pay and allowed recovery for the reasonable value of the services. Hixon v. Allphin, 76 Idaho 327, 281 P.2d 1042 (1955); Nagele v. Miller, 73 Idaho 441, 253 P.2d 233 (1953); Shurrum v. Watts, 80 Idaho 44, 324 P.2d 380 (1958). That reasoning is applicable to situations involving an attempt by a workman to recover for his services by the lien procedure. T. M. Deal Lumber Co. v. Vieux, 179 Kan. 760, 298 P.2d 339 (1956).

THE SUBCONTRACTOR'S LIEN

Appellants raise two contentions here: (1) that the amount of the subcontractor's lien cannot exceed the prime contractor's lien; and (2) that the subcontractor is not entitled to an in personam deficiency judgment under the lien statutes.

As to the amount of the Crofts' lien, appellants' contention that the lien cannot exceed the prime contractor's lien is without merit. The value of the prime contract was the reasonable value of the services performed. The total value of all work performed was determined to be $7,603. Weber could have filed his lien for this amount and upon recovery paid over the amount due the Crofts. However, the Idaho lien statute, I.C. § 45-501, permits a subcontractor to independently file his lien; the workman's classification is unimportant in this regard, for the purpose of the lien is to protect the one who expends his labor to improve the land. Hill v. Twin Falls Salmon River Land and Water Co., 22 Idaho 274, 125 P. 204 (1912). Chief Justice Stewart's statement in that case is still very relevant:

'Under the statute 1 the Legislature evidently intended to grant the right to claim a lien, to any person who contributes labor or material for the construction, alteration, or repair of a building or structure upon real property. It will also be observed from the language of this statute that it was clearly the intent of the Legislature to grant an absolute lien direct upon the property, to the person who performs labor * * * without We turn now to whether the subcontractor may obtain a deficiency judgment against the landowners. I.C. § 45-512 as...

To continue reading

Request your trial
10 cases
  • Pierson v. Sewell
    • United States
    • Idaho Supreme Court
    • August 8, 1975
    ...also awarded a personal judgment against the Sewells for any deficiency that might remain after the foreclosure sale. In Weber v. Eastern Idaho Packing Corporation, 18 the relevant provisions of I.C. § 45-512 19 were interpreted as allowing a lien claimant to treat that portion of the claim......
  • Barth v. Canyon County
    • United States
    • Idaho Supreme Court
    • May 23, 1996
    ...an obligation to pay. Gillette v. Storm Circle Ranch, 101 Idaho 663, 666, 619 P.2d 1116, 1119 (1980); Weber v. Eastern Idaho Packing Corp., 94 Idaho 694, 697, 496 P.2d 693, 696 (1972), overruled on other grounds by Pierson v. Sewell, 97 Idaho 38, 45, 539 P.2d 590, 597 (1975); Shurrum v. Wat......
  • Dale's Service Co., Inc. v. Jones
    • United States
    • Idaho Supreme Court
    • May 6, 1975
    ...247, 88 N.E. 835 (1909).7 91 Idaho 1, 5, 415 P.2d 43, 47 (1966).8 See Fairchild v. Mathews, supra n. 7; Weber v. Eastern Idaho Packing Corporation, 94 Idaho 694, 496 P.2d 693 (1972).9 See Cohen v. Delmer Drive-In Theatre, 7 Terry 427, 46 Del. 427, 84 A.2d 597 (1951); Chatfield v. Fish, 126 ......
  • Baker v. Boren
    • United States
    • Idaho Court of Appeals
    • March 21, 1997
    ...who have added directly to the value of the property of another by their materials or labor. Weber v. Eastern Idaho Packing Corp., 94 Idaho 694, 697-98, 496 P.2d 693, 696-97 (1972), overruled on other grounds by Pierson v. Sewell, 97 Idaho 38, 45, 539 P.2d 590, 597 At the time K.B.'s allege......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT