Wing v. Town of Landis

Full CitationWing v. Town of Landis, 165 N.C.App. 691, 599 S.E.2d 431 (N.C. App. 2004)
Decision Date03 August 2004
Citation599 S.E.2d 431,165 NC App. 691
Docket NumberNo. COA03-1021.,COA03-1021.
CourtNorth Carolina Court of Appeals
PartiesGuy F. WING d/b/a Franklin Homes Construction, Plaintiff, v. TOWN OF LANDIS, Defendant.

Ferguson, Scarbrough & Hayes, P.A., by James E. Scarbrough, Concord, for plaintiff-appellant.

Woodson, Sayers, Lawther, Short, Parrott & Walker, L.L.P., by Donald D. Sayers, Salisbury, for defendant-appellee.

GEER, Judge.

Plaintiff Guy F. Wing, d/b/a Franklin Homes Construction, appeals from the trial court's order granting summary judgment to defendant Town of Landis on plaintiff's quantum meruit claim for reimbursement of the cost of engineering plans for a water line extension. Because there was no showing that the plans were prepared in expectation of payment by the Town or that the Town received any benefit from the plans, plaintiff has failed to produce a forecast of evidence sufficient to establish each of the elements of his claim. The trial court, therefore, properly granted defendant's motion for summary judgment.

Facts

Early in 2001, plaintiff, a developer, sought to have municipal water service extended to serve an expansion of his Highland Woods development in the town of Landis. The Town informed plaintiff that the State's approval of any extension of service was contingent upon the Town's obtaining an additional water source from the City of Salisbury. The Town, however, agreed to apply to the N.C. Department of Environmental and Natural Resources ("DENR") for approval of an extension of its water service to Highland Woods. Plaintiff hired an engineer, at a cost of $22,469.00, to draft plans for the extension of service and to prepare an application for approval of the plans to be submitted to DENR. On 14 May 2001, the engineer submitted to DENR the completed application, signed by the Town's Mayor as required by DENR.

On 21 June 2001, DENR responded to the application by letter, requesting additional information prior to processing the application. The evidence is conflicting as to whether the Town's engineer or plaintiff's engineer was supposed to respond to DENR's request for additional information. In any event, neither responded.

Nevertheless, on 3 January 2002, DENR notified the Town that DENR would be able to approve expansion of the Town's water system since an "authorization to construct" letter had been issued to the City of Salisbury permitting it to supply additional water to the Town. When the Town's administrator called plaintiff's agent with the news, however, plaintiff's agent informed him that plaintiff no longer needed the water line extension. Plaintiff planned instead to construct community wells to serve the new homes. As a result, the water line extension has never been built.

On 5 August 2002, plaintiff filed a complaint alleging that by failing to respond to the State's requests for information, the Town breached its agreement to apply for approval of the application and, therefore, owed plaintiff $22,469.00 in reimbursement of plaintiff's cost in obtaining engineering plans for the water line extension. On 22 January 2003, the Town filed a motion for summary judgment, which the trial court granted in an order entered 20 May 2003. Plaintiff filed notice of appeal to this Court on 18 June 2003.

Standard of Review

Summary judgment shall be granted "if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that any party is entitled to a judgment as a matter of law." N.C.R. Civ. P. 56(c). The party moving for summary judgment has the burden of establishing the lack of a triable issue. Collingwood v. Gen. Elec. Real Estate Equities, Inc., 324 N.C. 63, 66, 376 S.E.2d 425, 427 (1989). The movant may meet this burden by showing that the opposing party cannot produce evidence to support an essential element of his claim or cannot surmount an affirmative defense that would bar the claim. Id. Once the moving party meets its burden, then the non-moving party must "produce a forecast of evidence demonstrating that [he] will be able to make out at least a prima facie case at trial." Id. In deciding the motion, all inferences of fact must be drawn against the movant and in favor of the party opposing the motion. Caldwell v. Deese, 288 N.C. 375, 378, 218 S.E.2d 379, 381 (1975).

On appeal, this Court's task is to determine whether, on the basis of the materials presented to the trial court, there is a genuine issue as to any material fact and whether the moving party is entitled to judgment as a matter of law. Oliver v. Roberts, 49 N.C.App. 311, 314, 271 S.E.2d 399, 401 (1980), cert. denied, 276 S.E.2d 283 (1981). A trial court's ruling on a motion for summary judgment is reviewed de novo because the trial court rules only on questions of law. Virginia Elec. & Power Co. v. Tillett, 80 N.C.App. 383, 384-85, 343 S.E.2d 188, 191, cert. denied, 317 N.C. 715, 347 S.E.2d 457 (1986).

