WASTE CONNECTIONS v. DEQ
Decision Date | 10 December 2002 |
Docket Number | No. 97,928.,97,928. |
Citation | 2002 OK 94,61 P.3d 219 |
Parties | WASTE CONNECTIONS, INC. d/b/a Red Carpet Landfill, Plaintiff/Appellant, v. OKLAHOMA DEPARTMENT OF ENVIRONMENTAL QUALITY, Defendant/Appellee. |
Court | Oklahoma Supreme Court |
Keith R. Gibson, Oklahoma City, OK, Jack Y. Perry & Lori J. Marco, Minneapolis, MN, for Waste Connections, Inc. d/b/a Red Carpet Landfill.
Stan A. Koop, Assistant Attorney General, Oklahoma City, OK, for the Department of Environmental Quality.
¶ 1 This appeal is the result of a June 13, 2002 order of the district court of Major County, in which the trial court dismissed Waste Connections', Inc. d/b/a Red Carpet Landfill (Waste Connections), request for declaratory judgment and injunctive relief, so that this case may proceed through the administrative process before the Department of Environmental Quality (DEQ). ¶ 2 The DEQ is a state agency charged with the administration of the Oklahoma Solid Waste Management Act, 27A O.S.2001, § 2-10-201, et seq. Waste Connections received a DEQ permit to operate its Meno, Oklahoma (Red Carpet Landfill) facility in September 2001. Shortly thereafter, the DEQ notified Waste Connections that it must submit a disposal plan under 27A O.S.2001, § 2-10-801(D)(1) before receiving any imported waste in excess of 200 tons per day.1 Waste Connections submitted a plan, but the DEQ refused to approve it, claiming it was inadequate. After conducting inspections of the landfill, the DEQ issued a notice of violations to Waste Connections, citing specific operational deficiencies as well as a lack of an acceptable disposal plan. On January 3, 2002, the DEQ issued an administrative compliance order, stating that Waste Connections failed to obtain a disposal plan prior to accepting imported waste in excess of 200 tons per day. The order further imposed daily fines.
¶ 3 The parties then scheduled an administrative appeal, which was continued at the request of the administrative hearing clerk. Prior to the rescheduled hearing, Waste Connections initiated suit against the DEQ in Major County, requesting a declaratory judgment, temporary restraining order and a temporary injunction. In its suit Waste Connections asserted, among other things that the rule, O.A.C. 252:205-3-2(c), did not apply to its landfill and both the rule and the statute, 27A O.S.2001, § 2-10-801(D)(1), are unconstitutional under the commerce clause of the U.S. Constitution.2
¶ 4 The DEQ moved to dismiss the cause for improper venue and failure to state a claim upon which relief could be granted. The trial court determined venue was appropriate in Major County, but dismissed Waste Connections' claim, because it failed to exhaust all administrative remedies prior to filing action in district court. In the order dismissing the claim the court determined it lacked jurisdiction to consider the matter in light of Waste Connections' failure to exhaust its administrative remedies.3
¶ 5 Waste Connections appealed the order dismissing its claim, asserting jurisdiction was proper.4 Waste Connections argued that its attack on the constitutionality of the statute, 27A O.S.2001, § 2-10-801(D), rendered it futile to proceed through the administrative process, because administrative agencies lack the power to determine the constitutionality of legislation. Waste Connections also asserted that it is entitled to bring a declaratory judgment action to determine the validity and application of an administrative rule, specifically O.A.C. 252:205-3-2(c), whether or not it requested the agency to pass upon the validity or applicability of the rule in question.
¶ 6 Waste Connections requested this Court retain this appeal. We retain this appeal to examine an apparent conflict between the trial court's decision and a number of recognized exceptions to the exhaustion of administrative remedies requirement.
975 P.2d at 887; Ledbetter, 764 P.2d at 180. Finally, exhaustion allows an administrative agency to compile a record which is adequate for judicial review. Moore v. City of East Cleveland Ohio, 431 U.S. 494, 524-25, 97 S.Ct. 1932, 52 L.Ed.2d 531 (1977); Harline v. Drug Enforcement Admin., 148 F.3d 1199, 1203 (10th Cir.1998).
¶ 8 In cases in which exhaustion of remedies is not required by statute, this Court has held that the requirement to exhaust administrative remedies is a prudential rule, rather than a jurisdictional bar. Walker, 37 P.3d at 761-62. The exhaustion rule "presents a remedial barrier to judicial proceedings when an agency's rule-prescribed administrative review process is not pursued to conclusion." Id. at 762. In such cases, the exhaustion requirement is discretionary with the court and may be excused if the administrative remedy is unavailable, ineffective or would have been futile to purse. Tinker Inv. & Mortgage Corp. v. City of Midwest City, 1994 OK 41, 873 P.2d 1029. When an administrative remedy is unavailable, ineffective or futile to pursue, the policy justifications for invoking the exhaustion of administrative remedies doctrine are no longer compelling.
¶ 9 The notion that an administrative process may be inadequate to fully and satisfactorily protect a right in question forms the basis of an exception to the doctrine of exhaustion of remedies for constitutional claims. The exception is a recognition that administrative agencies lack the power to pass on constitutional questions. Dow Jones & Co. Inc. v. State ex rel. Oklahoma Tax Comm'n, 1990 OK 6, 787 P.2d 843, 845 n. 9; Conoco, Inc. v. State Dept. of Health of State of Oklahoma, 1982 OK 94, 651 P.2d 125, 128-29. However, the exhaustion requirement is not excused merely because a party asserts a constitutional claim in a request for judicial relief. Ledbetter, 764 P.2d at 180. If relief may be granted on non-constitutional grounds, the necessity of deciding constitutional issues may be avoided and exhaustion may be required. Public Utilities Comm'n of the State of California v. U.S., 355 U.S. 534, 78 S.Ct. 446, 2 L.Ed.2d 470,rehearing denied by 356 U.S. 925, 78 S.Ct. 713, 2 L.Ed.2d 760 (1958). In Ledbetter, we recognized "where the situation involves the presence of constitutional questions, coupled with a sufficient showing of the inadequacy of the administrative process or remedy and of threatened or impending irreparable injury flowing from the delay that would be caused by following the administrative process[,]" administrative remedies need not be exhausted. Ledbetter, 764 P.2d at 180 (emphasis in original).
¶ 10 In addition, a plaintiff need not exhaust administrative remedies when the Administrative Procedures Act (APA) states that exhaustion is not required. Title 75 O.S.2001, § 306 of the APA provides an exception to the exhaustion rule. Section 306 provides that the validity or applicability of a rule may be determined in an action for declaratory judgment if it is alleged that "the rule, or its threatened application, interferes with or impairs . . . the legal rights or privileges of the plaintiff." 75 O.S.2001, § 306(A). Section 306(D) specifically provides that the "declaratory judgment may be rendered whether the plaintiff has requested the agency to pass upon the validity or applicability of the rule in question."
¶ 11 A declaratory judgment under § 306 of the APA is not available for review of an adjudication effected in the course of a judicial proceeding. Texas Co. Irrigation & Water Resources Ass'n v. Oklahoma Water Resources Bd., 1990 OK 121, 803 P.2d 1119, 1123. In differentiating between rules and adjudications, Oklahoma Courts have explained the difference between an administrative rule and an administrative adjudication.
An agency's authority to make rules is clearly distinguishable from that of adjudication. Rulemaking includes the power to adopt rules and regulations of general application—both substantive and procedural—which are legislative in nature, operate prospectively and have general application. Orders of an administrative body are adjudicative in character. They apply to named persons or specific situations and have immediate rather than future operation.
Harry R. Carlile Trust v. Cotton Petroleum Corp., 1986 OK 16, 732 P.2d 438, 441-42 (emphasis in original). Section 306 is intended to apply only to rules issued by an agency in its quasi-legislative function and not to...
To continue reading
Request your trial-
State ex rel. Okla. State Bd. of Med. Licensure & Supervision, v. Rivero
...constitutionality of a statute by asserting a facial challenge, an as-applied challenge, or both.").30 Waste Connections, Inc. v. Oklahoma Dept. of Environmental Quality , 2002 OK 94, ¶ 9, ¶ 10, 61 P.3d 219, 223 (administrative process may be inadequate to fully and satisfactorily protect a......
-
Trant v. Oklahoma
...remedies). Exhaustion of administrative procedures is a prudential doctrine when not statutorily required. Waste Connections, Inc. v. Okla. Dep't of Envtl. Quality, 2002 OK 94, ¶ 8, 61 P.3d 219, 223. Additionally, “ ‘[d]eclaratory relief may not be invoked as a substitute for an appeal by o......
-
Osage Nation v. Bd. of Comm'rs of Osage Cnty.
...judge's powers in equity are not invocable when clear and adequate statutory remedies are available"); Waste Connections, Inc. v. Oklahoma Dept. of Environment al Quality, 2002 OK 94, ¶ 9, 61 P.3d 219 (adequacy of an alternative remedy will depend on whether that remedy provides an opportun......
-
Hedrick v. Comm'r of the Dep't of Pub. Safety
...¶ 7, 158 P.3d 461, 464. 32.Atkinson v. Halliburton Co., 1995 OK 104, 905 P.2d 772, 774–775. 33.See, e.g., Waste Connections, Inc. v. Oklahoma Dept. of Environmental Quality, 2002 OK 94, ¶ 9,61 P.3d 219, 223 (an administrative agency lacks power to adjudicate a legal issue presenting a const......