Discussion

Plaintiff concedes that his agreement with the Town regarding the DENR application is unenforceable under N.C. Gen.Stat. § 160A-16 (2003), which provides that a contract made by or on behalf of a city is void and unenforceable unless it is in writing. See also Concrete Machinery Co. v. City of Hickory, 134 N.C.App. 91, 95, 517 S.E.2d 155, 157 (1999) (oral agreement to relocate sewer line unenforceable). Plaintiff contends on appeal, however, that he is entitled to recover his engineering costs under a theory of quantum meruit.

To recover in quantum meruit, a plaintiff must show that (1) services were rendered to the defendant; (2) the services were knowingly and voluntarily accepted; and (3) the services were not given gratuitously. Scott v. United Carolina Bank, 130 N.C.App. 426, 429, 503 S.E.2d 149, 152 (1998), disc. review denied, 350 N.C. 99, 528 S.E.2d 584 (1999). In addition, "[q]uantum meruit claims require a showing that both parties understood that services were rendered with the expectation of payment." Id. A party may recover from a municipality under a quantum meruit theory upon a proper showing.1 See e.g., Charlotte Lumber & Mfg. Co. v. City of Charlotte, 242 N.C. 189, 87 S.E.2d 204 (1955) (plaintiff could recover against city in quantum meruit); Hawkins v. Town of Dallas, 229 N.C. 561, 50 S.E.2d 561 (1948) (plaintiff could recover against town in quantum meruit); Orange Water & Sewer Auth. v. Town of Carrboro, 58 N.C.App. 676, 294 S.E.2d 757 (plaintiff could recover under an implied agreement in order to prevent the unjust enrichment of the town), disc. review denied, 307 N.C. 127, 297 S.E.2d 400 (1982).

In this case, plaintiff failed to present any evidence that the engineering plans were prepared with an expectation of payment by the Town. See also Twiford v. Waterfield, 240 N.C. 582, 585, 83 S.E.2d 548, 551 (1954) ("The plaintiff must show by the greater weight of the evidence that both parties, at the time the labor was done or the services were rendered, contemplated and intended that pecuniary recompense should be made for the same."). Plaintiff's evidence showed only that plaintiff, as the developer, hired and paid its own engineer to complete the engineering plans. There was no evidence that either party, at the time, expected the Town to reimburse plaintiff for the cost of the plans.

In addition, "[q]uantum meruit does not apply where no benefit accrues to the party from whom compensation is sought." Scott, 130 N.C.App. at 430-31, 503 S.E.2d at 152. See also Booe v. Shadrick, 322 N.C. 567, 570, 369 S.E.2d 554, 556 (1988) (internal citations omitted) ("[i]n order to establish a claim for unjust enrichment, a party must have conferred a benefit on the other party. The...

To continue reading

Request your trial
20 cases
  • Williams v. CITY OF JACKSONVILLE POLICE, COA03-1450.
    • United States
    • North Carolina Court of Appeals
    • August 3, 2004
  • Regency Centers Acquisition, LLC v. Crescent Acquisitions, LLC
    • United States
    • Superior Court of North Carolina
    • January 24, 2018
    ... ... were rendered with the expectation of payment.'" ... Wing v. Town of Landis , 165 N.C.App. 691, 693, 599 ... S.E.2d 431, 433 (2004) (quoting Scott v ... ...
  • Johnson v. Starboard Ass'n, Inc.
    • United States
    • North Carolina Court of Appeals
    • January 5, 2016
    ...River Equip., Inc. v. Tharpe's Excavating, Inc., 179 N.C.App. 336, 346, 634 S.E.2d 548, 556 (2006) (quoting Wing v. Town of Landis, 165 N.C.App. 691, 693, 599 S.E.2d 431, 433 (2004) ). Defendants cite no relevant legal authority which permits recovery in quantum meruit for costs unlawfully ......
  • M Series Rebuild, LLC v. Town of Mount Pleasant
    • United States
    • North Carolina Court of Appeals
    • August 7, 2012
    ...Carolina law provides for recovery against a municipality on a claim for unjust enrichment.2 Plaintiff relies on Wing v. Town of Landis, 165 N.C.App. 691, 599 S.E.2d 431 (2004), Charlotte Lumber & Manufacturing Co. v. City of Charlotte, 242 N.C. 189, 87 S.E.2d 204 (1955), and Hawkins v. Tow......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT